HomeMy WebLinkAboutR-2025-065 Bermelo Ajamil Amendment No. 2 - CW Thomas Park ImprovementsRESOLUTION NO. 2025-065
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA, AUTHORIZING THE PROPER CITY OFFICIALS TO
EXECUTE A SECOND AMENDMENT TO EXISTING AGREEMENT
BETWEEN THE CITY AND BERMELLO AJAMIL AND PARTNERS TO
EXTEND CONSTRUCTION ADMINISTRATION SERVICES THROUGH
JANUARY 31, 2026, WHICH SERVICES SHALL NOT EXCEED THE
AMOUNT OF ONE HUNDRED TWENTY-SIX THOUSAND NINE HUNDRED
AND FORTY-SEVEN DOLLARS ($126,947.00); PROVIDING FOR
CONFLICTS; FURTHER, PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, City officials adopted Resolution 2022-062 to execute an agreement with
Bermello Ajamil and Partners for the Design and Construction Administration Services of the CW
Thomas Park, Park Improvements on April 26, 2022; and
WHEREAS, the agreement was executed with Bermello Ajamil and Partners on May 6,
2022; and
WHEREAS, the initial agreement estimated the construction to be complete by April 15,
2024 and the construction administration and professional services lasting for 365 from the kickoff
of the construction of the project; and
WHEREAS, the City is requesting approval of the second amendment to the agreement
with Bermello Ajamil and Partners extending their agreement for design and construction
administration services through January 31, 2026; and
WHEREAS, additional funding is needed in the amount of One Hundred Twenty-Six
Thousand Nine Hundred and Forty-Seven Dollars ($126,947.00); and
WHEREAS, the Parks and Recreation Department recommends that the City Commission
approval the additional funding and the second amendment to the agreement extending design and
construction administration services through January 31, 2026.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF DANIA BEACH, FLORIDA:
Section 1. That the above “Whereas” clauses are ratified and confirmed, and they are
made a part of and incorporated into this Resolution by this reference.
Section 2. That all resolutions or parts of resolutions in conflict with this Resolution
are repealed to the extent of such conflict.
2 RESOLUTION #2025-065
Section 3. That the proper City officials are authorized to execute an Amendment to
the Agreement for Design and Construction Administration Services between the City and
Bermello Ajamil and Partners through January 31, 2026, in the amount of One Hundred Twenty-
Six Thousand Nine Hundred and Forty-Seven Dollars ($126,947.00), which Amendment is
attached as Exhibit “A” and is incorporated into this Resolution by this reference.
Section 4. That a budgetary transfer will be needed in the amount of $126,947.00 from
Account Number 001-72-01-572-46-50 - Repair & Maint. Services Grounds to Account Number
302-72-03-572-31-10 – Prof. Services General.
Section 5. That all resolutions or parts of resolutions in conflict with this Resolution
are repealed to the extent of such conflict.
Section 6. That this Resolution shall be effective 10 days after passage.
PASSED AND ADOPTED on May 13, 2025.
Motion by Commissioner Lewellen, second by Commissioner Ryan.
FINAL VOTE ON ADOPTION: Unanimous X
Yes No
Commissioner Lori Lewellen ____ ____
Commissioner Luis Rimoli ____ ____
Commissioner Archibald J. Ryan IV ____ ____
Vice Mayor Marco Salvino ____ ____
Mayor Joyce L. Davis ____ ____
ATTEST:
ERIN MCCLENDON JOYCE L. DAVIS
DEPUTY CITY CLERK MAYOR
APPROVED AS TO FORM AND CORRECTNESS:
EVE A. BOUTSIS
CITY ATTORNEY
Page 1 of 2
April 16, 2025
CITY OF DANIA BEACH
AMENDMENT No. 2 ADDITIONAL SERVICES REQUEST
C.W. THOMAS PARK IMPROVEMENTS EXTENDED CONSTRUCTION ADMINISTRATION SERVICES
Please accept this Scope of Work Amendment Request from Bermello Ajamil & Partners, LLC. (BA) to provide
Extended Construction Administration Services to the City of Dania Beach (City) for the C.W. Thomas Park
construction work. This request and associated work shall be prepared and completed in accordance with
“Agreement Between the City of Dania Beach, Florida and Bermello Ajamil & Partners for Design Services
Related to New Construction for Improvements at C.W. Thomas Park as Further Described in the City’s Request
for Qualifications (RFQ) No. 22-001”, dated May 6, 2022.
PART I - PROJECT BACKGROUND AND WORK DESCRIPTION:
In the original Scope of Services, noted above, the Construction Administration duration and professional services
are noted as lasting for 365 days. After execution of the Original professional design services scope and fee, and
well into the design process, a Construction Manager at Risk (CM) was retained by the City. Due to the
improvement’s logistical requirements, the CM determined and dictated that construction would take 548 days; a
six-month extension of construction from BA’s Original Agreement with the City. BA is submitting this amendment
request for the additional six months of construction administration work required above and beyond the Original
Agreement. This work shall include participation in additional Owner Architect City (OAC) Meetings, review of
additional contractor pay applications, performing additional site visits, review and responses to additional RFI’s
and preparation of additional permit revisions. Barring actions or changes beyond BA’s control such as additional
major changes to the project schedule or duration, supply chain or product and material availability problems,
major design change requests and complicated substitution negotiations, BA anticipates this amendment being
sufficient to complete the project in January 2026. Therefore, unless there are actions or changes outside of BA's
control as mentioned above, no additional fee for BA's extended construction administration services shall be
charged to the City.
This Amendment further requests to extend the duration of the Agreement between the City and BA from April
15, 2024 to January 31, 2026.
Assisting BA Landscape Architecture and Architecture with these services shall be the following firms:
CSA Group, Inc. Civil Engineering
MUEngineers, Inc. Structural Engineering
Hammond & Associates Mechanical, Electrical, Plumbing and Low-Voltage Engineering
Aquatic Design Group Aquatic Engineering
Kenneth DiDonato Irrigation Design
C.W. Thomas Park Improvements Page 2 of 2
City of Dania Beach, Florida
Amendment No. 2 Additional Services Request – Extended Construction Administration Services
April 16, 2025
PART II – SCOPE OF WORK:
TASK 13.0 – EXTENDED CONSTRUCTION ADMINISTRATION SERVICES
13.1 Extended Construction Administration Services – BA shall participate in thirteen (13) additional OAC
meetings, review and return six (6) additional contractor pay applications, prepare, coordinate and track
two (2) additional building department permit revisions, review and respond to contractor RFI’s and
perform up to six (6) additional site visits.
Deliverables for Task 13.0 Extended Construction Administration Services – As a result of this task, BA shall
deliver the following:
- 8 1/2” X 11” black and white PDFs of RFI responses
- 24” X 36” black and white signed and sealed Delta revised Permit Drawings
- Six (6) 8 ½” X 11” black and white PDFs of Reviewed Pay Applications
PART III – COMPENSATION:
BA shall bill the City lump sum fees, including all direct expenses, for added Task 13.0 as follows:
TASK 13.0 – EXTENDED CONSTRUCTION ADMINISTRATION SERVICES .................................... $126,947.00
TOTAL .................................................................................................................................................. $126,947.00
PART IV – SERVICES NOT INCLUDED:
The following design, production, coordination, studies, permitting, tasks or services are not included in this Scope
and shall be provided by BA as an additional service for an agreed to fee:
1. Any work or request not expressly included in this Amendment Request or the Original Agreement