HomeMy WebLinkAboutR-2009-020 Authorizing the Proper City Officials to Increase Funding Related to the Existing Contract with Frank Hill Constructions, Inc.RESOLUTION 2009-020
A RESOLUTION OF THE CITY COMMISSION OF THE CITY DANIA
BEACH, FLORIDA, AUTHORIZING THE PROPER CITY OFFICIALS TO
INCREASE FUNDING RELATED TO THE EXISTING CONTRACT WITH
FRANK HILL CONSTRUCTION, INC. FOR THE CONSTRUCTION OF THE
DANIA BEACH MARINA RESTROOMS BY THE AMOUNT OF $9,800.00;
PROVIDING FOR CONFLICTS; PROVIDING FOR FUNDING; FURTHER,
PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the City awarded a contract pursuant to Resolution No. 2006-227 on
December 12, 2006 to Frank Hill Construction, Inc. to design, rehabilitate and construct the
Dania Beach Marina Restrooms; and
WHEREAS, a contract between the City of Dania Beach and Frank Hill Construction,
Inc. was executed on January 23, 2007 for the project in the amount of $218,700.00; and
WHEREAS, the contract was increased by $26,568.00 in change orders to date; and
WHEREAS, the City desires to make modifications for the betterment of the use of the
Marina Restrooms which modifications have a total cost in the amount of $4,550.00 as detailed
in Change Order No. 5 in the document attached as "Exhibit A"; and
WHEREAS, the budget approved for this project is $269,050.00, funded from the
General Obligation Bond;
NOW, THEREFORE, BE IT RESOVED BY THE CITY COMMISSION OF
THE CITY OF DANIA BEACH, FLORIDA:
Section 1. That the proper City officials are authorized to execute Change Order No.
5 to the contract with Frank Hill Construction, Inc. for the Dania Beach Marina Restrooms
Project in the exact amount of Nine Thousand Eight Hundred Dollars ($9,800.00) for work
described in Exhibit "A" which is attached.