HomeMy WebLinkAbout2023-11-14 CRA Board Regular Meeting Agenda PacketAGENDA
COMMUNITY REDEVELOPMENT AGENCY
REGULAR MEETING
TUESDAY, NOVEMBER 14, 2023 - 5:30 PM
ANY PERSON WHO DECIDES TO APPEAL ANY DECISION MADE WITH REGARD TO ANY MATTER CONSIDERED AT THIS
MEETING OR HEARING WILL NEED A RECORD OF THE PROCEEDING, AND FOR SUCH PURPOSE MAY NEED TO ENSURE
THAT A VERBATIM RECORD OF THE PROCEEDING IS MADE WHICH RECORD INCLUDES THE TESTIMONY AND EVIDENCE
UPON WHICH THE APPEAL IS TO BE BASED.
LOBBYIST REGISTRATION IS REQUIRED. PRIOR TO ENGAGING IN ANY LOBBYING ACTIVITIES, WHETHER OR NOT
COMPENSATION IS PAID OR RECEIVED IN CONNECTION WITH THOSE ACTIVITIES, EACH LOBBYIST SHALL FILE WITH THE
CITY CLERK AN ANNUAL REGISTRATION STATEMENT AND PAY AN ANNUAL TWO HUNDRED FIFTY DOLLARS ($250.00)
REGISTRATION FEE FOR EACH PRINCIPAL OR EMPLOYER. REGISTRATION FORMS ARE AVAILABLE ON THE CITY WEBSITE:
WWW.DANIABEACHFL.GOV. (ORDINANCE #2012-019; AMENDED BY ORDINANCE #2019-019)
IN ACCORDANCE WITH THE AMERICANS WITH DISABILITIES ACT, PERSONS NEEDING ASSISTANCE TO PARTICIPATE IN
ANY OF THESE PROCEEDINGS SHOULD CONTACT THE CITY CLERK'S OFFICE, 100 W. DANIA BEACH BOULEVARD, DANIA
BEACH, FL 33004, (954) 924-6800 EXTENSION 3624, AT LEAST 48 HOURS PRIOR TO THE MEETING.
IN CONSIDERATION OF OTHERS, WE ASK THAT YOU:
A. PLEASE TURN CELL PHONES OFF, OR PLACE ON VIBRATE. IF YOU MUST MAKE A CALL, PLEASE STEP OUT INTO THE
ATRIUM, IN ORDER NOT TO INTERRUPT THE MEETING.
B. IF YOU MUST SPEAK TO SOMEONE IN THE AUDIENCE, PLEASE SPEAK SOFTLY OR GO OUT INTO THE ATRIUM, IN
ORDER NOT TO INTERRUPT THE MEETING.
DECORUM POLICY FOR MEETINGS OF THE BOARD OF DIRECTORS OF THE DANIA BEACH COMMUNITY
REDEVELOPMENT AGENCY OF THE CITY OF DANIA BEACH, FLORIDA:
INDIVIDUALS WHO WISH TO MAKE ANY “CITIZEN’S COMMENTS” UNDER THAT PORTION OF THE CRA BOARD AGENDA,
OR WHO OTHERWISE WANT TO ADDRESS THE CRA BOARD, MUST FIRST BE REGISTERED WITH THE CRA SECRETARY
(CLERK) (FORMS ARE AVAILABLE OUTSIDE OF THE CITY COMMISSION CHAMBER AND MUST BE GIVEN TO THE CLERK
BEFORE THE MEETING). OTHERS WHO WANT TO ADDRESS THE CRA BOARD ON ANY MATTERS MUST FIRST BE
RECOGNIZED BY THE CHAIR. ALL SUCH PERSONS MUST USE THE PODIUM IN THE COMMISSION CHAMBER. NO MORE
THAN ONE PERSON AT A TIME MAY ADDRESS THE CRA BOARD FROM THE PODIUM. COMMENTS ARE ONLY TO BE MADE
TO THE CRA BOARD AND ARE NOT TO BE DIRECTED TO THE AUDIENCE OR CRA STAFF.
NO INDIVIDUAL SHALL MAKE ANY SLANDEROUS OR UNDULY REPETITIVE REMARKS, OR ENGAGE IN ANY OTHER FORM
OF BEHAVIOR THAT DISRUPTS OR IMPEDES THE ORDERLY CONDUCT OF THE MEETING, AS DETERMINED BY THE CHAIR.
NO INDIVIDUAL MAY SPEAK DIRECTLY TO OR ADDRESS THE CHAIR, BOARD MEMBER OR CRA STAFF: COMMENTS ARE TO
BE ONLY DIRECTED TO THE CRA BOARD AS A WHOLE. NO CLAPPING, APPLAUDING, HECKLING OR VERBAL OUTBURSTS
IN SUPPORT OF OR OPPOSITION TO A SPEAKER OR HIS OR HER REMARKS SHALL BE PERMITTED. NO SIGNS OR PLACARDS
SHALL BE PERMITTED IN THE COMMISSION CHAMBER.
IF ANY PERSON’S CONDUCT AS DETERMINED BY THE CHAIR IS FOUND TO BE DISRUPTIVE OR INTERFERES WITH THE
ORDERLY CONDUCT OF THE MEETING, THE PERSON MAY BE ASKED BY THE CHAIR TO LEAVE THE COMMISSION
CHAMBER; IF THE PERSON DOES NOT LEAVE AND THE CONDUCT PERSISTS, THE CITY POLICE DEPARTMENT WILL BE
REQUESTED TO ESCORT THE INDIVIDUAL FROM THE COMMISSION CHAMBER.
ALL CELLULAR TELEPHONES ARE TO BE SILENCED DURING THE MEETING. ALL PERSONS EXITING THE COMMISSION
CHAMBER SHALL DO SO QUIETLY. (RESOLUTION #2020-CRA-006)
1. CALL TO ORDER/ROLL CALL
2. CITIZEN COMMENTS
Addressing the Commission: A thirty (30) minute "Citizen Comments" period shall be designated on the agenda for citizens and interested
persons to speak on matters whether or not scheduled on that day's agenda. Individuals wishing to speak on a matter not included on the
"Public Hearing" section of the agenda, which matter pertains to an item before the City Commission which requires a decision of the City
Commission, may do so by signing in and submitting a form to that effect with the City Clerk prior to the meeting. Speakers at Public
Hearings shall also submit such a form. Each speaker shall be limited to 3 minutes for his or her comments. If more than ten (10) speakers
express a desire to speak, the Commission shall determine on a meeting by meeting basis whether to (a) extend the time allotted for citizen
comments to accommodate all speakers, or (b) whether to limit the number of speakers or amount of time per speaker. A speaker's time
shall not be transferable to another speaker.
3. ADMINISTRATIVE REPORTS
Agenda – Community Redevelopment Agency
Tuesday, November 14, 2023 - 5:30 PM
Page 2 of 2
1. Administrative Report - Executive Director Chen
4. PRESENTATIONS: None.
5. CONSENT AGENDA
1. Minutes: October 10, 2023 Regular Board Meeting
2. Travel Requests: None.
6. PROPOSALS AND BIDS: None
7. DISCUSSION AND POSSIBLE ACTION
1. Dania Beach Clean Energy Industrial Park
2. Commercial Façade Grant – 225 SW 2nd Ter
3. Discussion and Approval of 2024 CRA Meeting Dates - City Clerk
8. BOARD MEMBER COMMENTS
9. INFORMATION ITEMS
10. ADJOURNMENT
City of Dania Beach
Memorandum
DATE: 11/14/2023
TO: Chair and Board Members
FROM: Michael Chen, Executive Director
SUBJECT: Administrative Report
1. DANIA BEACH INNOVATION ECOSYSTEM
Background: An Innovation Ecosystem has many different platforms to support
entrepreneurs and early-stage ventures. The Dania Beach Innovation Ecosystem includes:
• Education
• Location & Events
• Mentorship
• Incubation & Acceleration
• Funding
• Talent
Update: We have worked with SCORE to provide a new Dania Beach Business Academy
program – “REVENUE GENERATION” (flyer attached). The focus of the program is to
teach our businesses how to generate more revenue. This program was promoted through
city/CRA networks and the CRA network at AERO Partners. The dates and class topics were
as follows:
Thu, Oct 12: Branding 101
Thu, Oct 19: A.I. Content Generator - How to Use AI in Your Marketing
Thu, Oct 26: Build & Improve Social Media Presence: Facebook, Instagram, YouTube,
and Google
Thu, Nov 2: Upselling Strategies - Sell More, Make More
Every class in our 4-part series had over 100 participants and the third class had 174
participants. This reflects the highest attendance of any Academy series to date.
2. HABITAT FOR HUMANITY BROWARD
At the October 10th CRA Meeting, the Board approved sale of the property located at 608
West Dania Beach Boulevard (Folio No. 5042 34 01 2520) to Habitat For Humanity Broward
(Habitat) by Resolution 2023-CRA-013, for development as a for-sale, multi-unit townhouse
project as low-income affordable housing (80% AMI) and/or workforce affordable housing
(120% AMI).
The CRA has provided a draft of a sales contract and Restrictive Covenants to Habitat for
review. Habitat has requested a condition that would reflect a material change to their
response as discussed with the Board on October 10th. The CRA has requested Habitat to
further evaluate their request and, if necessary, make a formal proposal. Once the CRA
receives a defined request, we will bribg the subject back to the Board for your consideration.
3. GREATER FT LAUDERDALE ALLIANCE
The Greater Ft. Lauderdale Alliance Annual Meeting was on Thursday, October 19, at the
Signature Grand. The Mayor and several Commissioners were able to attend. Also joining
the CRA table was Mary Partin, CEO of the Dan Marino Foundation, and J. Chris Ford,
Ph.D., Principal Scientist of the FIU Applied Research Center and our IP2Mkt Incubator
manager.
4. FLORIDA REDEVELOPMENT ASSOCIATION
Attended the Florida Redevelopment Association (FRA) Annual Conference on October 25-
26, at Ponte Vedra Beach, FL. Some of the presentations I found most interesting were:
• Adaptive Reuse - Regulatory Frameworks, Sensitive Design
• Community Placemaking Strategies - preserve the character of your communities
• Creative Strategies for Public Art – Arts Plan, Arts Board. places for public art,
• Affordable Housing Partnerships – contribute land cost and local subsidies
• Hot Legal Topics - Live Local Act, CRA events
DANIA BEACH COMMUNITY REDEVELOPMENT AGENCY
REGULAR MEETING MINUTES
TUESDAY, OCTOBER 10, 2023 – 5:30 P.M.
1. Call to Order/Roll Call
Chair Ryan called the meeting to order at 5:30 p.m.
Present:
Chair: A. J. Ryan IV
Vice-Chair: Lori Lewellen *arrived at 5:37 p.m.
Board Members: Joyce L. Davis
Tamara James
Marco A. Salvino, Sr.
Executive Director: K. Michael Chen
City Attorney: Eve Boutsis
CRA Secretary: Elora Riera, MMC
2. Citizen Comments
None.
3. Administrative Reports
Executive Director Chen presented his administrative report that was provided to the Board in
their packets. He touched on the following topics:
- SkySpaces has received their Certificate of Occupancy. On October 5th, the CRA hosted
an informal open house for the CRA Board and senior city staff to do a tour of the co-
working space.
- CRA participated at the 2023 Florida International Trade and Cultural Expo (FITCE) on
October 4th & 5th at the Convention Center. FIU co-manned the table to talk about the
Incubator and take applications for the next Incubator cohort.
- Mary Partin, CEO of the Dan Marino Foundation, continues to explore areas for
collaboration with the CRA and the FIU IP2Mkt Incubator.
*Vice Chair Lewellen arrived at this time.
- Worked with SCORE to provide a new Dania Beach Business Academy program
- CRA Board workshop for the West 1st Avenue Visioning Plan
Minutes of Regular Meeting
Dania Beach Community Redevelopment Agency
Tuesday, October 10, 2023 – 5:30 p.m.
2
- Greater Ft Lauderdale Alliance Annual Meeting is on Thursday, October 19th
- Florida Redevelopment Association (FRA) Annual Conference will be held October 25-
26
- The Smart Growth Partnership is a collaborative of diverse professionals and
organizations providing leadership, advocacy, and education to promote livable,
sustainable and green communities for the South Florida region. The Smart Growth
Partnership Annual Forum will be held on November 2nd and Commissioner Davis will
be a speaker at the conference, discussing the development of affordable housing.
4. Presentations
None.
5. Consent Agenda
5.1 Minutes:
- September 13, 2023 Regular CRA Board Meeting
- September 20, 2023 CRA Workshop Meeting
Board Member James made a motion to approve the consent agenda. Vice Chair Lewellen
seconded the motion which carried unanimously on voice vote.
6. Proposals and Bids
There were no proposals on this agenda.
7. Discussion and Possible Action
7.1 RESOLUTION NO. 2023-CRA-
A RESOLUTION OF THE BOARD OF DIRECTORS OF THE COMMUNITY
REDEVELOPMENT AGENCY (“CRA”) OF THE CITY OF DANIA BEACH,
FLORIDA, AUTHORIZING HABITAT FOR HUMANITY AS THE SUCCESSFUL
PROPOSER UNDER RFP CRA-2023-018; AND AUTHORIZING THE
APPROPRIATE CITY OFFICIALS TO EXECUTE A PURCHASE AND SALE
AGREEMENT BETWEEN THE CRA AND HABITAT FOR HUMANITY OF A
CRA-OWNED PROPERTY LOCATED AT 608 WEST DANIA BEACH
BOULEVARD, DANIA BEACH, FLORIDA (“PROPERTY”) FOR A DOLLAR
($1.00), FOR THE PURPOSE OF DEVELOPING THE PROPERTY FOR USE AS
TOWNHOUSES FOR LOW-INCOME AFFORDABLE HOUSING (80% AMI)
AND/OR WORKFORCE AFFORDABLE HOUSING (140% AMI), PROVIDED
THE PARTIES COME TO A NEGOTIATED AGREEMENT AS TO THE
AMOUNT AND TYPE OF AFFORDABLE HOUSING AND FURTHER
PROVIDED THE PROPERTY IS TIED TO A RESTRICTIVE COVENANT
REQUIRING THE PURCHASER TO PROVIDE 30 YEARS OF AFFORDABLE
HOUSING (80% AMI) AND/OR WORKFORCE AFFORDABLE HOUSING
Minutes of Regular Meeting
Dania Beach Community Redevelopment Agency
Tuesday, October 10, 2023 – 5:30 p.m.
3
(140% AMI) AS NEGOTIATED BETWEEN THE PARTIES; PROVIDING FOR
CONFLICTS; FURTHER, PROVIDING FOR AN EFFECTIVE DATE.
City Attorney Boutsis read the title of the resolution into the record.
Board member James asked how the AMI is being determined and Executive Director Chen
responded that he is looking for direction from the Board and is recommending that the Board
provide for at least 50% of workforce affordable housing.
Board Member James would be in favor of splitting it 50/50.
Chair Ryan commented that Habitat for Humanity encourages homeownership and they have
their own programs that people have to qualify for in order to qualify for the loan for the house.
He does not feel that this has to do with workforce or affordable housing in this situation.
Vice Chair Lewellen commented that Habitat for Humanity needs to make the recommendation
and it should not be on the Commission to decide.
Discussion ensued on the AMI percentage and how it will be split.
Executive Director Chen stated that 80% AMI is approximately $65k and 120% AMI is a little
over $100K.
Board member Davis stated that she would like to allow Habitat for Humanity to go through the
process to see what the applicant pool will be.
Vice Chair Lewellen commented that she would be in favor of leaving it up to Habitat for
Humanity to determine based on the market at the time.
Vice Chair Lewellen made a motion to approve the resolution and leave the AMI to the
discretion of Habitat for Humanity based on what the market is at the time. Board member
Davis seconded the motion.
Chair Ryan felt that Habitat for Humanity should be provided with a little more direction.
There was further discussion on what guidance to provide to Habitat for Humanity for the AMI.
After some discussion, City Attorney Boutsis clarified that the Board is in favor of 50% at 120 to
140 AMI and the other 50% to 80% AMI and if it cannot be fulfilled after approximately 20
attempts then it would go to the 140 AMI.
Vice Chair Lewellen amended her motion to reflect the change as explained by City
Attorney Boutsis of 50% at 120% to 140% AMI and the other 50% at 80% AMI and if it
cannot be fulfilled after approximately 20 attempts, then it would go to the 140% AMI.
Board member Davis seconded the amendment which carried unanimously on voice vote.
Minutes of Regular Meeting
Dania Beach Community Redevelopment Agency
Tuesday, October 10, 2023 – 5:30 p.m.
4
7.2 PATCH Site Location Discussion
Executive Director Chen introduced the item.
Board member Salvino believes that more housing can be placed in the current location of the
PATCH. He recommended putting out a bid for the purchase of the PATCH.
Board member Salvino requested consensus for putting it out for a bid.
Board member James stated that she would want to speak with the community before she makes
any decision. She commented that she is in favor of keeping it where it is and is not in favor of
selling the PATCH at its current location.
Vice Chair Lewellen said that she agrees with Board Member Salvino and commented on
ongoing flooding issues at the PATCH that is costing the City. She doesn’t feel that there is
anything wrong with looking into the bid option to see if anyone is interested.
Board member Davis commented that the current PATCH location is a high traffic area. She is in
favor of having community buy-in before any decision is made.
Chair Ryan commented that both lots sizes are odd. He asked if the current PATCH has any
crops and Executive Director Chen responded that they are growing some vegetables.
To answer Chair Ryan’s question about memberships, Executive Director Chen stated that there
are 24 plots and there have been two registrations with each having four plots.
Chair Ryan believes that the community needs a PATCH and it’s good for the community. He
stated that not everything that the city provides needs to be profitable. This is a meant to be
service to our community.
Further discussion ensued regarding the location and future of the PATCH.
Board Member Davis asked how the $45,000 that was donated by Spirit was used towards the
PATCH and Executive Director Chen replied that it has gone towards farming of the PATCH,
towards the consultants who have assisted with crop rotations, identifying strategies and how to
implement the PATCH master plan and would also go towards the new location as well if there
is an outstanding balance.
Executive Director Chen stated that based on discussions, he would recommend that staff initiate
a public notice and an RFP for potential interest in selling the current PATCH site at 1201 West
Dania Beach Boulevard and including that the proposals also would also assist with the cost of
moving the current use of the PATCH to another location. An RFP like that meets the legal
standards for dealing with CRA Holdings invested interest in a piece of property and the
Commission can reject any and all proposals received so it doesn't commit you to any final
solution.
Board member Salvino made a motion to initiate a public notice and an RFP for potential
interest in selling the current PATCH site at 1201 West Dania Beach Boulevard and
Minutes of Regular Meeting
Dania Beach Community Redevelopment Agency
Tuesday, October 10, 2023 – 5:30 p.m.
5
including that the proposals also would also assist with the cost of moving the current use
of the PATCH to another location. Vice Chair Lewellen seconded the motion which carried
3-2 with Board member Salvino, Vice Chair Lewellen and Chair Ryan voting yes and
Board member Davis and Board member James voting no.
8. Board Member Comments
Board Member commented to save the patch.
Board member James had nothing to report.
Board member Salvino had nothing to report.
Vice Chair Lewellen had nothing to report.
Chair Ryan commented on the PATCH and thanked Executive Director Chen for his work on it.
9. Information Items
None.
10. Adjournment
Chair Ryan adjourned the meeting at 6:37 p.m.
ATTEST: COMMUNITY REDEVELOPMENT
AGENCY
ELORA RIERA, MMC ARCHIBALD J. RYAN IV
CRA SECRETARY CHAIR – CRA
Approved: November 14, 2023
100 West Dania Beach Boulevard, Dania Beach, Florida 33004
www.DaniaBeachCRA.org
MEMORANDUM
To: Dania Beach Community Redevelopment Agency Chair, Vice Chair, Board Members
From: Michael Chen, Executive Director
Date: November 14, 2023
Re: Dania Beach Clean Energy Industrial Park
Corporate Startups: I have been working with two “cleantech” companies to secure their
manufacturing operations to Dania Beach. The companies are: 1) Azra Tech, and Solis Power.
Azra Tech: I have been working with Paul Moore, Chairman & CIO
of Azra Tech, for about nine months. Azra Tech was launched in Italy:
their holding company and all intellectual property ownership is
based in New York. They have been developing "cleantech" chemical
products for industrial use for over 10 years and their international
patent portfolio has over 200 registrations with over 120 fully granted.
Their current focus is on the shipping sector as international
environmental regulations are being implemented to counter water
pollution and CO2 emissions. Their ship’s hull coating system has
advantages over the traditional toxic paints, as it is longer lasting without leaching
poisonous chemicals into the waterways. Due to its Nano clays content, Azra Tech coatings
are documented to reduce ship fuel consumption by 10% to 12%. Their hull coating system
can be adapted to recreational marine vessels and Dania Beach boatyards could be the
global lead on the newly adapted technology.
Azra Tech has dozens of other certified products including paints and primers with unique
properties such as anti-corrosion, anti-icing, and fire retardant. They are seeking a South
Florida location as their hub of operations for the Americas. Their interest in Dania Beach
has a direct connection to the FIU IP2Mkt Incubator and Paul Moore is requesting approval
from his Board of Directors to provide a Letter of Intent to Dania Beach.
Solis Power – Advanced Concentrating Solar Power (CSP) Systems: I have been
working with Dr Chris Ford, Partner in Solis, for about six months.
Founded in 2021, Solis has worked with world renown energy
systems experts to develop a patented solution.
Solis has developed a revolutionary solar concentrating solution
producing high quality heat that reaches temperatures more than
1,200oC (2,200oF) and high efficiency solar-to-electricity conversion.
Their system can operate 24/7 even when there is no sunlight and
Dania Beach Community Redevelopment Agency
Dania Beach Clean Energy Industrial Park
November 14, 2023
Page 2 of 4
100 West Dania Beach Boulevard, Dania Beach, Florida 33004
www.DaniaBeachCRA.org
offers a superior and more cost-effective CSP solution than all existing designs.
Solis Power recently awarded $2 million of a $4 million demonstration grant from the DOE’s
Office of Fossil Energy and Carbon Management as result of congressionally directed
spending led by Senator Joe Manchin. The associated manufacturing of the demonstration
grant will be fulfilled by South Florida fabricators. Facilitated through Golden Technologies,
Inc, Solis Power has investor commitments for more than $530 million for manufacturing
expansion and scale up They are in the middle of a $20 million equity raise and $363 million
in renewable energy projects. Their connection to Dania Beach through the FIU IP2Mkt
Incubator is obvious.
The Site: With two potential manufacturing in the wings, the next question is where they can
go. Broward County owns two adjacent parcels of land on the north border of Dania Beach:
1870 Griffin Rd (BCPA ID 5042 28 09 0010) and 1880-90 Griffin Rd (BCPA ID 5042 28 12
0030). Collectively, these parcels total 13.21 acres (575,734sf), with a Just Value of $6.91
million (BCPA folio sheets attached). With reasonable planning, this site should accommodate
approximately 250,000sf of manufacturing space. It is estimated that 1,000 manufacturing jobs
could be created. Over the past few years, I have had discussions with a Broward Commissioner
regarding their interest in using the sites for a manufacturing operation.
Florida has five target business activities: Manufacturing, Corporate HQ, Research &
Development, Global Logistics and Emerging Technologies. Within those activities, the State
focuses on six primary industries: Cleantech (Energy Equipment, Energy Storage,
Environmental/Sustainable Products) and Emerging Technologies (Marine Sciences, Materials
Science, and Nanotechnology). The Dania Beach Clean Energy Industrial Park, with the initial
tenants of Azra Tech and Solis, covers four of the five State focus activities and seven of the target
industries. Broward County has 10 target industries, which are closely aligned with the State. Azra Tech
and Solis cover six of the County’s target industries: Advanced Materials and High-Tech
Manufacturing, Alternative Energy and Renewable Resources, Global Business Services,
Headquarters and Management Operations, International Trade and Logistics, and Marine
Industries. It is expected that Broward County will have a great deal of interest in the concept
of the Dania Beach Clean Energy Industrial Park.
Potential Funding Sources: On October 19th, the CRA hosted a table at the Greater Ft
Lauderdale Alliance Annual Meeting. In addition to the Mayor and several Commissioners,
Mary Partin, CEO of the Dan Marino Foundation, and J. Chris Ford, Ph.D., Principal
Scientist FIU Applied Research Center and IP2Mkt Manager, joined the table. Between the
presentations, we discussed the IP2Mkt Incubator and the Dania Beach Clean Energy Industrial
Park. Ms. Partin explored how the Foundation could best be part of and support these initiatives. This
enthusiastic support resulted in Chris Ford writing a grant application on behalf of the team.
Dania Beach Community Redevelopment Agency
Dania Beach Clean Energy Industrial Park
November 14, 2023
Page 3 of 4
100 West Dania Beach Boulevard, Dania Beach, Florida 33004
www.DaniaBeachCRA.org
U. S. Department of Energy (DOE) Future Grant (EFG): DOE has allocated $37 million
to provide financial and technical assistance to support innovative, novel, or early-action
clean energy planning to benefit disadvantaged communities. This is a two-phase grant:
•Phase I: up to $500,000
•Phase II: up to $1,000,000 to Phase I awardees
Prime applicants include states/territories, local governmental entities, and tribal nations.
DOE is looking for collaborative applications that include eligible subrecipients such as:
•Non-profit entities including CBOs.
•Institutions of higher education, community colleges, and think tanks.
•Local or regional planning organizations.
•Investor-owned, coop/public, and municipal power providers.
•For-profit entities such as architecture, engineering, or consultants.
The application deadline was November 10th. Based on the EFG requirements, the table
below shows the application team:
Partner Role and Strategic Value Experience with Partners
Dania Beach CRA Prime Worked with FIU, Supported DOE proposals by Solis Power,
NextEra Energy (Advisory Board)
Florida Power and
Light (NextEra Energy)
Utility Representative On Advisory Board of Dania Beach IP2Mkt Incubator; Just built a
Green Hydrogen Facility in Dania Beach
Dan Marino Foundation Workforce Development and
Access to Grant Capital
MOU with Dania Beach
Florida International
University
Economic Modeling and Impact
Analysis, Energy Equity Scorecard
MOU with Dania Beach on IP2Mkt Business Incubator and
Economic Development
Golden Technologies,
Inc
Technical Advisement, Ecosystem
building, Raising Capital for Clean
Energy Manufacturing Participants
Experience in building ecosystems inclusive of DOE Resources;
Energy Justice and community engagement. Access to private
capital that has garnered capital commitments
The initial target companies include:
Company Commitment Relationship to Consortium
Golden Technologies Support Technology Transfer,
Incubation, and Acceleration
DOE experience, advisory services to initial anchor tenants, and will
work with university and
Solis Power Renewable Energy Solution
Provider and Manufacturer
Previously partnered with Dania Beach on proposals to DOE; Incubated
by Golden Technologies; Resident in Clean Energy Industrial Park
Azra Tech Renewable Energy
Manufacturer
Resident in Clean Energy Industrial Park
Ambra Technologies Waste-to-Hydrogen
technology provider
Resident in the Clean Energy Industrial Park facilitated through Golden
Technologies, Inc
Council of Development Finance Agencies (CDFA) Greenhouse Gas Reduction Fund
(GGRF): Under this first-of-its-kind program, CDFA will launch a $2 billion accelerator
program designed to serve a community lender network of development finance agencies
(DFAs). They will work to build the expertise and financial capacity of DFAs to nurture
projects that reduce or avoid emissions of greenhouse gas and other air pollutants in low-
income and disadvantaged communities (LIDACs). CDFA will provide capitalization funding
Dania Beach Community Redevelopment Agency
Dania Beach Clean Energy Industrial Park
November 14, 2023
Page 4 of 4
100 West Dania Beach Boulevard, Dania Beach, Florida 33004
www.DaniaBeachCRA.org
of up to $10 million to DFA Accelerator participants who submit a budget request and plan
for utilizing capitalization funds.
CDFA worked to build a broad base of support from communities and organizations across
the country and submitted a competitive application with interest from over 160 DFAs. As a
member of CDFA, I submitted a pre-application proposal on behalf of the CRA that was
part of the CDFA broad base of support used to secure their $2 billion of funding.
The DFA Accelerator places a premium on investing in LIDACs and ensuring the program’s
impact is congruent with President Biden’s Justice40 Initiative—that at least 40% of overall
funds distributed by CDFA and our partners flow to disadvantaged communities that are
marginalized, underserved, and overburdened by pollution.
U.S. Environmental Protection Agency (EPA) Greenhouse Gas Reduction Fund
(GGRF): The EPA the $27 billion GGRF, a first-of-its-kind, national-scale competitive grant
program created by the President’s Inflation Reduction Act. This program, part of the
Investing in America agenda, will leverage public investment with private capital and finance
clean energy projects that reduce pollution and energy costs, increase energy security, and
create good-paying jobs, especially in low-income and disadvantaged communities and
places that have historically shouldered the burden of harmful pollution. The GGRF will
catalyze investment in thousands of clean energy projects, build the capacity of community
lenders to drive local economic growth, and deploy cost-saving solar energy in communities
across the country.
Request: There is no immediate funding impact associated with this request. The CRA is
requesting direction from the CRA Board to collaborate with Mayor Ryan to initiate discussions
with the Broward County Mayor and Commissioners. Further, the CRA requests approval to
work with the Broward Office of Economic and Small Business Development (OESBD), other
Broward departments, and relevant trade agencies, as necessary. Finally, the CRA requests
approval to explore and apply for grant funds to support this initiative.
10/23/23, 11:11 AM 1870 GRIFFIN ROAD
https://bcpa.net/RecInfo.asp?URL_Folio=504228090010 1/1
Site Address 1870 GRIFFIN ROAD, DANIA BEACH FL 33315
Property Owner BROWARD COUNTY
BOARD OF COUNTY COMMISSIONERS
Mailing Address 115 S ANDREWS AVE RM 501-RP FORT
LAUDERDALE FL 33301-1801
ID #5042 28 09 0010
Millage 0413
Use 80
Abbr Legal
Description
AIRVIEW HOTEL 125-16 B PARCEL "A"
The just values displayed below were set in compliance with Sec. 193.011, Fla. Stat., and include a
reduction for costs of sale and other adjustments required by Sec. 193.011(8).
* 2024 values are considered "working values" and are subject to change.
Property Assessment Values
Year Land Building /
Improvement
Just / Market
Value
Assessed /
SOH Value Tax
2024 $5,758,900 $5,758,900 $5,758,900
2023 $5,758,900 $5,758,900 $5,621,030
2022 $5,758,900 $5,758,900 $5,110,030
2024 Exemptions and Taxable Values by Taxing Authority
County School Board Municipal Independent
Just Value $5,758,900 $5,758,900 $5,758,900 $5,758,900
Portability 0 0 0 0
Assessed/SOH $5,758,900 $5,758,900 $5,758,900 $5,758,900
Homestead 0 0 0 0
Add. Homestead 0 0 0 0
Wid/Vet/Dis 0 0 0 0
Senior 0 0 0 0
Exempt Type 04 $5,758,900 $5,758,900 $5,758,900 $5,758,900
Taxable 0 0 0 0
Sales History
Date Type Price Book/Page or CIN
10/1/2013 ORT-T 111827158
6/21/2004 SWD $25,938,000 37816 / 1652
12/15/1995 QCD $114,286 24284 / 251
12/1/1987 CET $2,736,364 15056 / 406
11/1/1985 WD $4,000,000
Land Calculations
Price Factor Type
$12.00 479,908 SF
Adj. Bldg. S.F.
Special Assessments
Fire Garb Light Drain Impr Safe Storm Clean Misc
04 DS
L
1 281.2
Pro
p
e
r
t
y
I
d
:
5
0
4
2
2
8
0
9
0
0
1
0
*
*
P
l
e
a
s
e
s
e
e
m
a
p
d
i
s
c
l
a
i
m
e
r
Octo
b
e
r
2
3
,
2
0
2
3
0
450
900
225
ft
0
130
260
65
m
1:4
,
8
0
0
Flig
h
t
D
a
t
e
:
J
a
n
.
6
t
o
J
a
n
.
1
1
,
2
0
2
3
B
r
o
w
a
r
d
C
o
u
n
t
y
P
r
o
p
e
r
t
y
A
p
p
r
a
i
s
e
r
10/23/23, 11:14 AM 1880-1890 GRIFFIN ROAD
https://bcpa.net/RecInfo.asp?URL_Folio=504228120030 1/1
Site Address 1880-1890 GRIFFIN ROAD, DANIA BEACH FL 33004
Property Owner BROWARD COUNTY
BOARD OF COUNTY COMMISSIONERS
Mailing Address 115 S ANDREWS AVE RM 501-RP FORT
LAUDERDALE FL 33301-1801
ID #5042 28 12 0030
Millage 0413
Use 80-01
Abbr Legal
Description
LAPOINTE PLAZA 140-27 B PAR A LESS POR DESC IN 17827/907 LESS PAR 108 CASE
92-25867 OR 20155/309
The just values displayed below were set in compliance with Sec. 193.011, Fla. Stat., and include a
reduction for costs of sale and other adjustments required by Sec. 193.011(8).
* 2024 values are considered "working values" and are subject to change.
Property Assessment Values
Year Land Building /
Improvement
Just / Market
Value
Assessed /
SOH Value Tax
2024 $1,149,910 $1,149,910 $1,149,910
2023 $1,149,910 $1,149,910 $1,122,370
2022 $1,149,910 $1,149,910 $1,020,340
2024 Exemptions and Taxable Values by Taxing Authority
County School Board Municipal Independent
Just Value $1,149,910 $1,149,910 $1,149,910 $1,149,910
Portability 0 0 0 0
Assessed/SOH $1,149,910 $1,149,910 $1,149,910 $1,149,910
Homestead 0 0 0 0
Add. Homestead 0 0 0 0
Wid/Vet/Dis 0 0 0 0
Senior 0 0 0 0
Exempt Type 04 $1,149,910 $1,149,910 $1,149,910 $1,149,910
Taxable 0 0 0 0
Sales History
Date Type Price Book/Page or CIN
4/3/2013 WD-D $1,894,000 111440725
11/14/2002 WD* $1,155,400 34265 / 782
* Denotes Multi-Parcel Sale (See Deed)
Land Calculations
Price Factor Type
$12.00 95,826 SF
Adj. Bldg. S.F.
Special Assessments
Fire Garb Light Drain Impr Safe Storm Clean Misc
04 DS
X
1 75.8
Pro
p
e
r
t
y
I
d
:
5
0
4
2
2
8
1
2
0
0
3
0
*
*
P
l
e
a
s
e
s
e
e
m
a
p
d
i
s
c
l
a
i
m
e
r
Octo
b
e
r
2
3
,
2
0
2
3
0
225
450
112
.
5
ft
0
60
120
30
m
1:2
,
4
0
0
Flig
h
t
D
a
t
e
:
J
a
n
.
6
t
o
J
a
n
.
1
1
,
2
0
2
3
B
r
o
w
a
r
d
C
o
u
n
t
y
P
r
o
p
e
r
t
y
A
p
p
r
a
i
s
e
r
City of Dania Beach
Memorandum
DATE: 11/14/2023
TO: Chair and Board Members
FROM: Micael Chen, Executive Director
SUBJECT: Commercial Façade Grant – 225 SW 2nd Ter
Request:
Background:
225 SW 2nd Ter is owned by Grant Einhorn, dba GEE Coin 3, Inc.
The Project: GEE Coin 3, Inc. is a laundromat, operating under the ownership of Grant Einhorn
for approximately 2 years. Grant feels it is time to rehab the building and update the store’s
identity from its current name signage, Sam’s Coin Laundry, to his company brand.
The renovation includes a new awning, painting, new paved parking lot, dumpster enclosure, and
new sign. The applicant estimates the rehab to cost from $57,000.00, documented by at least two
cost estimates for each segment of the project. The Façade Grant application is seeking the
$25,000.00, representing a 43.9% match of the cumulative estimated project cost. The owner’s
share of the construction costs will be self-funded.
Attachments: Owner’s Façade Grant application
Photos of the existing building
Property survey
BCPA folio sheet and map
Copies of the construction estimates
Budgetary Impact
If approved, the funds for this grant will come from CRA account #106-52-08-552-31-43, CRA
Economic Development Initiatives: Commercial Façade Grant.
Recommendation
The CRA requests your approval of the Façade Grant application for 225 SW 2nd Ter in an
amount of $25,000.00 or 50% of the actual project cost as evidenced by paid receipts, whichever
is less.
Dania Beach Community Redevelopment Agency
Facade Grant Program �! .. � }c�c�-��St� Grant Application
PART 3: LINE-ITEM BUDGET
Property Address: 2, 2 S SL:V 2 Ne , Lvvei,e
Applicant/Property Owner: Gvao+ ES�hc.ro I GEE L.e1·-3. Iv)C Address:3qz1 N 5'1 � CM;,cw Phone:(:l54)253-S3W3 Owner:
All work must be performed by contractor(s) with a valid Florida Contractor License and must be registered with the City of Dania
Beach. Only improvements seen from the building's street frontage (2 sides if the building is on a corner lot) will be eligible for a
grant award. Eligibility of work included in the calculation of a grant award is at the sole discretion of the CRA.
Improvement Description I Line-Item Cost
Architectural/engineering plans
Contractor fees
Removal of deteriorated or undesirable exterior alterations.
Exterior improvement, restoration, or rehabilitation
Repair, replacement, or installation of new storefront impact windows
Repair, replacement, or installation of new exterior doors
Repair, replacement, or installation of new awnings.
Repair, replacement, or installation of new exterior lighting.
Renewal or installation of new landscaping.
Exterior painting.
Signage,(Must be part of a bigger project and permanently affixed to the building. )
Parking lot improvements (Must be part of a bigger project..)
ADA compliance features/modifications Roof repairs
Structural stabilization
Dumpster enclosure
General maintenance items
Other Improvements: (describe)
Other Improvements: (describe)
Other Improvements: (describe)
TOTAL PROJECT BUDGET
$
$
$
$
$
$
$3 OOD.00
$
$
$11 000.00
$20.000.00
$
$
$ $2D 000.00
$
$
$
$
I hereby attest I am the Property Owner with authority to encumber the Property and the
information on this application is accurate to the best of my knowledge.
� � /0/2S12023
Property Owner/Applicant Date
COMMERCIAL FAÇADE GRANT APPLICATION
GEE COIN 3 INC
225 SW 2nd TER
Page 1 of 2
COMMERCIAL FAÇADE GRANT APPLICATION
GEE COIN 3 INC
225 SW 2nd TER
Page 2 of 2
This Survey has been prepared for:
On your behalf, and as a requirement for your transaction, this document has been coordinated with us by the firm shown
below. Landtec Surveying, Inc. is a private firm and remains entirely responsible for this document’s content.
PROPERTY ADDRESS:
Sheet 1 of 2 (Sketch of Survey) - See Sheet 2 of 2 for Legal Description, Certifications, Property and other Survey related data. SURVEY IS NOT COMPLETE WITHOUT ALL SHEETS
SCALE:1"=30'
10/30/23, 9:20 AM 225 SW 2 TERRACE
https://bcpa.net/RecInfo.asp?URL_Folio=514203440010 1/1
Site Address 225 SW 2 TERRACE, DANIA BEACH FL 33004
Property Owner GEE COIN 3 INC
Mailing Address 3821 N 51 AVE HOLLYWOOD FL 33021
ID #5142 03 44 0010
Millage 0413
Use 11-02
Abbr Legal
Description
GEORGE M PHIPPEN SUB-RESUB 35-4 B LOT 1 LESS BEG AT SW COR OF LOT 1,NELY
108.52,ELY 34.54 TO P/C, SWLY AN ARC DIST OF 87.83 TO P/C SLY & ELY AN ARC DIST
OF 39.83 TO P/T WITH S/L OF LOT 1,WLY 38.35 TO POB,2 LESS E 2
The just values displayed below were set in compliance with Sec. 193.011, Fla. Stat., and include a
reduction for costs of sale and other adjustments required by Sec. 193.011(8).
* 2024 values are considered "working values" and are subject to change.
Property Assessment Values
Year Land Building /
Improvement
Just / Market
Value
Assessed /
SOH Value Tax
2024 $74,490 $381,980 $456,470 $456,470
2023 $74,490 $381,980 $456,470 $456,470
2022 $74,490 $325,850 $400,340 $400,340 $9,133.42
2024 Exemptions and Taxable Values by Taxing Authority
County School Board Municipal Independent
Just Value $456,470 $456,470 $456,470 $456,470
Portability 0 0 0 0
Assessed/SOH $456,470 $456,470 $456,470 $456,470
Homestead 0 0 0 0
Add. Homestead 0 0 0 0
Wid/Vet/Dis 0 0 0 0
Senior 0 0 0 0
Exempt Type 0 0 0 0
Taxable $456,470 $456,470 $456,470 $456,470
Sales History
Date Type Price Book/Page or CIN
5/13/2022 DRR-T $100 118191438
4/6/2022 WD-D $650,000 118106483
4/1/1992 WD $300,000 19452 / 774
1/1/1990 QCD $85,000
12/1/1988 WD $150,000
Land Calculations
Price Factor Type
$10.00 7,449 SF
Adj. Bldg. S.F. (Card, Sketch)2065
Eff./Act. Year Built: 1971/1970
Special Assessments
Fire Garb Light Drain Impr Safe Storm Clean Misc
04 DS
C
2065 10.8
Pro
p
e
r
t
y
I
d
:
5
1
4
2
0
3
4
4
0
0
1
0
*
*
P
l
e
a
s
e
s
e
e
m
a
p
d
i
s
c
l
a
i
m
e
r
Octo
b
e
r
3
0
,
2
0
2
3
0
50
100
25
ft
0
10
20
5
m
1:6
0
0
Flig
h
t
D
a
t
e
:
J
a
n
.
6
t
o
J
a
n
.
1
1
,
2
0
2
3
B
r
o
w
a
r
d
C
o
u
n
t
y
P
r
o
p
e
r
t
y
A
p
p
r
a
i
s
e
r
Awninglux INC.
14125 NW 19 AVE
Opalocka, FL 33054
+1 7866632609
awninglux@gmail.com
www.awninglux.com
ADDRESS SHIP TO
Steve Einhorn
225 SW 4 Terr Dania Beach
Fl 33304
Steve Einhorn
225 SW 4 Terr Dania Beach
Fl 33304
Estimate
DATE 02/23/2023
ACTIVITY AMOUNT
SalesReplace fabric on one front awning color TBD Commercial grade Vinyl Patio 500 18.5 heavy duty. Do as existing.
2,950.00T
Terms: 50% deposit and 50% balance after installation.SUBTOTAL 2,950.00
TAX 206.50
TOTAL $3,156.50
Accepted By Accepted Date
• The “TERMS AND CONDITIONS OF THIS SALE: accompany, and are part of, this proposal •
PLEASE RETURN SIGNED ORIGINAL UPON ACCEPTANCE
Winner of over 80 National
and International Awards
Ft. Lauderdale Office
844 NW 9th Avenue
Ft Lauderdale, FL 33311
954-764-1711
Hoover Canvas Products Co., DBA
Serving all of South Florida
Since 1949
Palm Beach Location
5107 N. Australian Avenue
West Palm Beach, FL 33407
561-844-4444
INVOICE TO
Epic Properties
PROJECT NAME
Sam's Coin Laundry
STREET
STREET
225 Southwest 2nd Terrace
CITY, STATE, ZIP CODE
CITY, STATE, ZIP CODE
Dania Beach Fl, 33004
CONTACT
Steve
PHONE
(954) 812-0414
EMAIL
einhorn44@yahoo.com
FABRIC
Coastline Plus
VALANCE LENGTH
9"
SCALLOP #
TBD
BRAID COLOR
TBD
TRIM COLOR
None
FRAME PAINT COLOR
None
Fabricate and install (1) new awning cover.
Approx 56’wide by 9’ projection.
• Fabric to be Coastline Plus – Color TBD. Extended fabric warranty included*.
• All stitching to be Gore Tenara and carries a lifetime seam warranty.
• All major seams to have a 1” welded seam for maximum strength.
• Permit fees additional, at cost if needed and are not included in this quote if needed.
• Engineering will be an additional and cost will be added to the final invoice if needed.
• Please refer to https://hooverap.com/hoover-warranty/ for warranty details.
• Price does not include any painting or repairs to the current frame.
**Permit Fees, Engineering Calculations, and/or Applicable Government Fees Additional if needed**
Additional Work: **Customer is responsible for verifying all wire payment information by phone prior to sending any money electronically**
Hoover does not perform any electrical work. Hoover does not replace pavers or any flooring materials. Hoover can coordinate these services at a fee of cost + 15%. Customer is responsible for any structural banking (costs & installation) that may be required at any time during the project. Warranty: Please refer to Hoover’s warranty at www.hooverap.com/warranty for all warranty information.
THIS IS A LUMP SUM CONTRACT UNLESS OTHERWISE STATED. We Propose hereby to furnish material and labor as described above.
A Proposal in excess of $5,000 will not be binding on Hoover until signed by an executive officer.
PRICE $4,239.00
PERMIT Additional
ENGINEER Additional
Sales Person: John Yarbrough Date: 3/31/23 TOTAL
Hoover AP Exec: DEPOSIT 50%
Payment Terms: Deposit & Bal Upon Completion BAL DUE
CANVAS AND VINYL AWNINGS WILL WRINKLE.
Acceptance of Proposal- The above prices, specifications and
conditions on the reverse side hereof are satisfactory and are
hereby accepted. You are authorized to do the work as specified.
Payment will be made as outlined above.
CBC128905 C.C. #77-76-AE U-15047 C.C. #1630
CUSTOMER
PRINT NAME ________________________________
SIGNATURE _________________________________ DATE __________________
I OWN THE PROPERTY ☐YES ☐ NO
I am a repeat customer ☐ YES ☐ NO
TERMS AND CONDITIONS OF THIS SALE
1. Hoover Canvas Products Co., (hereinafter "Hoover" or "we") hereby warrants all materials to be as specified and that all work shall be performed in a workmanlike manner, according to accepted standard practices. THIS EXPRESS WARRANTY EXCLUDES ALL OTHER AGREEMENTS, REPRESENTATIONS AND WARRANTIES, EXPRESSED OR IMPLIED. HOOVER SPECIFICALLY DISCLAIMS ANY IMPLIED WARRANTY OF MERCHANTABILITY OR WARRANTY OF FITNESS FOR A PARTICULAR PURPOSE. 2. "Customer" or "you" understands that all vinyl coated and fabric materials will expand and contract when exposed to changing temperatures and weather conditions. These materials may be used to construct awnings, trim, and binding and Hoover cannot warranty these materials against wrinkling and shrinkage. Any necessary sewing or
stitching of material will be done with white thread.
3. Acrylic material is not waterproof. It has a tendency to leak when wet. (Sunbrella, etc.) Customer shall have a pro rated warranty on fabric, whether manufactured from
vinyl-coated fabric or other fabric types, provided the awning has been maintained and cleaned regularly. The Customer's failure to maintain and clean the awning regularly
could result in the fabric not meeting its intended life expectancy and voiding this warranty. Hoover recommends cleaning every three months.
4. Lateral arm awnings ("Retractable Awnings") are designed for sun protection only, not for rain protection. Hoover cannot warrant Retractable Awnings against collapse or
damage resulting from rain, severe weather, or winds in excess of 30 m.p.h. During such time, the Customer is advised to keep these awnings retracted. Hoover recommends
that Customer use only acrylic fabric with Retractable Awnings, use of any other fabric voids Hoover's warranty. Motion/wind sensors do not, in anyway, guarantee against
damage from winds in excess of 30MPH.
5. Hoover shall not be responsible for loss or damage to Customer's business or property or injury or death to persons. For any risk, liability or responsibility assumed by the
Customer and/or Owner under this Contract, or disclaimed by Hoover under this Contract (collectively, the "Assumed Risks"), the parties acknowledge and agree that: a]
some of the Assumed Risks may be covered under insurance held by the Customer or the property owner; b] Hoover shall have no liability (in contract or in tort) to the
Customer, property owner and/or third parties for any of the Assumed Risks, regardless of whether Hoover takes any action to avoid, limit or remedy any of the Assumed
Risks; and c] such action or inaction on the part of Hoover shall not constitute a breach of this Contract or of any duty of care owed to the Customer, a property owner or third
parties. Notwithstanding any other contrary provision in the Contract, Customer agrees to indemnify, hold harmless and defend Hoover from and against any and all claims,
obligations, demands, damages, causes of action, liabilities, losses, and expenses, including reasonable attorneys' and expert fees, whether now known or hereafter known,
foreseen or unforeseen, attributable in whole or in part to the Assumed Risks (the "Indemnity").This Indemnity shall be capped at $1 million dollars (US) and is given to Hoover in consideration for the warranty offered by Hoover hereunder (if applicable) and/or for the job pricing, which would be higher absent the Indemnity. 6. The parties agree that Customer's sole and exclusive remedy against Hoover shall be for the repair or replacement of any awning materials, which are defective when delivered. In no event shall Hoover be liable for direct, indirect, special, incidental or consequential damages (including loss of profits) whether based on contract, tort or any
other legal theory. Any defects or discrepancies in the awning materials as delivered or installed must be reported to Hoover within twenty (20) days after the Customer
receives the awning materials or it will be conclusively presumed that the awning materials were as ordered and were received in good condition. Notice to Hoover of any
defects, discrepancies or objections must be delivered in writing via certified or registered mail to the address shown on the face of this agreement.
7. It is hereby expressly provided that although the said materials have been hereinbefore described, the materials delivered by Hoover hereunder shall be deemed to
correspond with their description, when they correspond with the sample which has been produced to, examined and selected by the Customer. Since aesthetics is an
important factor in our industry and since Hoover's services are essentially to transform canvas and metal into pleasing designs, it is sometimes necessary to alter Customer's
layout and/or specifications to make them conform to available materials, acceptable tolerances and engineering or regulatory constraints. Hoover reserves the right to make
such changes. Hoover also reserves the right to cancel this contract if engineering changes required by a governmental entity or permitting authority increase Hoover's
materials and/or labor costs by more than 5%. Hoover is not obligated to advance any permitting or engineering fees on Customer's behalf.
8. Hoover will not be responsible for the usefulness of any frame not built or installed by us, unless we are authorized by the customer to rebuild same to Hoover's
specifications. Hoover does not warrant against water leaks where awning meets wall when existing frames are recovered, unless such leaks are listed and addressed on
contract. All awning materials used by Hoover have been treated with a mildew inhibitor. Mildew is micro-organic bacteria, which can grow on any material, metal, glass or
plastics, BUT WE OFFER NO GUARANTEE WHATSOEVER THAT MILDEW WILL NOT OCCUR.
9. It is hereby expressly acknowledged, understood and agreed that this is a contract for a special order of custom fabricated goods and materials and the Customer cannot
alter, revoke or cancel the same without the specific written consent of Hoover. 10. The estimated delivery date of this order is subject to contingencies beyond the control of Hoover, including, but not limited to fires, strikes, lockout, inability to secure material, labor or transportation, inclement weather, accidents, Acts of God and unavailability of the Customer. In the event of the occurrence of such contingency, the estimated delivery date shall be extended by equal duration to the extent of the duration of such contingency. 11. Customer agrees to pay Hoover the full balance of the purchase price immediately upon completion and delivery of the material and work to the Customer and time of such payment shall be of the essence. No back charges will be accepted. Hoover shall retain title to all goods pending receipt of the entire purchase price. 12. The Customer covenants and agrees that upon his default by the failure to pay any part of or the entire purchase price when due, or otherwise, Hoover shall, at its option,
have the right to:
A. Without judicial action, take possession of all said property and all payment made by the Customer up to the time of said default shall be applied as rent
and depreciation on said property for and during the time the property is in the Customer's possession. Permission is granted to re-enter the property to
remove said property; Hoover is granted permission to re-enter the Customer's land or structure to remove said property; and/or,
B. Bring legal action to collect all monies due Hoover under the terms of this agreement; and/or,
C. Enforce and foreclose a lien against the said property without further notice to the Customer; and/or,
D. Void any warranties and pursue any other remedy available to said company in law or in equity.
13. The Customer covenants and agrees to pay reasonable attorney's fees and costs to Hoover in the event Hoover incurs such fees and costs in enforcing its rights under
the terms of this contract, including attorney's fees incurred in obtaining and enforcing a judgment and/or pursuing on defending an appeal. Any legal action brought by either
party shall be governed by Florida law and, shall, at Hoover's election, be brought in Broward County, Florida, or a different county if necessary to enforce Hoover's lien rights
or other remedies.
14. This proposal by Hoover shall expire thirty (30) days after date of issue, but is subject to withdrawal during such time if notice to that effect is given before written
acceptance by the Customer. The only terms of the agreement between the Customer and Hoover are those set forth in this document, and these
terms may be changed or modified only by a writing signed by both parties.
15. After acceptance of this proposal, any delay by the purchaser may result in a change of price corresponding to any change in the cost of labor or raw materials.
16. A charge of 1-1/2% per month or fraction thereof (18% per annum) shall be added to all delinquent accounts. 17. Occasionally after installation, "pinholes" can be found in the awning cover. This is not a result of fabric quality, and does not affect the long-term performance of your awning cover. Should this occur, we will address the pinholes to keep water from coming through your awning cover.
Once we have addressed this issue, we guarantee, that your awning cover will not fail as a direct result of the original pinholes, for a period of five (5) years from the date of
installation.
18. Over time, awnings experience a great deal of environmental hardship from day-to-day exposure to the elements. This exposure may cause the awning cover to fade and
lose color, become brittle and hard or even lose material surface from what is known as "plasticizer migration". Given these conditions, we know that removing a cover may
result in any combination of the following conditions: "pinholes", cracks, small tears, wrinkles and/or "crazing". In addition, once awning covers are removed from the frame
and reinstalled, they tend to readily attract dirt, smudges and marks. Therefore, if we remove awning cover from the frame for storage, cleaning and/or maintenance, we
cannot guarantee or provide remedy against the above possible conditions. Any awning taken down, regardless of age, will get extremely dirty and Hoover Canvas Products
cannot be held responsible for this occurrence. We recommend that awnings be thoroughly cleaned prior to any work being done, requiring awnings to be taken down.
19. Concerning warranties for jobs outside of Dade, Broward, Palm Beach and Martin counties. Hoover will not be responsible for any expenses incurred by Hoover to bring
Hoover's labor, to and from the job site, or to bring the awning(s), to and from Hoover, including (without limitation): airfare, room and board, taxi's, rental cars, taxes, duty,
labor cost to and from the job site, etc.
20. Customer acknowledges receipt from Hoover of exhibit "A" called "Statutory Disclosures".
Customer's signature: _____________________________________________________________Date:
STATUTORY DISCLOSURES
Hoover Canvas Products Co.
Exhibit "A
CONSTRUCTION LIENS. ACCORDING TO FLORIDA'S CONSTRUCTION LIEN LAW (SECTIONS 713.001-713.37,
FLORIDA STATUTES), THOSE WHO WORK ON YOUR PROPERTY OR PROVIDE MATERIALS AND SERVICES
AND ARE NOT PAID IN FULL HAVE A RIGHT TO ENFORCE THEIR CLAIM FOR PAYMENT AGAINST YOUR
PROPERTY. THIS CLAIM IS KNOWN AS A CONSTRUCTION LIEN. IF YOUR CONTRACTOR OR A
SUBCONTRACTOR FAILS TO PAY SUBCONTRACTORS, SUB-SUBCONTRACTORS, OR MATERIAL SUPPLIERS,
THOSE PEOPLE WHO ARE OWED MONEY MAY LOOK TO YOUR PROPERTY FOR PAYMENT, EVEN IF YOU
HAVE ALREADY PAID YOUR CONTRACTOR IN FULL. IF YOU FAIL TO PAY YOUR CONTRACTOR, YOUR
CONTRACTOR MAY ALSO HAVE A LIEN ON YOUR PROPERTY. THIS MEANS IF A LIEN IS FILED YOUR
PROPERTY COULD BE SOLD AGAINST YOUR WILL TO PAY FOR LABOR, MATERIALS, OR OTHER SERVICES
THAT YOUR CONTRACTOR OR A SUBCONTRACTOR MAY HAVE FAILED TO PAY. TO PROTECT YOURSELF,
YOU SHOULD STIPULATE IN THIS CONTRACT THAT BEFORE ANY PAYMENT IS MADE, YOUR CONTRACTOR IS
REQUIRED TO PROVIDE YOU WITH A WRITTEN RELEASE OF LIEN FROM ANY PERSON OR COMPANY THAT
HAS PROVIDED TO YOU A "NOTICE TO OWNER." FLORIDA'S CONSTRUCTION LIEN LAW IS COMPLEX, AND IT
IS RECOMMENDED THAT YOU CONSULT AN ATTORNEY.
CONSTRUCTION DEFECTS. ANY CLAIMS FOR CONSTRUCTION DEFECTS ARE SUBJECT TO THE NOTICE AND
CURE PROVISIONS OF CHAPTER 558, FLORIDA STATUTES.
THREE (3) DAY RIGHT OF RESCISSION (applicable only to residential homeowners). YOU ARE ENTERING INTO
A CONTRACT THAT MAY RESULT IN A LIEN ON YOUR HOME. YOU HAVE A LEGAL RIGHT UNDER FEDERAL
LAW TO CANCEL THIS CONTRACT, WITHOUT COST, WITHIN THREE BUSINESS DAYS FROM THE DATE YOUR
CONTRACT IS FULLY EXECUTED (SIGNED BY BOTH PARTIES). IF YOU DECIDE TO CANCEL THIS
TRANSACTION, YOU MAY DO SO BY: A] NOTIFYING HOOVER IN WRITING AT THE POSTAL ADDRESS OR E-
MAIL ADDRESS SHOWN BELOW; B] USE ANY WRITTEN STATEMENT THAT IS SIGNED AND DATED BY YOU
AND STATES YOUR INTENTION TO CANCEL; AND C] SENDING THE NOTICE NO LATER THAN THE THIRD
BUSINESS DAY FOLLOWING FINAL EXECUTION OF YOUR CONTRACT. IF YOU SEND OR DELIVER YOUR
WRITTEN NOTICE TO CANCEL SOME OTHER WAY, IT MUST BE DELIVERED TO HOOVER AT THE ADDRESS
BELOW NO LATER THAN THE ABOVE SPECIFIED TIMEFRAME. IF YOU PROPERLY AND TIMELY CANCEL THE
CONTRACT, HOOVER WILL REFUND YOUR DEPOSIT (SUBJECT TO CLEARANCE OF ANY DEPOSIT MADE BY
CHECK) WITHIN 10 BUSINESS DAYS, NOT INCLUDING THE DATE HOOVER RECEIVES YOUR WRITTEN NOTICE
OF CANCELLATION. ANY SUCH NOTICE OF CANCELATION SHOULD BE ADDRESSED TO HOOVER CANVAS
PRODUCTS CO., ATTN LUCIE FABIEN, 844 NW. 9TH AVE., FT. LAUDERDALE, FL 33311 EMAIL:
LUCIE@HOOVERAP.COM.
CONSTRUCTION INDUSTRIES RECOVERY FUND. PAYMENT MAY BE AVAILABLE FROM THE CONSTRUCTION
INDUSTRIES RECOVERY FUND IF YOU LOSE MONEY ON A PROJECT PERFORMED UNDER CONTRACT WHERE
THE LOSS RESULTS FROM SPECIFIED VIOLATIONS OF FLORIDA LAW BY A STATE LICENSED CONTRACTOR.
FOR INFORMATION ABOUT THE RECOVERY FUND AND FILING A CLAIM, CONTACT THE FLORIDA
CONSTRUCTION INDUSTRY LICENSING BOARD AT THE FOLLOWING TELEPHONE NUMBER AND ADDRESS.
CONSTRUCTION INDUSTRY LICENSING BOARD, ATTN. RECOVERY FUND, 1940 NORTH MONROE STREET,
SUITE 60, TALLAHASSEE, FL 32399, (850) 921-6539.
RECIPIENT:
Epic Properties
225 Southwest 2nd Terrace
Dania Beach, Florida 33004
Phone: 954-812-0414
Estimate #2839
Sent on Mar 06, 2023
Total $2,600.00
PRODUCT / SERVICE DESCRIPTION QTY.UNIT
PRICE
TOTAL
Re-cover Install new cover at existing awning frame
~55'-6" x 3-0 lean-to style attached to building
Reinforced vinyl fabric: Client's choice of color:
TBD
Hanging Valance: Straight or scalloped TBD
Removal and disposal of old cover
1 $2,600.00 $2,600.00
A deposit of $1,300.00 will be required to begin.
This quote is valid for the next 30 days. Material pricing is secured upon receipt of deposit. 1-year
workmanship warranty. 5-year warranty on heat-sealed seams. Pro-rata warranty on fabric per fabric
manufacturer. Prices include design & engineering. City fees & S/S drawing fees to be added as
applicable. Modifications to existing awning frames or building structure is not included unless specifically
noted. We accept checks, cash, Visa, and MasterCard. 3% service fee applies to all credit card charges.
Delinquent accounts are subject to incur monthly interest of 1.5% on outstanding balance plus collection
costs including attorney's fees. NOTE: Fabric awnings wrinkle. Sunbrella fabric may leak.
Signature: _____________________ Date: _____________
Total $2,600.00
Walker Awning - Sky Awning
5190 NW 10th Terrace
Fort Lauderdale, Florida 33309
954-772-1951
team@walkerawning.com | www.walkerawning.com
Complete Structure Painting, Inc. – Page 1 of 6
COMPLETE STRUCTURE PAINTING, INC.
933-A South State Road 7 ▪ Plantation, FL ▪ 33317
(954) 792-1834 • Fax (954) 584-7253 ▪ LICENSED PAINTING CONTRACTOR
▪ Broward Lic. 10-PU-17100-X ▪ Dade Lic. 12BS00143 ▪ Palm Beach Lic. U-21816
▪ Monroe Lic SP251 ▪ Martin Lic MC1800174 ▪ Collier Lic LCC20180002072
March 28, 2023
TO: Epic Properties
RE: 225 SW Second Terrace
Dania Beach, FL
ATTN: Steve Einhorn
954-812-0414
Einhorn44@yahoo.com
DESCRIPTION: Exterior Painting Proposal for the exterior walls and trim at 225 SW
Second Terrace, Dania Beach, FL. Excluding the backside of the building.
The following is our proposal for the work specified as described.
A. Scope of Work included, but not limited to:
1. Bleach wash and pressure clean all exterior stucco and trim surfaces.
2. Seal all exterior stucco surfaces using one coat of masonry sealer.
3. Patch all hairline cracks and holes using SHERWIN WILLIAMS Elastomeric Smooth
Stucco Patch.
4. Apply SHERWIN WILLIAMS FINEST “LATITUDE” FLAT OR SATIN FINISH
EXTERIOR PREMIUM to all exterior stucco surfaces. Complete Structure Painting, Inc.
and SHERWIN WILLIAMS will warranty for TEN (10) years all new vertical stucco paint
against peeling from previous coating. Color as selected by owner.
5. Spot prime fascia board, and dripcap, and topcoat with SHERWIN WILLIAMS
“LATITUDE” SATIN FINISH. Color as selected by owner.
NOTE: It is the responsibility of the owner to cut shrubbery away from walls and trim trees
away from building, if needed.
Complete Structure Painting, Inc. – Page 2 of 6
B. Scope of work excluded, but not limited to:
1. Exclude any and all windows, window frames, light fixtures, the backside of the
building, AC units, etc. and any area not mentioned in above scope of work.
C. Workmanship:
All materials shall be applied uniformly. If any reduction of the coating's viscosity is
necessary, it shall be done in accordance with the manufacturer's label directions.
Surfaces to be painted shall not be primed until it has been determined these substrates
have dried sufficiently to safely accept paint.
Before painting begins, all other crafts shall have removed dirt and debris resulting
therefrom. The areas are to be left in broom clean condition.
All primers and spot primers are to be allowed to dry completely before applying the finish
coat.
No exterior painting shall be undertaken if air or surface temperature is below 35 degrees
Fahrenheit, nor immediately following rain or until frost, dew or condensation has
evaporated.
D. Materials:
Colors shall be approved. All primers and undercoats are to be tinted to the approximate
selected finish coat if necessary, for better hide.
All paint and coatings will be delivered to the job site in manufacturer's original containers.
E. Preparation of Surfaces:
Complete Structure Painting, Inc. shall be wholly responsible for the quality of work, and
will not commence any part of it until surface is in proper condition.
If we consider any surface unsuitable for proper finishing, we will notify the owner of this
fact in writing. We will not apply any material until corrective measures have been taken or
the owner has instructed us to proceed.
All surfaces will be cleaned, if for any reason the surface cannot be cleaned, this condition
shall be reported to the owner promptly.
If Complete Structure Painting, Inc. has been instructed by the owner to begin painting
under conditions and circumstances we believe could result in poor performance and early
failure of the coatings, we shall request from the owner a decision in writing.
The prime coat will be applied soon after surface preparation has been completed, to
prevent contamination of the substrate.
Complete Structure Painting, Inc. – Page 3 of 6
F. Removal:
Upon completion of an area, it shall be left in a clean and orderly condition, and all paint
spatters, contaminated rags and trash shall be removed.
Upon completion of the job, Complete Structure Painting, Inc. will remove all surplus
materials, scaffolds, etc. from the premises that relate to our project. We shall clean all
window glass free of excess paint and remove paint that has been misplaced on other
surfaces.
EXTERIOR SURFACE PREPARATION AND FINISHING SYSTEM:
A. Exterior Stucco:
Apply commercial mildewcide (chlorine) solution to remove dirt, mildew, and all red and
green mildew. This solution will be allowed to stay on the surface until all mildew has been
killed.
Pressure clean all stucco and masonry surfaces with pressure cleaning equipment using
3,500 p.s.i. to remove as much existing deteriorating coating as possible. All masonry
surfaces will be free of dirt, grease, oil, and chalk. Surfaces will be allowed to dry
thoroughly. If necessary, we will repeat procedure. Multiple coats of paint that are in an
advance state of deterioration will be removed.
NOTE: If aggressive cleaning techniques become necessary for proper preparation to the
substrate, work should cease until an equitable solution can be reached between the
Owner and Contractor as to proceed. This situation will be determined as a concealed
condition.
All cracks in masonry larger than hairline (over 1/16") are to be ground out to form a "V" or
"U" shape and blown or brushed out to remove all dust, dried of all moisture, sealed with
penetrating masonry primer. The resultant opening shall have sealant knifed into
completely fill the void.
Once cured, the filled crack shall be over-coated with knife grade "flexible" sealant, such
as Flex-Lox knife grade, crowned in the center approximately 1/16" and feathered at least
3" on either side of the crack to match the surrounding surface as closely as possible.
All hairline cracks (less than 1/16") will be filled using an approved "flexible" sealant over a
properly primed surface, crowning the application approximately 1/16" over the center of
the crack and feathering the edges approximately 2" on either side to match the adjacent
surface.
Primer: After pressure cleaning and chlorinating apply one coat of SHERWIN WILLIAMS
PREMIUM ACRYLIC MASONRY SEALER.
Apply SHERWIN WILLIAMS Elastomeric as per specifications.
Complete Structure Painting, Inc. – Page 4 of 6
Finish Coat: Apply SHERWIN WILLIAMS FINEST “LATITUDE” 100% ACRYLIC
EXTERIOR PREMIUM.
C ONTRACTOR RESPONSIBILITIES:
A. The Contractor shall supply all labor, materials and equipment necessa ry
for the total completion of the required work as per Sherwin-Williams specifications. The
Contractor shall be responsible for and use care in the protection of the occupant’s
property, such as screens, windows, shrubbery, and walkways, and shall protect other
areas not in this scope of work for paint and/or damage. If such damage occurs, the
Contractor shall be solely responsible for the restoration of such damages caused by
either the Contractor, or any employees of the Contractor. The Contractor shall work with
the manager to arrange for all automobiles and other vehicles to be removed from the
adjacent work areas to safeguard against possible damages.
B. The Contractor shall be responsible for the proper preparation of surfaces to be treated
and will not commence any part of the work until surfaces are in proper condition to
receive the specified system and/or product. In the event Contractor discovers
deteriorated areas or latent defects of structure previously undetected, the repair of which
is not covered under the enclosed specifications, the Contractor shall notify
Owners/Association for further direction.
C. All work shall be performed in a workmanlike manner by skilled mechanics and shall be
carried out in such a way as to minimize any inconvenience to the occupants and tenants.
The Contractor shall maintain a full work force from the start to the completion of the
project providing a qualified foreman on the job site at all times. The Contractor shall
ensure that all such mechanics shall be fully and properly clothed in identifiable uniforms
while working on the premises or entering any part of the work areas.
D. All stages, ladders, and other materials shall be secured at the end of each work day.
Contractor will inspect area as job progresses, and upon completion of the work, the
Contractor shall promptly remove all debris, material and equipment, etc., and shall leave
the premises of the job site clean and orderly. The Contractor shall not be responsible to
clean glass except from new paint drips.
E. The Contractor shall deliver, or have delivered, necessary materials in unopened
containers with the original labels and batch numbers clearly visible. All materials shall
be used in strict adherence to the manufacturer’s written specifications, and/or
recommendations.
F. The Contractor shall arrange with the manager for working space, space for material
storage, and proper access to the areas where the work is to be performed.
G. Contractor will NOT be responsible to clean glass except from new paint drips.
Contractor shall not be responsible for any scratches or imperfections in glass unless
clearly caused by contractor’s negligence. Under no circumstances shall contractor be
responsible for scratches which are of medium or less intensity as defined in ASTM
designation: C1036-91 (Re-approved 1997)
Complete Structure Painting, Inc. – Page 5 of 6
OWNER’S RESPONSIBILITIES:
A. The Owner shall provide proper water and full 20 amps elect ric service
for the preparation of materials and equipment necessary to complete
the work. Use of sanitary facilities shall be used by mutua l consent.
B. It shall be the responsibility o f the Owner to perform any trimming or
pruning of foliage necessary to prevent any problems with the
requirements of the coating work. The Owners shall be re sponsible to
remove or protect loose objects in the work area that are not included in
this scope of work. If such items are not rem oved, the Contractor shall
exercise due diligence to protect any such items, but will not be
responsible for any damages. The Owner shall be responsible for
providing proper parking spaces for vehicles and all equipment
necessary to complete all work.
C. Whenever possible, exterior work shall be performed from the exterior
of the building. However, in the event it becomes necessary to enter
the building, the Owner shal l be present to access and the in
attendance for bu ilding entry.
D. Owner shall notify Contractor, in writing, of any unusual circumstances
(i.e. Lexan glass, hurricane glass, frosted glass, loose tiles and/or
deteriorated tile grout, deteriorated carpet, et c.) which may be present
on the building(s). Contractor shall not assume any respo nsibility or
liability for items of this nature.
SAFETY AND PUBLIC CONVEYANCE :
The Contractor shall rope off and erect warning signs in areas where overspray, dripping, or
any chance of damage or injury could occur. The Contractor shall be responsible for job safety
administrations, including tools, equipment, and work methods, and will be in compliance with the
applicable OSHA safety regulations.
Complete Structure Painting, Inc. – Page 6 of 6
Price for work as detailed in these specifications using QUALITY COMPLETE
STRUCTURE PAINTING, INC. LABOR AND SHERWIN WILLIAMS paint.
LABOR AND MATERIALS COMPLETE: $2,250.00
-This Proposal does not include any permit and/or other municipality fees. Any such
fees shall be additional and paid by the Owner.
-This Proposal will expire in 90 days.
-Any alteration or deviation from the specifications in the Proposal which involves
additional time, materials or costs, will not be performed until there is an agreement
on the scope and cost and Owner executes a written change order.
Payment terms will be 50% at start of job and balance on completion.
Thank you-
_____________________________________ ___________________
Complete Structure Painting, Inc. Date
_____________________________________ ___________________
Epic Properties Date
PROPOSAL
Date
3/1/2023
Name / Address
Steven Einhorn
225 SW 2nd Terrace
Dania Beach, FL 33004
Total
5631 JOHNSON STREET
HOLLYWOOD, FL 33021
FAX (954) 987-0344
GEMCO98@AOL.COM
YOU ARE HEREBY AUTHORIZED TO DO THE WORK SPECIFIED ABOVE.
PAYMENT WILL BE MADE AS OUTLINED. PROPOSAL IS VALID FOR 60
DAYS. PLEASE SIGN AND RETURN TO SCHEDULE WORK.
DATE:_______________________________
SIGNATURE:_______________________________
Description Total
EXTERIOR PAINTING PROPOSAL
3 SIDES OF SAM'S COIN LAUNDRY BUILDING
Pressure clean walls, trim, dumpster fence, tile walls and floors; lightly rinse windows, doors, and canopy
Cover floors, lights, vehicles, etc.
Patch walls as needed with Vinlox masonry patch
SW corner of building - Scrape loose stucco; apply bonding agent. Apply 1 scratch coat of stucco. Apply
1 finish coat of stucco; texture to match as closely to existing as possible
Caulk door frames as needed
Apply sealer to all surfaces being painted
Prime all patches with water-based primer
Prime roll-up and swing doors with DTM primer
Apply 2 coats of high-quality exterior acrylic latex paint to all masonry surfaces, trim, and building letters;
colors to be specified
Apply 1 coat of high-quality solvent-based urethane to swing doors and roll-up doors; color to be specified
Clean up all areas daily.
Certificate of insurance workers compensation and liability and copy of license upon request.
Payment to be made in full upon completion of proposed work 5,200.00
$5,200.00
Sam's Coin Laundry Parking Modifications & Bunker Build Out 225 SW 2 Terrace Dania Beach 4-6-23 AD CTL
PROPOSAL CTL#
Arrow Asphalt & Engineering, Inc.
3050 N.W. 129th Street, Opa Locka, FL 33054
(305) 688-8686 Voice (305) 688-8484 Fax
PROPOSAL SUBMITTED TO: Date: Thursday, April 6, 2023
Client Information Job Site Information
Steve Einhorn Sam's Coin Laundry
Sam's Coin Laundry Parking Area Demo & Restore
225 SW 2 Terrace All Asphalt Parking
Dania Beach, FL 33004 Fabricate Trash Bunker (CBS)
(954) 812-0414 Email: Bollard Installation (4)
We hereby submit specifications and estimates to perform work at the above job site:
1. Demo existing concrete slab. Load and dispose of debris. Approx 1,000 SF............................$2,500.00
2. Furnish & install up to 6" limerock base. Approx. 1,000 SF....................................................$1,500.00
3. Remove existing damaged asphalt in areas to be marked in orange. Load and dispose of debris. Add
limerock, fine grade and compact to 98%. Apply RC 70 tack coat. Pave area with up to 1 1/2" thick type
SP-9.5 hot plant mix asphalt. Compact new asphalt with 5 ton roller & compactor.
Approx. 3,120 SF..........................................................................................................................$15,600.00
4. Demo 6" deep existing material on southside of building. Form and pour new 6"concrete slab
driveway out to street using 3,000 PSI concrete mix. Approx. 500 LF..........................................$6,000.00
5. Excavate 12" existing dirt and grass 30" wide for new spread footer, load and dispose of debris.
Form and pour new spread footer with #5 vertical rebar 4' OC doubled at corner. using 3,000 PSI
concrete mix. Approx. 40 LF..........................................................................................................$2,250.00
6. Furnish and install new 7' high block wall, with cell filled using 3,000 PSI concrete. Furnish and
instal U-block tie beam filled with 3,000 PSI concrete. Approx. 40 LF......................................$5,500.00
7. . Furnish and install 6" thick concrete slab inside walls using 3,000 PSI concrete.
Approx 120 SF................................................................................................................................$1,440.00
8. Furnish and install (4) 6" concrete bollards 2 inside structure at back wall and 2 outside structure to
protect corners of bunker, leave ready for gate installation by others............................................$3,200.00
Total: $37,990.00
*[Add cost of permit processor & permit to total, any additional work will be an extra]
_________________________________________________________________________________________________
We hereby propose to furnish labor and materials to complete in accordance with the above specifications, for the sum of:
Thirty Seven Thousand Nine Hundred Ninety Dollars & 00/100($37,990.00) with 50% deposit, and
remaining balance payment due upon completion of job.
_________________________________________________________________________________________________
Sam's Coin Laundry Parking Modifications & Bunker Build Out 225 SW 2 Terrace Dania Beach 4-6-23 AD CTL
PROPOSAL CTL#
Arrow Asphalt & Engineering, Inc.
3050 N.W. 129th Street, Opa Locka, FL 33054
(305) 688-8686 Voice (305) 688-8484 Fax
PROPOSAL SUBMITTED TO: Date: Thursday, April 6, 2023
Client Information Job Site Information
Steve Einhorn Sam's Coin Laundry
Sam's Coin Laundry Parking Area Demo & Restore
225 SW 2 Terrace All Asphalt Parking
Dania Beach, FL 33004 Fabricate Trash Bunker (CBS)
(954) 812-0414 Email: Bollard Installation (4)
We hereby submit specifications and estimates to perform work at the above job site:
1. Demo existing concrete slab. Load and dispose of debris. Approx 1,000 SF............................$2,500.00
2. Furnish & install up to 6" limerock base. Approx. 1,000 SF....................................................$1,500.00
3. Remove existing damaged asphalt in areas to be marked in orange. Load and dispose of debris. Add
limerock, fine grade and compact to 98%. Apply RC 70 tack coat. Pave area with up to 1 1/2" thick type
SP-9.5 hot plant mix asphalt. Compact new asphalt with 5 ton roller & compactor.
Approx. 3,120 SF..........................................................................................................................$15,600.00
4. Demo 6" deep existing material on southside of building. Form and pour new 6"concrete slab
driveway out to street using 3,000 PSI concrete mix. Approx. 500 LF..........................................$6,000.00
5. Excavate 12" existing dirt and grass 30" wide for new spread footer, load and dispose of debris.
Form and pour new spread footer with #5 vertical rebar 4' OC doubled at corner. using 3,000 PSI
concrete mix. Approx. 40 LF..........................................................................................................$2,250.00
6. Furnish and install new 7' high block wall, with cell filled using 3,000 PSI concrete. Furnish and
instal U-block tie beam filled with 3,000 PSI concrete. Approx. 40 LF......................................$5,500.00
7. . Furnish and install 6" thick concrete slab inside walls using 3,000 PSI concrete.
Approx 120 SF................................................................................................................................$1,440.00
8. Furnish and install (4) 6" concrete bollards 2 inside structure at back wall and 2 outside structure to
protect corners of bunker, leave ready for gate installation by others............................................$3,200.00
Total: $37,990.00
*[Add cost of permit processor & permit to total, any additional work will be an extra]
_________________________________________________________________________________________________
We hereby propose to furnish labor and materials to complete in accordance with the above specifications, for the sum of:
Thirty Seven Thousand Nine Hundred Ninety Dollars & 00/100($37,990.00) with 50% deposit, and
remaining balance payment due upon completion of job.
_________________________________________________________________________________________________
Sam's Coin Laundry Parking Modifications & Bunker Build Out 225 SW 2 Terrace Dania Beach 4-6-23 AD CTL
PROPOSAL CTL#
Arrow Asphalt & Engineering, Inc.
3050 N.W. 129th Street, Opa Locka, FL 33054
(305) 688-8686 Voice (305) 688-8484 Fax
PROPOSAL SUBMITTED TO: Date: Thursday, April 6, 2023
Client Information Job Site Information
Steve Einhorn Sam's Coin Laundry
Sam's Coin Laundry Parking Area Demo & Restore
225 SW 2 Terrace All Asphalt Parking
Dania Beach, FL 33004 Fabricate Trash Bunker (CBS)
(954) 812-0414 Email: Bollard Installation (4)
We hereby submit specifications and estimates to perform work at the above job site:
1. Demo existing concrete slab. Load and dispose of debris. Approx 1,000 SF............................$2,500.00
2. Furnish & install up to 6" limerock base. Approx. 1,000 SF....................................................$1,500.00
3. Remove existing damaged asphalt in areas to be marked in orange. Load and dispose of debris. Add
limerock, fine grade and compact to 98%. Apply RC 70 tack coat. Pave area with up to 1 1/2" thick type
SP-9.5 hot plant mix asphalt. Compact new asphalt with 5 ton roller & compactor.
Approx. 3,120 SF..........................................................................................................................$15,600.00
4. Demo 6" deep existing material on southside of building. Form and pour new 6"concrete slab
driveway out to street using 3,000 PSI concrete mix. Approx. 500 LF..........................................$6,000.00
5. Excavate 12" existing dirt and grass 30" wide for new spread footer, load and dispose of debris.
Form and pour new spread footer with #5 vertical rebar 4' OC doubled at corner. using 3,000 PSI
concrete mix. Approx. 40 LF..........................................................................................................$2,250.00
6. Furnish and install new 7' high block wall, with cell filled using 3,000 PSI concrete. Furnish and
instal U-block tie beam filled with 3,000 PSI concrete. Approx. 40 LF......................................$5,500.00
7. . Furnish and install 6" thick concrete slab inside walls using 3,000 PSI concrete.
Approx 120 SF................................................................................................................................$1,440.00
8. Furnish and install (4) 6" concrete bollards 2 inside structure at back wall and 2 outside structure to
protect corners of bunker, leave ready for gate installation by others............................................$3,200.00
Total: $37,990.00
*[Add cost of permit processor & permit to total, any additional work will be an extra]
_________________________________________________________________________________________________
We hereby propose to furnish labor and materials to complete in accordance with the above specifications, for the sum of:
Thirty Seven Thousand Nine Hundred Ninety Dollars & 00/100($37,990.00) with 50% deposit, and
remaining balance payment due upon completion of job.
_________________________________________________________________________________________________
Sam's Coin Laundry Parking Modifications & Bunker Build Out 225 SW 2 Terrace Dania Beach 4-6-23 AD CTL
PROPOSAL CTL#
Arrow Asphalt & Engineering, Inc.
3050 N.W. 129th Street, Opa Locka, FL 33054
(305) 688-8686 Voice (305) 688-8484 Fax
PROPOSAL SUBMITTED TO: Date: Thursday, April 6, 2023
Client Information Job Site Information
Steve Einhorn Sam's Coin Laundry
Sam's Coin Laundry Parking Area Demo & Restore
225 SW 2 Terrace All Asphalt Parking
Dania Beach, FL 33004 Fabricate Trash Bunker (CBS)
(954) 812-0414 Email: Bollard Installation (4)
We hereby submit specifications and estimates to perform work at the above job site:
1. Demo existing concrete slab. Load and dispose of debris. Approx 1,000 SF............................$2,500.00
2. Furnish & install up to 6" limerock base. Approx. 1,000 SF....................................................$1,500.00
3. Remove existing damaged asphalt in areas to be marked in orange. Load and dispose of debris. Add
limerock, fine grade and compact to 98%. Apply RC 70 tack coat. Pave area with up to 1 1/2" thick type
SP-9.5 hot plant mix asphalt. Compact new asphalt with 5 ton roller & compactor.
Approx. 3,120 SF..........................................................................................................................$15,600.00
4. Demo 6" deep existing material on southside of building. Form and pour new 6"concrete slab
driveway out to street using 3,000 PSI concrete mix. Approx. 500 LF..........................................$6,000.00
5. Excavate 12" existing dirt and grass 30" wide for new spread footer, load and dispose of debris.
Form and pour new spread footer with #5 vertical rebar 4' OC doubled at corner. using 3,000 PSI
concrete mix. Approx. 40 LF..........................................................................................................$2,250.00
6. Furnish and install new 7' high block wall, with cell filled using 3,000 PSI concrete. Furnish and
instal U-block tie beam filled with 3,000 PSI concrete. Approx. 40 LF......................................$5,500.00
7. . Furnish and install 6" thick concrete slab inside walls using 3,000 PSI concrete.
Approx 120 SF................................................................................................................................$1,440.00
8. Furnish and install (4) 6" concrete bollards 2 inside structure at back wall and 2 outside structure to
protect corners of bunker, leave ready for gate installation by others............................................$3,200.00
Total: $37,990.00
*[Add cost of permit processor & permit to total, any additional work will be an extra]
_________________________________________________________________________________________________
We hereby propose to furnish labor and materials to complete in accordance with the above specifications, for the sum of:
Thirty Seven Thousand Nine Hundred Ninety Dollars & 00/100($37,990.00) with 50% deposit, and
remaining balance payment due upon completion of job.
_________________________________________________________________________________________________
Sam's Coin Laundry Parking Modifications & Bunker Build Out 225 SW 2 Terrace Dania Beach 4-6-23 AD CTL
PROPOSAL CTL#
Arrow Asphalt & Engineering, Inc.
3050 N.W. 129th Street, Opa Locka, FL 33054
(305) 688-8686 Voice (305) 688-8484 Fax
PROPOSAL SUBMITTED TO: Date: Thursday, April 6, 2023
Client Information Job Site Information
Steve Einhorn Sam's Coin Laundry
Sam's Coin Laundry Parking Area Demo & Restore
225 SW 2 Terrace All Asphalt Parking
Dania Beach, FL 33004 Fabricate Trash Bunker (CBS)
(954) 812-0414 Email: Bollard Installation (4)
We hereby submit specifications and estimates to perform work at the above job site:
1. Demo existing concrete slab. Load and dispose of debris. Approx 1,000 SF............................$2,500.00
2. Furnish & install up to 6" limerock base. Approx. 1,000 SF....................................................$1,500.00
3. Remove existing damaged asphalt in areas to be marked in orange. Load and dispose of debris. Add
limerock, fine grade and compact to 98%. Apply RC 70 tack coat. Pave area with up to 1 1/2" thick type
SP-9.5 hot plant mix asphalt. Compact new asphalt with 5 ton roller & compactor.
Approx. 3,120 SF..........................................................................................................................$15,600.00
4. Demo 6" deep existing material on southside of building. Form and pour new 6"concrete slab
driveway out to street using 3,000 PSI concrete mix. Approx. 500 LF..........................................$6,000.00
5. Excavate 12" existing dirt and grass 30" wide for new spread footer, load and dispose of debris.
Form and pour new spread footer with #5 vertical rebar 4' OC doubled at corner. using 3,000 PSI
concrete mix. Approx. 40 LF..........................................................................................................$2,250.00
6. Furnish and install new 7' high block wall, with cell filled using 3,000 PSI concrete. Furnish and
instal U-block tie beam filled with 3,000 PSI concrete. Approx. 40 LF......................................$5,500.00
7. . Furnish and install 6" thick concrete slab inside walls using 3,000 PSI concrete.
Approx 120 SF................................................................................................................................$1,440.00
8. Furnish and install (4) 6" concrete bollards 2 inside structure at back wall and 2 outside structure to
protect corners of bunker, leave ready for gate installation by others............................................$3,200.00
Total: $37,990.00
*[Add cost of permit processor & permit to total, any additional work will be an extra]
_________________________________________________________________________________________________
We hereby propose to furnish labor and materials to complete in accordance with the above specifications, for the sum of:
Thirty Seven Thousand Nine Hundred Ninety Dollars & 00/100($37,990.00) with 50% deposit, and
remaining balance payment due upon completion of job.
_________________________________________________________________________________________________
Sam's Coin Laundry Parking Modifications & Bunker Build Out 225 SW 2 Terrace Dania Beach 4-6-23 AD CTL
ACCEPTANCE OF PROPOSAL
The above prices, specifications and conditions are hereby accepted. We have reviewed the important Disclosures and
have provided any special billing instructions on the reverse side. You are authorized to do the work as specified.
Payment will be made as outlined above.
ACCEPTED: AUTHORIZED SIGNATURE:
Signature:__________________________ ________________________________
Arrow Asphalt & Engineering, Inc
Date:___________________
Sam's Coin Laundry Parking Modifications & Bunker Build Out 225 SW 2 Terrace Dania Beach 4-6-23 AD CTL
PROPOSAL CTL#
Arrow Asphalt & Engineering, Inc.
3050 N.W. 129th Street, Opa Locka, FL 33054
(305) 688-8686 Voice (305) 688-8484 Fax
PROPOSAL SUBMITTED TO: Date: Thursday, April 6, 2023
Client Information Job Site Information
Steve Einhorn Sam's Coin Laundry
Sam's Coin Laundry Parking Area Demo & Restore
225 SW 2 Terrace All Asphalt Parking
Dania Beach, FL 33004 Fabricate Trash Bunker (CBS)
(954) 812-0414 Email: Bollard Installation (4)
We hereby submit specifications and estimates to perform work at the above job site:
1. Demo existing concrete slab. Load and dispose of debris. Approx 1,000 SF............................$2,500.00
2. Furnish & install up to 6" limerock base. Approx. 1,000 SF....................................................$1,500.00
3. Remove existing damaged asphalt in areas to be marked in orange. Load and dispose of debris. Add
limerock, fine grade and compact to 98%. Apply RC 70 tack coat. Pave area with up to 1 1/2" thick type
SP-9.5 hot plant mix asphalt. Compact new asphalt with 5 ton roller & compactor.
Approx. 3,120 SF..........................................................................................................................$15,600.00
4. Demo 6" deep existing material on southside of building. Form and pour new 6"concrete slab
driveway out to street using 3,000 PSI concrete mix. Approx. 500 LF..........................................$6,000.00
5. Excavate 12" existing dirt and grass 30" wide for new spread footer, load and dispose of debris.
Form and pour new spread footer with #5 vertical rebar 4' OC doubled at corner. using 3,000 PSI
concrete mix. Approx. 40 LF..........................................................................................................$2,250.00
6. Furnish and install new 7' high block wall, with cell filled using 3,000 PSI concrete. Furnish and
instal U-block tie beam filled with 3,000 PSI concrete. Approx. 40 LF......................................$5,500.00
7. . Furnish and install 6" thick concrete slab inside walls using 3,000 PSI concrete.
Approx 120 SF................................................................................................................................$1,440.00
8. Furnish and install (4) 6" concrete bollards 2 inside structure at back wall and 2 outside structure to
protect corners of bunker, leave ready for gate installation by others............................................$3,200.00
Total: $37,990.00
*[Add cost of permit processor & permit to total, any additional work will be an extra]
_________________________________________________________________________________________________
We hereby propose to furnish labor and materials to complete in accordance with the above specifications, for the sum of:
Thirty Seven Thousand Nine Hundred Ninety Dollars & 00/100($37,990.00) with 50% deposit, and
remaining balance payment due upon completion of job.
_________________________________________________________________________________________________
Sam's Coin Laundry Parking Modifications & Bunker Build Out 225 SW 2 Terrace Dania Beach 4-6-23 AD CTL
PROPOSAL CTL#
Arrow Asphalt & Engineering, Inc.
3050 N.W. 129th Street, Opa Locka, FL 33054
(305) 688-8686 Voice (305) 688-8484 Fax
PROPOSAL SUBMITTED TO: Date: Thursday, April 6, 2023
Client Information Job Site Information
Steve Einhorn Sam's Coin Laundry
Sam's Coin Laundry Parking Area Demo & Restore
225 SW 2 Terrace All Asphalt Parking
Dania Beach, FL 33004 Fabricate Trash Bunker (CBS)
(954) 812-0414 Email: Bollard Installation (4)
We hereby submit specifications and estimates to perform work at the above job site:
1. Demo existing concrete slab. Load and dispose of debris. Approx 1,000 SF............................$2,500.00
2. Furnish & install up to 6" limerock base. Approx. 1,000 SF....................................................$1,500.00
3. Remove existing damaged asphalt in areas to be marked in orange. Load and dispose of debris. Add
limerock, fine grade and compact to 98%. Apply RC 70 tack coat. Pave area with up to 1 1/2" thick type
SP-9.5 hot plant mix asphalt. Compact new asphalt with 5 ton roller & compactor.
Approx. 3,120 SF..........................................................................................................................$15,600.00
4. Demo 6" deep existing material on southside of building. Form and pour new 6"concrete slab
driveway out to street using 3,000 PSI concrete mix. Approx. 500 LF..........................................$6,000.00
5. Excavate 12" existing dirt and grass 30" wide for new spread footer, load and dispose of debris.
Form and pour new spread footer with #5 vertical rebar 4' OC doubled at corner. using 3,000 PSI
concrete mix. Approx. 40 LF..........................................................................................................$2,250.00
6. Furnish and install new 7' high block wall, with cell filled using 3,000 PSI concrete. Furnish and
instal U-block tie beam filled with 3,000 PSI concrete. Approx. 40 LF......................................$5,500.00
7. . Furnish and install 6" thick concrete slab inside walls using 3,000 PSI concrete.
Approx 120 SF................................................................................................................................$1,440.00
8. Furnish and install (4) 6" concrete bollards 2 inside structure at back wall and 2 outside structure to
protect corners of bunker, leave ready for gate installation by others............................................$3,200.00
Total: $37,990.00
*[Add cost of permit processor & permit to total, any additional work will be an extra]
_________________________________________________________________________________________________
We hereby propose to furnish labor and materials to complete in accordance with the above specifications, for the sum of:
Thirty Seven Thousand Nine Hundred Ninety Dollars & 00/100($37,990.00) with 50% deposit, and
remaining balance payment due upon completion of job.
_________________________________________________________________________________________________
Sam's Coin Laundry Parking Modifications & Bunker Build Out 225 SW 2 Terrace Dania Beach 4-6-23 AD CTL
IMPORTANT DISCLOSURES
AND DESIGNATION OF SPECIAL BILLING INSTRUCTIONS
Disclosures:
1.) Bid does not include fees for permits, bonds, engineering stakes layouts, as-builds or densities. A fee of $500.00
will be added if Arrow Asphalt & Engineering Inc. is to apply and be responsible for procurement of permit. No
import or export, excess fill or deterious materials included unless noted (cap-rock, muck, grass, trees, ect.) Not
responsible for errors and/ or omissions by engineer or surveyor. BID PRICE VALID FOR THIRTY (30) DAYS.
2.) A 50% deposit is required upon signed contract to schedule work proposed, balance will be due upon job
completion. DEPOSIT IS NON-RE FUNDABLE
3.) All material guaranteed to be specified, and the above work to be preformed in accordance with the drawings and
specifications submitted for above work and completed in a substantial workmanlike manner.
4.) We guarantee our work not to flake, crack or unravel for a period of one year. We are not responsible for the
wearing off of the material from the top of the asphalt aggregate due to traffic wear.
5.) Any alteration or deviation from the above specifications involving extra costs will be executed only upon written
change order, and will become and extra charge over and above the contract. Bid is based on today's market price for
materials. Any increase in material price at start of job will be extra cost. All agreements contingent upon strikes,
accidents or delays beyond our control.
6.) Prices given without plans and specs are subject to price change when plans are available. Final payment will be
based on actual quantities installed which will be verified by field measurements.
7.) Arrow Asphalt and Engineering is not responsible for delays created by other trades, material suppliers, labor
strikes or acts of God.
8.) Arrow Asphalt and Engineering is not responsible for damage to underground sprinkler's or utilities, sod ,
landscaping, dust removal, painting or stucco, during the normal course of construction.
9.) Claims for property damage must be made in writing 24 hours after the completion of the work. Job related
complaints must be made within 48 hours of completion.
10.) Tree hedges and grass to be trimmed prior to the commencement of work.
11.) Seal Coating and striping to be completed in one mobilization. Additional mobilization are additional costs to
the contract. Additional mobilizations are $1,200.00 per mobilization.
12.) Arrow Asphalt and Engineering is not responsible for the following but not limited to the tracking of the sealer
on pavers, driveways, sidewalks or any other areas besides roadway. Sealed areas will be blocked off until dry.
13.) A 1.5% finance charge per month shall be added to any invoice 30 days past due.
14.) This proposal is based on work being completed during the hours of 8am- 5pm, Monday - Friday excluding
Holidays and Weekends. No warranties are honored unless payment is made in full. Arrow Asphalt & Engineering
will provide a one (1) year warranty on material and workmanship. Normal wear and tear is not covered under this
warranty.
15.) Due to the instability in today's market, Arrow Asphalt & Engineering, Inc. cannot guarantee unit prices
for any materials, All increases in material costs will be added to cost of contract.
16.)Asphalt unit price predicated on asphalt costing $110.00 per ton, asphalt will be requoted at time of
installation and client to be responsible for difference in cost plus 15% DRE mark-up for overhead and
profit, change order to be executed prior to installation of asphalt.
Initial _______
Sam's Coin Laundry Parking Modifications & Bunker Build Out 225 SW 2 Terrace Dania Beach 4-6-23 AD CTL
PROPOSAL CTL#
Arrow Asphalt & Engineering, Inc.
3050 N.W. 129th Street, Opa Locka, FL 33054
(305) 688-8686 Voice (305) 688-8484 Fax
PROPOSAL SUBMITTED TO: Date: Thursday, April 6, 2023
Client Information Job Site Information
Steve Einhorn Sam's Coin Laundry
Sam's Coin Laundry Parking Area Demo & Restore
225 SW 2 Terrace All Asphalt Parking
Dania Beach, FL 33004 Fabricate Trash Bunker (CBS)
(954) 812-0414 Email: Bollard Installation (4)
We hereby submit specifications and estimates to perform work at the above job site:
1. Demo existing concrete slab. Load and dispose of debris. Approx 1,000 SF............................$2,500.00
2. Furnish & install up to 6" limerock base. Approx. 1,000 SF....................................................$1,500.00
3. Remove existing damaged asphalt in areas to be marked in orange. Load and dispose of debris. Add
limerock, fine grade and compact to 98%. Apply RC 70 tack coat. Pave area with up to 1 1/2" thick type
SP-9.5 hot plant mix asphalt. Compact new asphalt with 5 ton roller & compactor.
Approx. 3,120 SF..........................................................................................................................$15,600.00
4. Demo 6" deep existing material on southside of building. Form and pour new 6"concrete slab
driveway out to street using 3,000 PSI concrete mix. Approx. 500 LF..........................................$6,000.00
5. Excavate 12" existing dirt and grass 30" wide for new spread footer, load and dispose of debris.
Form and pour new spread footer with #5 vertical rebar 4' OC doubled at corner. using 3,000 PSI
concrete mix. Approx. 40 LF..........................................................................................................$2,250.00
6. Furnish and install new 7' high block wall, with cell filled using 3,000 PSI concrete. Furnish and
instal U-block tie beam filled with 3,000 PSI concrete. Approx. 40 LF......................................$5,500.00
7. . Furnish and install 6" thick concrete slab inside walls using 3,000 PSI concrete.
Approx 120 SF................................................................................................................................$1,440.00
8. Furnish and install (4) 6" concrete bollards 2 inside structure at back wall and 2 outside structure to
protect corners of bunker, leave ready for gate installation by others............................................$3,200.00
Total: $37,990.00
*[Add cost of permit processor & permit to total, any additional work will be an extra]
_________________________________________________________________________________________________
We hereby propose to furnish labor and materials to complete in accordance with the above specifications, for the sum of:
Thirty Seven Thousand Nine Hundred Ninety Dollars & 00/100($37,990.00) with 50% deposit, and
remaining balance payment due upon completion of job.
_________________________________________________________________________________________________
Sam's Coin Laundry Parking Modifications & Bunker Build Out 225 SW 2 Terrace Dania Beach 4-6-23 AD CTL
PROPOSAL CTL#
Arrow Asphalt & Engineering, Inc.
3050 N.W. 129th Street, Opa Locka, FL 33054
(305) 688-8686 Voice (305) 688-8484 Fax
PROPOSAL SUBMITTED TO: Date: Thursday, April 6, 2023
Client Information Job Site Information
Steve Einhorn Sam's Coin Laundry
Sam's Coin Laundry Parking Area Demo & Restore
225 SW 2 Terrace All Asphalt Parking
Dania Beach, FL 33004 Fabricate Trash Bunker (CBS)
(954) 812-0414 Email: Bollard Installation (4)
We hereby submit specifications and estimates to perform work at the above job site:
1. Demo existing concrete slab. Load and dispose of debris. Approx 1,000 SF............................$2,500.00
2. Furnish & install up to 6" limerock base. Approx. 1,000 SF....................................................$1,500.00
3. Remove existing damaged asphalt in areas to be marked in orange. Load and dispose of debris. Add
limerock, fine grade and compact to 98%. Apply RC 70 tack coat. Pave area with up to 1 1/2" thick type
SP-9.5 hot plant mix asphalt. Compact new asphalt with 5 ton roller & compactor.
Approx. 3,120 SF..........................................................................................................................$15,600.00
4. Demo 6" deep existing material on southside of building. Form and pour new 6"concrete slab
driveway out to street using 3,000 PSI concrete mix. Approx. 500 LF..........................................$6,000.00
5. Excavate 12" existing dirt and grass 30" wide for new spread footer, load and dispose of debris.
Form and pour new spread footer with #5 vertical rebar 4' OC doubled at corner. using 3,000 PSI
concrete mix. Approx. 40 LF..........................................................................................................$2,250.00
6. Furnish and install new 7' high block wall, with cell filled using 3,000 PSI concrete. Furnish and
instal U-block tie beam filled with 3,000 PSI concrete. Approx. 40 LF......................................$5,500.00
7. . Furnish and install 6" thick concrete slab inside walls using 3,000 PSI concrete.
Approx 120 SF................................................................................................................................$1,440.00
8. Furnish and install (4) 6" concrete bollards 2 inside structure at back wall and 2 outside structure to
protect corners of bunker, leave ready for gate installation by others............................................$3,200.00
Total: $37,990.00
*[Add cost of permit processor & permit to total, any additional work will be an extra]
_________________________________________________________________________________________________
We hereby propose to furnish labor and materials to complete in accordance with the above specifications, for the sum of:
Thirty Seven Thousand Nine Hundred Ninety Dollars & 00/100($37,990.00) with 50% deposit, and
remaining balance payment due upon completion of job.
_________________________________________________________________________________________________
Sam's Coin Laundry Parking Modifications & Bunker Build Out 225 SW 2 Terrace Dania Beach 4-6-23 AD CTL
Paving Commercial/ Owner Responsibility & Conditions
1.) Barricaded Parking Lot: It is vital that all vehicles are removed from our area of work no later than 7:15am unless
otherwise agreed. As you can imagine, our project costs are based on the property having all cars, people and objects
off the area of work. Tow Trucks need to be arranged 5 days prior to the start of any work and be on call to remove
cars from the scheduled work area. If any cars are left in the area of work, we cannot be held responsible for any
damage to the vehicles. There will be additional costs if we are unable to access the work area billed at a minimum
of $2,500.00
2.) Site service: The management company / property owner is responsible to notify all landscapers and garbage
companies to not show up in the area of work the day we are performing work. In the event of a reschedule due to
unforseen conditions, you are required to let all service providers know about the change.
3.) Rain: If it is raining the day of scheduled service, assume we will not be coming and we will contact you to
reschedule as soon as possible. If it rains after our installation, please contact our representative. We monitor the
weather closely and can generally predict this very well. In the event that an unexpected storm happens, we will
touch up any areas any areas where sealer has not bonded.
4.) Sprinklers: Should be off 24 hours prior and 48 hours after service. Avoid lawn cutting during this same period
of time. The surface must be dry for our arrival. Areas where the newly sealed pavement is wet may wear
prematurely.
5.) Drainage: Arrow Asphalt and Engineering cannot guarantee 100% drainage in areas where the design grade is
less than 1% fall.
6.) Asphalt Over-Runs: Will be billed to owner at $150.00 per ton.
Pricing does not include asphalt leveling unless stated otherwise in the original scope of work. Owners agrees to
leveling at $185.00 per ton.
7.) Reflective Cracking: Arrow Asphalt and Engineering will not accept responsibility for reflective cracking of new
asphalt overlay due to the cracked conditions of the existing asphalt pavement.
8.) Driving on surface: Once you start driving on paved/ sealed surface, avoid turning your wheels unless your car is
moving. We understand this may be difficult to do, but understand that when wheels are turned on freshly paved/
sealed asphalt surface, scuffing and turn marks will be evident, no worries in time they will blend with surrounding
surface.
Other Terms and Conditions:
1.) 90% of contract amount and change orders must be paid prior to completing punch list items and/ or any changes
for additional work required by cities or municipalities.
2.) Towing fees, if necessary, billed as actual. Any vehicles left in the construction area at the commencement of the
work will be relocated on site and billed to the Owner/Authorized Agent
3.) Change orders, additions or extras requested by Owner, Contractor or Municipality will be invoiced as an
addition to the contact and shall not delay payment of the original contract sum. All Change Orders must be
approved and signed by management/ Board President/ Building Owner (whichever applies.)
4.) Arrow Asphalt and Engineering will not be responsible for paint adhesion to car stops that have not been pressure
cleaned.
5.) Cannot guarantee sealcoat longevity where there is standing water. Cracks in pavement will still be noticeable
after sealcoating. Tire turning marks will be visible at first but will disappear over time.
8.) Additional mobilization to be billed at $1,200.00 each for sealcoating. This charge may be billed due to, but not
limited to: site unavailability for commencement of work due to vehicles encroaching on the work area, change of
schedule by Other/ Authorized Agent without prior consent of contractor or repairs to work caused by tresspassing.
Initial _______
Sam's Coin Laundry Parking Modifications & Bunker Build Out 225 SW 2 Terrace Dania Beach 4-6-23 AD CTL
PROPOSAL CTL#
Arrow Asphalt & Engineering, Inc.
3050 N.W. 129th Street, Opa Locka, FL 33054
(305) 688-8686 Voice (305) 688-8484 Fax
PROPOSAL SUBMITTED TO: Date: Thursday, April 6, 2023
Client Information Job Site Information
Steve Einhorn Sam's Coin Laundry
Sam's Coin Laundry Parking Area Demo & Restore
225 SW 2 Terrace All Asphalt Parking
Dania Beach, FL 33004 Fabricate Trash Bunker (CBS)
(954) 812-0414 Email: Bollard Installation (4)
We hereby submit specifications and estimates to perform work at the above job site:
1. Demo existing concrete slab. Load and dispose of debris. Approx 1,000 SF............................$2,500.00
2. Furnish & install up to 6" limerock base. Approx. 1,000 SF....................................................$1,500.00
3. Remove existing damaged asphalt in areas to be marked in orange. Load and dispose of debris. Add
limerock, fine grade and compact to 98%. Apply RC 70 tack coat. Pave area with up to 1 1/2" thick type
SP-9.5 hot plant mix asphalt. Compact new asphalt with 5 ton roller & compactor.
Approx. 3,120 SF..........................................................................................................................$15,600.00
4. Demo 6" deep existing material on southside of building. Form and pour new 6"concrete slab
driveway out to street using 3,000 PSI concrete mix. Approx. 500 LF..........................................$6,000.00
5. Excavate 12" existing dirt and grass 30" wide for new spread footer, load and dispose of debris.
Form and pour new spread footer with #5 vertical rebar 4' OC doubled at corner. using 3,000 PSI
concrete mix. Approx. 40 LF..........................................................................................................$2,250.00
6. Furnish and install new 7' high block wall, with cell filled using 3,000 PSI concrete. Furnish and
instal U-block tie beam filled with 3,000 PSI concrete. Approx. 40 LF......................................$5,500.00
7. . Furnish and install 6" thick concrete slab inside walls using 3,000 PSI concrete.
Approx 120 SF................................................................................................................................$1,440.00
8. Furnish and install (4) 6" concrete bollards 2 inside structure at back wall and 2 outside structure to
protect corners of bunker, leave ready for gate installation by others............................................$3,200.00
Total: $37,990.00
*[Add cost of permit processor & permit to total, any additional work will be an extra]
_________________________________________________________________________________________________
We hereby propose to furnish labor and materials to complete in accordance with the above specifications, for the sum of:
Thirty Seven Thousand Nine Hundred Ninety Dollars & 00/100($37,990.00) with 50% deposit, and
remaining balance payment due upon completion of job.
_________________________________________________________________________________________________
Sam's Coin Laundry Parking Modifications & Bunker Build Out 225 SW 2 Terrace Dania Beach 4-6-23 AD CTL
PROPOSAL CTL#
Arrow Asphalt & Engineering, Inc.
3050 N.W. 129th Street, Opa Locka, FL 33054
(305) 688-8686 Voice (305) 688-8484 Fax
PROPOSAL SUBMITTED TO: Date: Thursday, April 6, 2023
Client Information Job Site Information
Steve Einhorn Sam's Coin Laundry
Sam's Coin Laundry Parking Area Demo & Restore
225 SW 2 Terrace All Asphalt Parking
Dania Beach, FL 33004 Fabricate Trash Bunker (CBS)
(954) 812-0414 Email: Bollard Installation (4)
We hereby submit specifications and estimates to perform work at the above job site:
1. Demo existing concrete slab. Load and dispose of debris. Approx 1,000 SF............................$2,500.00
2. Furnish & install up to 6" limerock base. Approx. 1,000 SF....................................................$1,500.00
3. Remove existing damaged asphalt in areas to be marked in orange. Load and dispose of debris. Add
limerock, fine grade and compact to 98%. Apply RC 70 tack coat. Pave area with up to 1 1/2" thick type
SP-9.5 hot plant mix asphalt. Compact new asphalt with 5 ton roller & compactor.
Approx. 3,120 SF..........................................................................................................................$15,600.00
4. Demo 6" deep existing material on southside of building. Form and pour new 6"concrete slab
driveway out to street using 3,000 PSI concrete mix. Approx. 500 LF..........................................$6,000.00
5. Excavate 12" existing dirt and grass 30" wide for new spread footer, load and dispose of debris.
Form and pour new spread footer with #5 vertical rebar 4' OC doubled at corner. using 3,000 PSI
concrete mix. Approx. 40 LF..........................................................................................................$2,250.00
6. Furnish and install new 7' high block wall, with cell filled using 3,000 PSI concrete. Furnish and
instal U-block tie beam filled with 3,000 PSI concrete. Approx. 40 LF......................................$5,500.00
7. . Furnish and install 6" thick concrete slab inside walls using 3,000 PSI concrete.
Approx 120 SF................................................................................................................................$1,440.00
8. Furnish and install (4) 6" concrete bollards 2 inside structure at back wall and 2 outside structure to
protect corners of bunker, leave ready for gate installation by others............................................$3,200.00
Total: $37,990.00
*[Add cost of permit processor & permit to total, any additional work will be an extra]
_________________________________________________________________________________________________
We hereby propose to furnish labor and materials to complete in accordance with the above specifications, for the sum of:
Thirty Seven Thousand Nine Hundred Ninety Dollars & 00/100($37,990.00) with 50% deposit, and
remaining balance payment due upon completion of job.
_________________________________________________________________________________________________
Sam's Coin Laundry Parking Modifications & Bunker Build Out 225 SW 2 Terrace Dania Beach 4-6-23 AD CTL
9.) Additional mobilizations to be billed at $3,000.00 each for Concrete Services. This charge may be billed due to,
but not limited to site unavailability for commencement of work due to vehicles encroaching on the work area,
change of schedule by Owner/ Authorized agent without prior consent of contractor or repairs to work caused by
tresspassing.
10.) Additional mobilizaions to be billed at $2,500.00 for paving. This charge may be billed due to, but not limited
to: site unavailability for commencement of the work to due to vehicles encroaching on the work area, change of
schedule by Owner/ Authorized agent without prior consent of contractor or repairs to work caused by tresspassing.
Arrow Asphalt and Engineering will provide a schedule to be approved by Owner prior to any additional
mobilizations.
11.) Saturday mobilizations will be an additional $2,000.00.
12.) Arrow Asphalt and Engineering cannot guarantee 100% drainage in areas where the design grade is less than
1% fall.
Special Billing Instructions:
Please fill out the information below:
Specify Billing Information:
Company Name:______________________________________
Contact Person: ______________________________________
Address: ______________________________________
______________________________________
Phone Number: ______________________________________
Purchase Order: ______________________________________
Provide email for eBilling:______________________________
Please note any particular forms, documents, and/or procedures required prior to release of payment:
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Initial _______
Dumpster Enclosure & Parking Lot
Steve Einhorn 225 SW 2nd Terrace, Dania
Beach 33004.
HRT Construction Group, LLC
DUMPSTER ENCLOSURE & PARKING LOT
Client Name: Steve Einhorn
Address: 14711 SW 42nd Terr
We hereby propose to complete the repairs and improvements shown below.
DUMPSTER ENCLOSURE & PARKING LOT ESTIMATE
Scope of Work: Detailed description below
Material Selection: Selected finish materials for the space
Payment Terms: Payment schedule based on percentage project completion
Project Schedule: Estimated length of project completion
Estimated Project Cost: List of materials that will be purchased to complete the scope of work.
Submitted by:
William Hall
HRT Construction Group, LLC
786.646.6730 Ext:701
Cell: 786.325.1884
*The final construction amount can vary beyond these figures based on
and mechanical conditions.
225 SW 2nd Terrace, Dania
Beach 33004.
HRT Construction Group, LLC CGC1527561
DUMPSTER ENCLOSURE & PARKING LOT ESTIMATE
Estimate valid
We hereby propose to complete the repairs and improvements shown below.
DUMPSTER ENCLOSURE & PARKING LOT ESTIMATE
description below
Selected finish materials for the space.
Payment schedule based on percentage project completion
Estimated length of project completion
List of materials that will be purchased to complete the scope of work.
*The final construction amount can vary beyond these figures based on client selections, and further evaluation of existing structural
Estimate Laundry
ESTIMATE
valid for 15 days from:
03/21/2023
List of materials that will be purchased to complete the scope of work.
client selections, and further evaluation of existing structural
HRT Construction Group, LLC
SCOPE OF WORK
SECTION 1: PRECONSTRUCTION:
ENGINEERING SERVICES
o ONSITE INSPECTION AND SITE MEASUREMENTS
o SIGNED/SEALED ENGINEERING DRAWINGS
(3) THREE ROUNDS OF REVISION WITH THE CITY
o STRUCTURAL DESIGN CALCULATIONS
o PRELIMINARY DRAWING REVIEW WITH THE OWNER.
o PERMIT READY PLANS
SECTION 2: GENERAL CONDITIONS:
PERMIT PROCESSING WITH THE CITY
HRT PROJECT MANAGEMENT
CITY INSPECTIONS
MOBILIZATION INCL. BONDS, ETC.
SECTION 3: DEMOLITION
REMOVAL of existing structure AND HAULing
Bobcat Services
o EXCAVATION FOR FOUNDATION WALLS
DUMPSTER ON SITE
REMOVE AND HAUL LEFTOVER DEBRIS
SECTION 4: SLAB WORK
FRAME & POUR CONCRETE FOUNDATION FOOTERS AND SLAB
o FRAMING, REBAR, WIRE MESH
POUR 300 SQFT AT A 6"SLAB
APPROACH 90SQFT AT 6" THICKNESS
BOLLARDS DIG 6" AND FILLED
FOLLOWING FLORIDA BUILDING CODE 2020 & CITY REQUIREMENTS
SECTION 4: Masonry Work
FOLLOWING FLORIDA BUILDING CODE 2020 & CITY REQUIREMENTS
INSTALL (2) CMU WALLS 8’ W X 6’ H
CREATE A 36” W OPENING ON THE SIDE OF THE ENCLOSURE FOR ACCESS
STUCCO FINISH
HRT Construction Group, LLC CGC1527561
SCOPE OF WORK: DUMPSTER ENCLOSURE
ONSITE INSPECTION AND SITE MEASUREMENTS
SIGNED/SEALED ENGINEERING DRAWINGS
(3) THREE ROUNDS OF REVISION WITH THE CITY
STRUCTURAL DESIGN CALCULATIONS
PRELIMINARY DRAWING REVIEW WITH THE OWNER.
MIT PROCESSING WITH THE CITY
INCL. BONDS, ETC.
REMOVAL of existing structure AND HAULing
EXCAVATION FOR FOUNDATION WALLS, slab, and ROW approach
REMOVE AND HAUL LEFTOVER DEBRIS
FOUNDATION FOOTERS AND SLAB
MESH, CONCRETE, AND BOLLARD MAT
THICKNESS
FOLLOWING FLORIDA BUILDING CODE 2020 & CITY REQUIREMENTS
ING FLORIDA BUILDING CODE 2020 & CITY REQUIREMENTS
8’ W X 6’ H PER PROVIDED PLAN SET BY CITY REQUIREMENTS
CREATE A 36” W OPENING ON THE SIDE OF THE ENCLOSURE FOR ACCESS
Estimate Laundry
CITY REQUIREMENTS
HRT Construction Group, LLC
INSTALL (2) BOLLARDS AT 6' H (SCHEDULE 40 STEEL 6"
SECTION 5: Welding Work
FABRICATE AND INSTALL A 12’ W X 6’ H METAL GATE
o INSTALL THE GATE TO THE STEEL
FABRICATE AND INSTALL A 36” W X 6’ H METAL GATE
SECTION 6: Finish
PER PROVIDED A PLAN SET
EXTERIOR PAINT OF THE NEW ADDITION
o MATCH THE EXISTING PAINT COLOR
o MATCH THE EXISTING TEXTURE
SECTION 7: CLEAN UP AND DISPOSAL
LEAVE THE JOBSITE BROOM CLEAN DAILY
REMOVAL OF ALL DEBRIS FROM THE SITE AS NEEDED
LEAVE ALL SPACE CLEAN AND READY TO OCCUPY UPON COMPLETION
SECTION 8: NOT INCLUDED
CITY PERMIT FEES
LANDSCAPING
ITEMS
Material
Labor
TOTAL
The anticipated duration of this project
does not include building & zoning review and approval time.
before we can confirm a start date. The project start date is predicated on
times.
HRT Construction Group, LLC CGC1527561
AT 6' H (SCHEDULE 40 STEEL 6")
FABRICATE AND INSTALL A 12’ W X 6’ H METAL GATE
INSTALL THE GATE TO THE STEEL BOLLARDS
FABRICATE AND INSTALL A 36” W X 6’ H METAL GATE
OR PAINT OF THE NEW ADDITION
MATCH THE EXISTING PAINT COLOR
MATCH THE EXISTING TEXTURE
LEAVE THE JOBSITE BROOM CLEAN DAILY
REMOVAL OF ALL DEBRIS FROM THE SITE AS NEEDED
LEAVE ALL SPACE CLEAN AND READY TO OCCUPY UPON COMPLETION
ESTIMATE PROJECT
PROJECT DURATION:
project construction is 2.75 – 3.75 weeks after city approval
does not include building & zoning review and approval time. All product selections will need to be made
before we can confirm a start date. The project start date is predicated on product availability and lead
Estimate Laundry
AMOUNT
$12,636.70
$30,348.55
$42,985.25
after city approval. The duration
All product selections will need to be made
product availability and lead
HRT Construction Group, LLC
SCOPE OF WORK: ASPHALT MILLING & PAVING AND STENCILING
SECTION 1: PRECONSTRUCTION
ENGINEERING SERVICES
o ONSITE INSPECTION AND SITE MEASUREMENTS
o AS-BUILT DRAWINGS
(3) THREE ROUNDS OF REVISION WITH THE CITY
o PERMIT READY PLANS
SECTION 2: GENERAL CONDITIONS
PERMIT PROCESSING WITH THE CITY
HRT PROJECT MANAGEMENT
CITY INSPECTIONS
MOBILIZATION INCL. BONDS, ETC
SECTION 3: ASPHALT MILLING OF EXISTING PAVEMENT SURFACE
MILLING OF DAMAGED ASPHALT PAVEMENT.
REMOVAL & DISPOSAL OF ALL MILLED MATERIAL.
SUPPLY AND COMPACT LIMEROCK AS MAY BE NEEDED.
CLEANING OF PREPARED MILLED SURFACE USING MECHANICAL BROOM.
SECTION 4: ASPHALT PAVING
PREPARATION OF PAVEMENT AREA FOR ASPHALT PAVING.
SAW CUT, REMOVAL & DISPOSAL
ABUTTING EDGES TO DOORS, SIDEWALKS, WALKWAYS, ETC.
CLEAN THE ENTIRE EXISTING ASPHALT AREA TO BE OVERLAYED
APPLICATION OF SS-1H TACK COAT TO PROMOTE ADHESION BETWEEN PREPARED SURFACE AND
PRECEDING ASPHALT SURFACE.
FILLING IN AND ROLLING OF LOW
PAVE PREPARED AREAS USING ASPHALT PLANT HOT MIX
ROLLING AND COMPACTION OF SPREAD ASPHALT USING A 4
RE-SETTING AND INSTALLATION OF REMOV
SECTION 5: CLEAN UP AND DISPOSAL
LEAVE THE JOBSITE BROOM CLEAN DAILY
REMOVAL OF ALL DEBRIS FROM THE SITE AS NEEDED
HRT Construction Group, LLC CGC1527561
ASPHALT MILLING & PAVING AND STENCILING
ONSITE INSPECTION AND SITE MEASUREMENTS
(3) THREE ROUNDS OF REVISION WITH THE CITY
MIT PROCESSING WITH THE CITY
MOBILIZATION INCL. BONDS, ETC.
ASPHALT MILLING OF EXISTING PAVEMENT SURFACE
MILLING OF DAMAGED ASPHALT PAVEMENT.
REMOVAL & DISPOSAL OF ALL MILLED MATERIAL.
SUPPLY AND COMPACT LIMEROCK AS MAY BE NEEDED.
CLEANING OF PREPARED MILLED SURFACE USING MECHANICAL BROOM.
PREPARATION OF PAVEMENT AREA FOR ASPHALT PAVING.
SAW CUT, REMOVAL & DISPOSAL OF A 2' PERIMETER AROUND DRAIN INLETS, MANHOLE COVERS, AND
ABUTTING EDGES TO DOORS, SIDEWALKS, WALKWAYS, ETC.
CLEAN THE ENTIRE EXISTING ASPHALT AREA TO BE OVERLAYED
1H TACK COAT TO PROMOTE ADHESION BETWEEN PREPARED SURFACE AND
FILLING IN AND ROLLING OF LOW-LYING ASPHALT AREAS BEFORE ASPHALT OVERLAY.
PAVE PREPARED AREAS USING ASPHALT PLANT HOT MIX
ROLLING AND COMPACTION OF SPREAD ASPHALT USING A 4-5 TON VIBRATORY ROLLER.
SETTING AND INSTALLATION OF REMOVED CAR STOPS.
LEAVE THE JOBSITE BROOM CLEAN DAILY
REMOVAL OF ALL DEBRIS FROM THE SITE AS NEEDED
Estimate Laundry
ASPHALT MILLING & PAVING AND STENCILING
OF A 2' PERIMETER AROUND DRAIN INLETS, MANHOLE COVERS, AND
1H TACK COAT TO PROMOTE ADHESION BETWEEN PREPARED SURFACE AND
LYING ASPHALT AREAS BEFORE ASPHALT OVERLAY.
5 TON VIBRATORY ROLLER.
HRT Construction Group, LLC
LEAVE ALL SPACE CLEAN AND READY TO OCCUPY UPON COMPLETION
SECTION 6: NOT INCLUDED
CITY PERMIT FEES
LANDSCAPING
ESTIMATE PROJECT RAN
*Once the site inspection is completed, we would be able to provide a formal proposal.
The anticipated duration of this project construction is
does not include building & zoning review and approval time.
before we can confirm a start date. The project start date is predicated on product availability and lead
times.
10% Signing non-refundable deposit
20% Notice to Proceed
30% progress payments
30% progress payments
10% upon substantial completion.
HRT Construction Group, LLC CGC1527561
LEAVE ALL SPACE CLEAN AND READY TO OCCUPY UPON COMPLETION
ESTIMATE PROJECT RANGE*
$ 18,922 - $23,750
Once the site inspection is completed, we would be able to provide a formal proposal.
PROJECT DURATION:
he anticipated duration of this project construction is 0.75 – 1.75 weeks after city approval
does not include building & zoning review and approval time. All product selections will need to be made
before we can confirm a start date. The project start date is predicated on product availability and lead
PAYMENT TERMS
Progress
refundable deposit CONTRACT AGREEMENT
MOBILIZATION
60% COMPLETION
90% COMPLETION
100% COMPLETION
Estimate Laundry
Once the site inspection is completed, we would be able to provide a formal proposal.
.75 weeks after city approval. The duration
All product selections will need to be made
before we can confirm a start date. The project start date is predicated on product availability and lead
Progress
CONTRACT AGREEMENT
MOBILIZATION
60% COMPLETION
90% COMPLETION
100% COMPLETION
HRT Construction Group, LLC
CONSTRUCTION PROCESS
ESTIMATE: FREE BALLPARK COSTS
PRE-CONSTRUCTION SERVICES: PROVIDE A
DETAILED BUDGET TO FOLLOW. SERVICE FEE (CREDIT WILL BE APPLIED IF AWARDED)
CONTRACT AGREEMENT: CONTRACT SIGNING MEETING WITH CONTRACTOR AND OWNER
KICK-OFF MEETING: PROVIDE PRELIMINARY CONSTRUCTION SCHEDULE AND PERMIT DOCUMENTS PROCESS
MOBILIZATION: START OF THE CONSTRUCTION
INSPECTIONS: CITY INSPECTION, PUNCH LIST, SUBSTANTIAL COMPLETI
POST-CONSTRUCTION MEETING: PROJECT CLOSE
WARRANTY PERIOD: PERFORMANCE & COOPERATION. END
HRT Construction Group, LLC CGC1527561
CONSTRUCTION PROCESS FLOW
ESTIMATE AND DURATION
: PROVIDE A MORE EXACT COST ESTIMATION, BETTER DECISION
. SERVICE FEE (CREDIT WILL BE APPLIED IF AWARDED)
CONTRACT SIGNING MEETING WITH CONTRACTOR AND OWNER
PROVIDE PRELIMINARY CONSTRUCTION SCHEDULE AND PERMIT DOCUMENTS PROCESS
START OF THE CONSTRUCTION
: CITY INSPECTION, PUNCH LIST, SUBSTANTIAL COMPLETION, AND FINAL APPROVAL
PROJECT CLOSE-OUT, PROVIDE PRODUCT AND WORKMANSHIP WARRANTIES
: PERFORMANCE & COOPERATION. END-OF-WARRANTY INSPECTIONS
Estimate Laundry
MORE EXACT COST ESTIMATION, BETTER DECISION-MAKING, AND A
CONTRACT SIGNING MEETING WITH CONTRACTOR AND OWNER
PROVIDE PRELIMINARY CONSTRUCTION SCHEDULE AND PERMIT DOCUMENTS PROCESS
ON, AND FINAL APPROVAL
OUT, PROVIDE PRODUCT AND WORKMANSHIP WARRANTIES
-OF-WARRANTY INSPECTIONS
CITY OF DANIA BEACH
COMMUNITY REDEVELOPMENT AGENCY MEETING DATES
JANUARY 2024 – DECEMBER 2024
CRA Meeting Date
2nd Tuesdays – 5:30 p.m.**Holidays and/or Events**
January 9, 2024
February 13, 2024
March 12, 2024
April 9, 2023
May 14, 2024
June 11, 2024
July 9, 2024
August 13, 2024 Commission Summer Break
September 10, 2024
October 8, 2024
November 12, 2024
(Special, CRA & Regular
Meeting)
Special Meeting for 11/5 General
Election Confirmation
December 10, 2024