HomeMy WebLinkAboutR-2026-078 SE Drainage Project Change Order #8RESOLUTION NO. 2026-078
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA, AUTHORIZING THE APPROVAL OF CHANGE ORDER
NO. 08 RELATED TO THE SE DRAINAGE RETROFIT PROJECT WITH RIC-
MAN CONSTRUCTION INC. FOR SIX HUNDRED SEVENTY-SEVEN
THOUSAND SIX HUNDRED EIGHTY-SIX DOLLARS AND EIGHTY SIX
CENTS ($677,686.86); PROVIDING FOR CONFLICTS; FURTHER,
PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, During ongoing construction activities for the SE Drainage Retrofit Project
Phase 1, the City, Engineer of Record (EOR), Construction Engineering and Inspection (CEI)
team, and Contractor identified several field-condition adjustments, quantity overruns, operational
modifications, utility coordination requirements, and constructability-related items necessary to
complete the project in accordance with the intended drainage performance objectives of the
approved scope; and
WHEREAS, the additional work included in this CO remains within the overall Project
scope and supports completion of the approved drainage infrastructure and associated roadway
improvements, and includes removal and modification of drainage structures; pump station bypass
improvements; additional roadway, sidewalk, paver, and driveway restoration; additional drainage
pipe and fittings required during construction; and
WHEREAS, Ric-Man Construction Inc. submitted Change Order No. 08, which is
attached as Exhibit “A” and incorporated into this Resolution by this reference, in the total amount
of $677,686.86 to perform the aforementioned tasks among other modifications; and
WHEREAS, Change Order No. 08 will primarily be derived from available underrun bid
items identified throughout the project, with current underrun balances totaling approximately
$1,032,562.47, which exceeds the value of the proposed change order; and
WHEREAS, the total cost of Change Order No. 08 is $677,686.86, and the City Commission
authorizes the utilization of available underrun bid item balances within the Contract to fund the
additional work associated with this change order.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF DANIA BEACH, FLORIDA:
Section 1. That the above “Whereas” clauses are ratified and confirmed, and they are
made a part of and incorporated into this Resolution by this reference.
2 RESOLUTION #2026-078
Section 2. That the City Commission hereby approves Change Order No. 08 with Ric-
Man Construction Inc. for the total amount of Six Hundred Seventy-Seven Thousand Six Hundred
Eighty Six Dollars and Eight Six Cents ($677,686.86).
Section 3. That the City Commission authorizes the utilization of available underrun
bid item balances within the contract to fund the additional work associated with change order No.
08.
Section 4. That current underrun bid item balances total approximately $1,032,562.47
and exceed the value of Change Order No. 08 in the amount of $677,686.86.
Section 5. That all resolutions or parts of resolutions in conflict with this Resolution
are repealed to the extent of such conflict.
Section 6. That this Resolution shall be effective immediately after passage.
PASSED AND ADOPTED on June 9, 2026.
Motion by Commissioner Lewellen, second by Commissioner Rimoli.
FINAL VOTE ON ADOPTION: Unanimous ____
Yes No
Commissioner Lori Lewellen X ____
Commissioner Luis Rimoli X ____
Commissioner Archibald J. Ryan IV X ____
Vice Mayor Marco Salvino X ____
Mayor Joyce L. Davis ABSENT FOR VOTE
ATTEST:
ELORA RIERA, MMC MARCO A. SALVINO, SR.
CITY CLERK VICE-MAYOR
APPROVED AS TO FORM AND CORRECTNESS:
EVE A. BOUTSIS
CITY ATTORNEY
CITY OF DANIA BEACH
CHANGE ORDER
Change Order No.: 08 Date: May 22nd, 2026
Project: SE DRAINAGE PHASE I
Project No.: DANI-017
Contractor: Ric-Man Construction Florida, Inc.
DESCRIPTION OF WORK:
REASON:
Following is the work included in this Change Order:
1- Removal of Drainage Structures
2- Modification of Structures
3- Pipe Removal
4- Pump Station Bypass
5- Pavers, Arch Concrete, Sidewalk, Asphalt Driveway Repairs
6- Asphalt on Swale Areas
7- Superpave Asphaltic Concrete, TraAic Level A
8- Utility Fitting, DI/CI, Furnish & Install Reducer 20-49.9"
9- Inlets, DT Bot, Type D < 10'
10- Pipe Culvert, Optional Material Round, 15" SD
11- Pipe Culvert, Optional Material Round, 24" SD
12- Regular Excavation
13- Utility Pipe PVC, Furnish and Install 12"
14- Driveways, Other (Gravel)
15- MOT
16- Changes JS-01
17- Change Inlets to Manholes
18- Driveways Impacted by Change in Roadway Profile
19- Electrical Ductbank, TC Meters Enclosure
1- Removal of drainage structures to allow new construction.
2- Modification of several drainage structures to adjust to existing conditions.
3- Removal of existing drainage pipe to allow new construction.
4- A bypass was added to the pump station to allow the use of a portable in case of breakdown.
5- There is an overrun on the quantity of pavers, concrete and asphalt driveways repairs.
6- There is an overrun on the quantity of asphalt to be installed in swale areas.
7- Several street segments were added to the scope of work and the quantity of asphalt was
increased.
8- There was not enough quantity of force main reducers in the contract.
9- There is an overrun on the Ditch Bottom Inlet, Type D<10.
10- There is an overrun on the 15” culvert pipe installed.
11- There is an overrun on the 24” culvert pipe installed.
12- The regular excavation item was increased due to the pipe segments added to the scope.
Continue on Page 2
SE Drainage Project Phase I - City of Dania Beach
Change Order 08
Page 2 of 4
REASON: (Continuation)
13- There is an overrun on the 15” culvert pipe installed.
14- There is an overrun on the quantity of gravel driveways.
15- There was not enough quantity of MOT days in the contract.
16- Some changes were introduced to the installation of junction structure JS-01.
17- The EOR requested changing two drainage structures from inlets to manholes.
18- Several driveways need reconstruction due to changes in the roadway profile.
19- The electrical ductbank was not included in the electrical pay items. The CT meters
enclosure was requested by FPL.
SE Drainage Project Phase I - City of Dania Beach
Change Order 08
Page 3 of 4
0 Calendar Days
$677,686.86
GRANTED TIME DUE TO DELAYS IN CRITICAL ACTIVITIES:
Note: The work included in this Change Order is concurrent with FPL delays. Any time extension
required will be addressed in a separate Change Order related to the FPL delays.
TOTAL COST OF WORK
Change Order 08 - Cost Breakdown
Item Description Qty. Unit Unit Price Amount
1 Removal of Drainage Structures 2 EA $3,000.00 $6,000.00
2 Modification of Structures 11 EA $566.30 $6,229.30
3 Pipe Removal 193 LF $77.00 $14,861.00
4 Pump Station Bypass 1 LS $22,142.00 $22,142.00
5 Pavers, Arch Concrete, Sidewalk, Asphalt Driveway Repairs 208 SY $218.00 $45,344.00
6 Asphalt on Swale Areas 788 SY $165.00 $130,020.00
7 Superpave Asphaltic Concrete, Traffic Level A 230 TN $220.00 $50,600.00
8 Utility Fitting, DI/CI, Furnish & Install Reducer 20-49.9" 6 EA $1,818.00 $10,908.00
9 Inlets, DT Bot, Type D < 10' 3 EA $15,656.00 $46,968.00
10 Pipe Culvert, Optional Material Round, 15" SD 32.00 LF $212.00 $6,784.00
11 Pipe Culvert, Optional Material Round, 24" SD 234.00 LF $345.00 $80,730.00
12 Regular Excavation 206.00 CY $15.00 $3,090.00
13 12" PVC utility pipe 9.00 LF $330.00 $2,970.00
14 Driveways, Other(Gravel) 99.00 SY $111.00 $10,989.00
15 MOT 1.00 LS $135,000.00 $135,000.00
16 Changes JS-01 1.00 LS $19,886.00 $19,886.00
17 Change Inlets to Manholes 1.00 LS $14,063.00 $14,063.00
18 Driveways Impacted by Change in Roadway Profile 1.00 LS $31,864.07 $31,864.07
19 Electrical Ductbank, TC Meters Enclosure 1.00 LS $39,238.49 $39,238.49
TOTAL $677,686.86
Requested by:
Tyson DiPetrillo Date
Project Manager – Ric Man Construction, Inc.
Recommended by:
Hugo E. Da Silva, P.E. Date
Project Administrator - CEI
Concurrence:
Luis Soto, P.E. on behalf of Luis Soto Date
Engineer of Record - WSP, Inc.
5/27/2026
5/27/2026
SE Drainage Project Phase I - City of Dania Beach
Change Order 08
Page 4 of 4
Approved by:
Alvaro Cortes Date
Senior Project Manager - City of Dania Beach
Approved by:
Yeimi Guzman Date
Chief Financial OAicer
Approved by:
Date Candido Sosa-Cruz
City Manager - City of Dania Beach