HomeMy WebLinkAboutR-2026-104 Third Amendment with WSP Inc.RESOLUTION NO. 2026-104 A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DANIA BEACH, FLORIDA, AUTHORIZING THE PROPER CITY OFFICIALS TO EXECUTE THE THIRD AMENDMENT TO THE AGREEMENT WITH WSP USA, INC. FOR ADDITIONAL ENGINEERING SERVICES ASSOCIATED WITH THE SOUTHEAST DRAINAGE IMPROVEMENT PROJECT – PHASE I, IN AN AMOUNT NOT TO EXCEED NINE THOUSAND TWO HUNDRED EIGHTY-ONE DOLLARS AND SEVENTY-FIVE CENTS ($9,281.75); PROVIDING FOR A FUNDING APPROPRIATION; PROVIDING FOR CONFLICTS; AND PROVIDING FOR AN EFFECTIVE DATE. WHEREAS, the City of Dania Beach is currently implementing the Southeast Drainage Improvement Project – Phase I; and WHEREAS, during final coordination with Florida Power & Light (FPL), the electrical service configuration for the project pump stations was modified from the originally anticipated transformer arrangement, requiring revisions to the electrical design documents; and WHEREAS, WSP USA, Inc., the Engineer of Record for the project, submitted a proposal to provide the engineering services necessary to update the electrical plans, calculations, and related technical documentation associated with the revised transformer configuration and location; and WHEREAS, the proposed Third Amendment includes technical coordination services and electrical design modifications necessary to maintain consistency with FPL’s final service requirements; and WHEREAS, the Public Services Department recommends approval of the Third Amendment with WSP USA, Inc. in the amount of Nine Thousand Two Hundred Eighty-One Dollars and Seventy-Five Cents ($9,281.75). NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF DANIA BEACH, FLORIDA: Section 1. That the above “Whereas” clauses are ratified and confirmed, and they are made a part of and incorporated into this Resolution by this reference. Section 2. The City Commission hereby authorizes the proper City officials to execute the Third Amendment with WSP USA, Inc. for additional engineering services associated with the Southeast Drainage Improvement Project – Phase I, in an amount not to exceed Nine Thousand Two Hundred Eighty-One Dollars and Seventy-Five Cents ($9,281.75), which Amendment is attached hereto as Exhibit “A”. 2 RESOLUTION #2026-104 Section 3. That funding will be appropriated within Stormwater Account No. 403-38- 01-538-31-10, and will increase the existing Purchase Order by $9,281.75. Section 4. That all resolutions or parts of resolutions in conflict with this Resolution are repealed to the extent of such conflict. Section 5. That this Resolution shall be effective 10 days after passage. PASSED AND ADOPTED on August 25, 2026 Motion by Commissioner Ryan, seconded by Commissioner Lewellen. FINAL VOTE ON ADOPTION: Unanimous X Yes No Commissioner Lori Lewellen Commissioner Luis Rimoli Commissioner Archibald J. Ryan IV Vice Mayor Marco Salvino Mayor Joyce L. Davis APPROVED AS TO FORM AND CORRECTNESS: JOYCE L. DAVIS MAYOR 1 THIRD AMENDMENT TO AN EXISTING AGREEMENT BETWEEN THE CITY OF DANIA BEACH, FLORIDA AND WSP USA, INC. INC. FOR SERVICES RELATED TO THE SOUTHEAST DRAINAGE PROJECT AND AMENDING THE EXISTING AGREEMENT TO PROVIDE ADDITIONAL SERVICES IN THE PROJECT SCOPE AND DELIVERABLES. This is the Third Amendment to an Agreement existing between the City of Dania Beach, Florida, a Florida municipal corporation and WSP USA, Inc. Contractor foreign corporation registered to conduct business in Florida, having its local office located at Corporate Center Drive, Suite , Miami, Florida 33126. The original Agreement dated May 13, 2021, is made a part of and is incorporated into this Amendment by this reference. In consideration of the mutual covenants, terms and conditions contained in the Amendment, and other good and valuable consideration, the adequacy and receipt of which are acknowledged and agreed upon, the parties agree as follows: 1.The Parties acknowledge and agree upon the changes in Scope as shown in the attached “Scope and Fee Proposal Amendment” which incorporated by this reference and Attached to this amendment as Exhibit “A”. 2.That in all other respects, the Agreement, and all Exhibits to it, are ratified and reaffirmed, and remains in full force and effect. SIGNATURES ON THE FOLLOWING PAGES EXHIBIT C (Description of work to be performed, approximate time frame, cost.) CITY OF DANIA BEACH, FLORIDA WORK ORDER This is a Work Order, dated June 11, 20_26, issued by the City of Dania Beach, Florida (the “City”) to ________WSP USA___________________ (the “Consultant”), in connection with an Agreement dated _______July 28________, 2020_, existing between the City and the Consultant, which Agreement is incorporated by this reference. The Consultant shall perform work (the “Work”) for the City as described in Exhibit C, a copy of which is attached and incorporated by this reference. The Work Order and any and all timeframes pertinent to the Work are specified in that Exhibit. IN WITNESS OF THE FOREGOING, the parties have set their hands and seals the day and year first above written. CITY: ATTEST: CITY OF DANIA BEACH, FLORIDA a Florida Municipal Corporation ELORA RIERA, MMC CANDIDO SOSA-CRUZ, ICMA-CM CITY CLERK CITY MANAGER APPROVED FOR FORM AND CORRECTNESS: EVE A. BOUTSIS CITY ATTORNEY 2 WITNESSES: CONSULTANT: WSP USA, Inc., a foreign corporation registered to conduct business in Florida. SIGNATURE SIGNATURE PRINT Name PRINT Name SIGNATURE Title PRINT Name STATE OF FLORIDA COUNTY OF ______________ The foregoing instrument was acknowledged before me on ________________ 20___, by __________________, as of ______________________________, a Florida corporation, on behalf of the corporation. He/she is personally known to me or produced __________________________________ as identification and did (did not) take an oath. NOTARY PUBLIC My Commission Expires: State of Florida WSP USA Suite F 7255 Corporate Center Drive Miami, FL 33126 Tel.: +1 305 514-3100 Fax: +1 305 261-5735 April 27, 2026 Via email: acortes@daniabeachfl.gov Alvaro Cortes Senior Project Manager 1201 Stirling Road, Dania Beach, FL 33004 SE Drainage Project - Phase 1 (Amendment – FPL Transformer Location Modification) Dear Mr. Cortes, The City of Dania Beach has requested WSP USA Inc. (WSP) provide design support during construction for Phase 1 modifications associated with Florida Power & Light (FPL) changes to the transformer configuration and location serving the pump stations. These changes require revisions to the electrical design documents to remain consistent with FPL’s final service conditions. This proposal incorporates the electrical modification services described in the attached subcontractor proposal from Premiere Design Solutions, Inc. (PDS), including updates to electrical plans and calculations to accommodate a pole-mounted transformer (300 kVA) and revised available fault current. In addition, WSP will provide technical coordination support by Luis Soto to coordinate with PDS, the City, FPL, and the contractor during the modification effort. SCOPE OF SERVICES Based on our understanding of the issue, please find below a description of the proposed scope of work associated with this Phase 1 Amendment for modifications to the transformer location and related electrical design updates. Task 1 – Technical Coordination (WSP – Luis Soto) WSP will provide technical coordination led by Luis Soto to support implementation of the transformer location modification. Coordination activities include meetings and technical communications with PDS, the City, FPL, and the contractor; review of proposed electrical approach and interfaces with other disciplines; and tracking/closure of electrical-related RFIs and field coordination items associated with the change. Task 2 – Electrical Design Modifications (Subconsultant – PDS) PDS will update electrical plans and calculations to accommodate FPL’s final transformer configuration and service conditions, including a pole-mounted transformer (300 kVA) and WSP USA Suite F 7255 Corporate Center Drive Miami, FL 33126 Tel.: +1 305 514-3100 Fax: +1 305 261-5735 revised available fault current. PDS scope includes (as described in the attached proposal): coordination with the City, contractor, and FPL; review and update of short-circuit calculations; evaluation of impacts to breaker AIC ratings and equipment SSCCR; revisions to the single line diagram, panel schedules, equipment callouts, and applicable details (including trenching and service connection details); review of updated shop drawings; internal QA/QC; and delivery of revised signed and sealed electrical drawings and calculations. PDS will assist as needed with permit modification support. Deliverables Revised electrical drawings and calculations (signed and sealed by the electrical EOR) reflecting the final transformer location/configuration and updated service conditions. COMPENSATION WSP will perform the work as specified in this scope of services for a total lump sum fee of $9,281.75. A breakdown is provided below. Item Description Fee 1 PDS Electrical design modifications for FPL transformer location/configuration change (Task 6), including revised calculations and signed/sealed electrical plan updates. $7,281.75 2 WSP Technical coordination (Luis Soto) with PDS, City, FPL, and contractor. $2,000.00 Total $9,281.75 DELIVERY SCHEDULE Delivery Schedule: PDS will complete the electrical design modifications within one (1) week of written Notice to Proceed (NTP), consistent with the attached PDS proposal. WSP technical coordination will occur during the same period (and as needed to support review cycles and field coordination). CLOSURE We appreciate your consideration and look forward to the continued success of the project. If this proposal is acceptable to you, please sign below as your formal authorization to proceed and return a copy for our files. If you have questions, please call us at 305-514-3100. Sincerely, Judeen Johnson WSP Project Manager WSP USA Suite F 7255 Corporate Center Drive Miami, FL 33126 Tel.: +1 305 514-3100 Fax: +1 305 261-5735 AUTHORIZATION Receipt of this proposal, including the General Terms and Conditions annexed hereto, is hereby acknowledged and all of the terms and conditions contained therein and accepted. Approved City of Dania Beach _______________________________________ ________________ Name/Title Date 05/07/2026 WSP USA Suite F 7255 Corporate Center Drive Miami, FL 33126 Tel.: +1 305 514-3100 Fax: +1 305 261-5735 EXHIBIT A Exhibit A: Premiere Design Solutions, Inc. (PDS) proposal for electrical design modifications associated with the FPL transformer location/configuration change. PREMIERE DESIGN SOLUTIONS, INC 12781 Miramar Parkway, Suite 205, Miramar, FL 33027 Tel: (954) 237-7850 Fax: (954) 337-2332 April 20, 2026 Ms. Judeen Johnson South Florida Water Leader WSP USA, Inc. 7255 Corporate Center Dr., Suite F Miami, FL 33162 judeen.johnson@wsp.com REF: Professional Engineering Services Proposal Dania Beach Southeast Drainage – Design Modifications for FPL Transformer Change Broward County, Florida PDS Project Number 18110013.1 Dear Ms. Johnson: Premiere Design Solutions, Inc. (PDS) is pleased to submit this proposal for the above referenced project to WSP USA (WSP), Inc. (Client), to provide Professional Engineering Support Services for this project in the City of Dania Beach, located in Broward County (County), Florida. It is our understanding that the contractor has proposed some changes due to the change from FPL in the type of transformer. Initial coordination with FPL resulted in pad mounted transformers located next to the proposed pump station platform. However, during final testing, FPL changed the transformer from pad mounted to pole mounted on the other side of the street from the proposed platforms. This would require modifications on the plans to be consistent with the final FPL design. This will generate additional engineering effort, not included in the original scope of work. PDS will be responsible for the Electrical Design only for the proposed Pump changes and modifications. No other modifications are included. SCOPE OF SERVICES In order to meet the Client’s need for this project, PDS will need to complete the following tasks to develop the PDS assigned tasks described above: Task 6: FPL Transformer Change This task should be an additional task added to our previously approved scope of work, and is to make the necessary electrical design and calculations modifications, to accommodate the new pole mounted transformer at the location and with the capacity as per the final design of FPL. The work includes to update the latest version of electrical plans and calculations to incorporate the service conditions provided by FPL, including the new pole mounted transformer rated 300 kVA and the newly revised available short-circuit current. PREMIERE DESIGN SOLUTIONS, INC 12781 Miramar Parkway, Suite 205, Miramar, FL 33027 Tel: (954) 237-7850 Fax: (954) 337-2332 The work will include the following: •Coordination with City, Contractor and FPL for the new configuration and type of transformer including virtual meetings. •Analyze the updated utility information, including the transformer (Pole mounted 300 kVA) and available fault current •Review and update short-circuit calculations to reflect revised conditions •Evaluate the impact of increased available fault current on the electrical distribution system •Review and update drawing as required based on the impact of the revised available fault current on breaker AIC ratings and equipment SSCCR •Revise the single line diagram as required to reflect the updated service conditions •Update panel schedules and equipment callouts as required •Revise the applicable electrical details including trenching and service connection details •Review any updated shop drawings •Perform internal QA/QC of drawings and calculations •Provide updated revised signed and sealed drawings by the electrical EOR •Assist as needed in the permit modification Deliverables of this task will include a PDF and AutoCAD file format, signed and sealed by a Florida Registered professional engineer, reflecting all plan modifications required due to the new transformer layout. PROPOSED TIME SCHEDULE PDS will make all necessary adjustments to meet the project schedule and complete design modification within one week of written NTP. PROPOSED FEES The above services will be provided for a lump sum fee of $ 7,281.75, to be billed upon completion. We value the opportunity to provide our professional services on this exciting project. If you decide to accept this proposal, please sign below and return an executed copy to our office. If you have any questions please call us at (954)-237-7850. Sincerely, PREMIERE DESIGN SOLUTIONS, Inc. Luis J. Jurado, P.E. President PREMIERE DESIGN SOLUTIONS, INC 12781 Miramar Parkway, Suite 205, Miramar, FL 33027 Tel: (954) 237-7850 Fax: (954) 337-2332 Contract Terms and Agreements 1.This contract agreement is for a lump sum fee. Any work performed outside of the scope of work outlined in this proposal will be billed based in the hourly rates provided herein with written approval from the Client. 2.Invoices are due net 30 days from invoice date. 3.Any invoices past due more than 30 days will accrue a 1.5% interest per month fee. Cost of these services are: $ 7,281.75 Lump Sum. CONTRACT AGREEMENT ACCEPTANCE Premiere Design Solutions, Inc. WSP USA, Inc. 4/20/26 PREMIERE DESIGN SOLUTIONS, INC. QA/QC $75.00 2.85 $213.75 1 2 3 $641.25 Project Manager $75.00 2.85 $213.75 7 3 10 $2,137.50 Project Engineering $45.00 2.85 $128.25 3 13 16 $2,052.00 Drafting Technician $30.00 2.85 $85.50 0 27 27 $2,308.50 Administrative Support $25.00 2.85 $71.25 2 0 2 $142.50 13 45 58 $2,237.25 $5,044.50 $7,281.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $2,237.25 $5,044.50 LABOR SUBTOTALS: Hourly Billing Rate Labor Multiplier Raw Hourly Rate Electrcial Engineering Design Modifications General Coordination Hrs Subtotals ATTACHMENT A Fee Breakdown Summary PDS Project No.18110013.1 Dania Beach Southeast Drainage – Electrical Modifications for FPL Transformer Change Professional Engieneering Services Man Hour Estimate and Fee Proposal Task 6BTask 6A $0.00SUBTOTAL EXPENSES: Permit Fees Not Included (To be paid by Owner or Client) Project Role Subtotal Labor Hours: Costs TOTAL LABOR & EXPENSES $7,281.75 Summary of Direct Expenses Reimbursable Expenses (Mileage, Printing, Tolls, Parking, Postage, Records Fees, Etc.)