HomeMy WebLinkAboutR-2026-146 S3S Construction Award and Agreement - Fire House 1 Wind Retrofit (ITB 26-009)RESOLUTION NO. 2026-146
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA, AUTHORIZING THE AWARD OF INVITATION TO BID
(ITB) NO. 26‑009, “FIRE STATION NO. 1 WIND RETROFIT PROJECT,” TO
S3S CONSTRUCTION INC. IN AN AMOUNT NOT TO EXCEED ONE
MILLION EIGHTY‑FOUR THOUSAND THREE HUNDRED THIRTY
DOLLARS AND FIFTY CENTS ($1,084,330.50); AUTHORIZING THE
PROPER CITY OFFICIALS TO EXECUTE AN AGREEMENT FOR
SERVICES WITH S3S CONSTRUCTION INC.; AND TO EXCEED THE
ANNUAL SINGLE‑VENDOR PURCHASING THRESHOLD OF FIFTY
THOUSAND DOLLARS ($50,000.00); PROVIDING FOR FUNDING;
PROVIDING FOR CONFLICTS; AND PROVIDING FOR AN EFFECTIVE
DATE.
WHEREAS, the Dania Beach Code of Ordinances, Chapter 2, Article 1, Section 2-10,
“Monetary thresholds for certain purchases and payment disbursement authorizations”,
Subsection (a), sets the monetary threshold at Fifty Thousand Dollars ($50,000.00) for a vendor
each fiscal year; and
WHEREAS, Fire Station No. 1 serves as a critical emergency response facility for the
City of Dania Beach and must remain operational before, during, and after severe weather events
and other emergencies; and
WHEREAS, the City developed the Fire Station No. 1 Wind Retrofit Project to improve
the resiliency of the facility by implementing wind mitigation measures designed to reduce
damage from hurricanes and other severe weather events; and
WHEREAS, the project includes structural, electrical, civil, and site improvements,
including replacement of exterior doors, roll-up bay doors, roofing, louvers, roof access
components, construction of a new concrete generator slab, installation of the City-furnished 250-
kW diesel emergency generator, automatic transfer switch (ATS), annunciator, associated
electrical equipment, utility coordination, testing and commissioning, and all related work
necessary to provide a complete and operational wind retrofit project; and
WHEREAS, the City publicly advertised Invitation to Bid (ITB) No. 26-009, "Fire
Station No. 1 Wind Retrofit Project," in accordance with the City's procurement requirements;
and
WHEREAS, bids were publicly opened on July 24, 2026, and five (5) responsive bids
were received; and
WHEREAS, Procurement completed its review for responsiveness, and the Engineer of
Record reviewed the technical qualifications and bid submissions; and
RESOLUTION #2026-146
WHEREAS, Di Pompeo Construction Inc. submitted the lowest responsive and
responsible bid in the amount of $982,342.99; and
WHEREAS, the City and Di Pompeo Construction Inc. were unable to reach an
agreement on the contract, and the City therefore did not proceed with an award to Di Pompeo
Construction Inc.; and
WHEREAS, S3S Construction Inc. submitted the next available lowest bid in the amount
of $1,084,330.50, and the Public Services Department recommends award of ITB No. 26-009 to
S3S Construction Inc. and approval of the Construction Agreement for completion of the Fire
Station No. 1 Wind Retrofit Project; and
WHEREAS, the total project authorization shall not exceed $1,192,763.55; and
WHEREAS, funding for this project will be appropriated from Grant Account No. 103-
18-65-519-63-10. This project is fully funded through the FDEM grant.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF DANIA BEACH, FLORIDA:
Section 1. That the above “Whereas” clauses are ratified and confirmed, and they are
made a part of and incorporated into this Resolution by this reference.
Section 2. That the City Commission hereby authorizes the award of Invitation to Bid
(ITB) No. 26-009, "Fire Station No. 1 Wind Retrofit Project," to S3S Construction Inc. in the
amount of $1,084,330.50, which will exceed the annual vendor threshold of $50,000.00.
Section 3. That the City Commission hereby approves the Construction Agreement
between the City of Dania Beach and S3S Construction Inc. completion of Fire Station No. 1
Wind Retrofit Project.
Section 4. That the total project authorization, including a 10 percent contingency,
shall not exceed $1,084,330.50.
Section 5. That funding for this project will be appropriated from the Grant Fund
Account No. 103-22-65-522-63-10 in the amount of $1,084,330.50.
Section 6. That funding will be reallocated from CSLIP Cycle 9 Project Account No.
301-15-05-515-31-10 in the amount of $314,810.00, EOC Project Account No. 301-22-04-522-
31-10 in the amount of $108,696.00, and from Community Shuttle Account No. 001-39-01-539-
31-60 in the amount of $5,253.21.
RESOLUTION #2026-146
Section 7. That the City Manager, or designee, is hereby authorized to take all
administrative actions reasonably necessary to implement the bid award authorized herein, and
authorize the appropriate City officials to execute the agreement.
Section 8. That the use of contingency funds in the amount of $98,575.50 may be
approved by the City Manager through written request by the Public Services Department upon
receipt of written change orders from the vendor.
Section 9. That all resolutions or parts of resolutions in conflict with this Resolution
are repealed to the extent of such conflict.
Section 10. That this Resolution shall become effective immediately after adoption.
PASSED AND ADOPTED on October 13, 2026.
Motion by Commissioner Lewellen, second by Commissioner Rimoli.
FINAL VOTE ON ADOPTION: Unanimous X
Yes No
Commissioner Lori Lewellen ____ ____
Commissioner Luis Rimoli ____ ____
Commissioner Archibald J. Ryan IV ____ ____
Vice Mayor Marco Salvino ____ ____
Mayor Joyce L. Davis ____ ____
ATTEST:
ELORA RIERA, MMC JOYCE L. DAVIS
CITY CLERK MAYOR
APPROVED AS TO FORM AND CORRECTNESS:
EVE A. BOUTSIS
CITY ATTORNEY
1
CONSTRUCTION AGREEMENT
FIRE STATION NO. 1 WIND RETROFIT PROJECT
ITB NO. 26-009 | HMGP PROJECT NO. DR-4337-285-R
This Construction Agreement (the “Agreement”) is entered into on _______________, 2026 by
and between the City of Dania Beach, Florida, a Florida municipal corporation (the “City” or
“Owner”), and S3S Construction, Inc., a Florida profit corporation, Document No. P17000046730
(the “Contractor”). The City and Contractor may each be called a “Party” and together the
“Parties.”
RECITALS
A. Fire Station No. 1, located at 116 West Dania Beach Boulevard, is an essential public-safety
facility that must remain capable of supporting fire-rescue operations during hurricanes, utility
outages and other emergencies.
B. The City developed the Fire Station No. 1 Wind Retrofit Project to harden the facility against
extreme wind events and complete the structural, roofing, electrical, civil and site improvements
necessary to provide a complete, resilient and operational facility and emergency-power system.
C. The City publicly advertised Invitation to Bid No. 26-009, “Fire Station No. 1 Wind Retrofit
Project,” in accordance with the City’s procurement requirements.
D. Bids were publicly opened on July 24, 2026, and, following review by the City’s Procurement
Division and Engineer of Record, Contractor was determined to be the second lowest responsive
and responsible bidder, with a total bid of $1,084,330.50, inclusive of a $25,000.00 permitting
allowance and an $98,575.50contingency.
E. By Resolution No. 2026-TBD adopted October 13, 2026, the City Commission awarded ITB
No. 26-009 to Contractor in the amount of $1,084,330.50, approved this Agreement, and
authorized its execution by the appropriate City officials.
F. The Project is funded in whole or in part through the Hazard Mitigation Grant Program, Project
No. DR-4337-285-R, as approved by the Florida Division of Emergency Management and the
Federal Emergency Management Agency, and Contractor acknowledges that the Work is subject
to the applicable grant requirements incorporated into the Contract Documents.
G. Contractor represents that it is qualified, licensed, adequately staffed and financially able to
perform the Work, has examined the Contract Documents and Project Site, and has included in its
Contract Sum all labor, supervision, materials, equipment, coordination, temporary facilities,
testing, permits, overhead, profit and incidentals necessary for a complete and operational Project.
.
2
NOW, THEREFORE, for good and valuable consideration, the Parties agree as follows:
ARTICLE 1
DEFINITIONS AND CONTRACT DOCUMENTS
1.1 Definitions.
(a) “Change Order” means a written instrument signed by the City Manager or other official
possessing lawful authority and by Contractor that adjusts the Contract Sum, Contract Time, or
both. No oral direction, field condition, meeting note, email, submittal review, inspection, or
course of conduct is a Change Order.
(b) “City Representative” means the City employee or consultant identified in the Notice to
Proceed or later designated in writing. The City Representative may administer and inspect the
Work but may not amend this Agreement or authorize additional compensation or time unless
separately vested with that authority.
(c) “Contract Documents” means this executed Agreement; approved Change Orders; written
addenda; the Special Conditions; the General Conditions and federal requirements in the ITB; the
technical specifications; plans and drawings; the Scope of Work incorporated by reference as
Exhibit A; Contractor’s accepted price schedule incorporated by reference as Exhibit B; the federal
and grant provisions incorporated by reference as Exhibit C; only those additional portions of
Contractor’s bid expressly accepted by the City; and the Notice to Proceed. Contractor terms,
exclusions, qualifications, assumptions or boilerplate are excluded unless expressly stated in a
signed Change Order.
(d) “Final Completion” means completion of all Work, correction of all punch-list items, delivery
and City acceptance of all closeout documents, releases, warranties, training, manuals, as-builts
and required approvals, and satisfaction of all other conditions for final payment.
(e) “Substantial Completion” means the stage at which the Work is complete, code-compliant,
commissioned, approved for intended use by authorities having jurisdiction, and capable of safe
and uninterrupted operation for the City, except for minor punch-list items that do not impair
operation, safety, security or access.
(f) “Work” means everything required by the Contract Documents to deliver a complete, tested,
commissioned, code-compliant and fully operational wind-retrofitted fire station and emergency-
power system, together with a fully restored Project Site, whether or not every incidental item is
specifically identified.
1.2 Order of precedence.
In a conflict, the more stringent requirement and the requirement producing the more complete,
safe and functional Project controls, subject to the following order:
3
(1) executed Change Orders;
(2) this Agreement;
(3) written addenda, in reverse chronological order;
(4) Special Conditions;
(5) General Conditions and federal requirements;
(6) technical specifications;
(7) plans and drawings;
(8) scope of work;
(9) City-issued bid forms; and
(10) Contractor’s accepted price schedule.
Contractor shall promptly request a written interpretation before proceeding with affected Work.
Contractor’s failure to do so waives any claim based on the conflict to the extent it could have
been avoided.
1.3 Entire agreement; no reliance.
The Contract Documents are the entire agreement. Contractor acknowledges that it has not relied
on any oral statement, estimate, schedule, representation or promise not stated in the Contract
Documents. No purchase order, invoice, proposal, website term or shrink-wrap, click-wrap or
similar term modifies the Contract Documents.
ARTICLE 2
SCOPE AND STANDARD OF PERFORMANCE
2.1 General scope.
Contractor shall furnish all labor, supervision, materials, consumables, tools, equipment,
temporary facilities, transportation, rigging, cranes, protection, testing, documentation and
incidentals required to complete the Fire Station No. 1 wind retrofit, including removal of the
existing generator system; roofing and roof-drain work; replacement of exterior personnel doors,
roll-up bay doors and louvers; roof-access and mechanical-equipment improvements; construction
of the generator slab; and installation, integration, testing and commissioning of the City-
purchased 250-kW diesel generator, fuel tank, automatic transfer switches, annunciator and
associated equipment.
The Work includes structural, electrical, civil and site work; temporary emergency power;
demolition; underground utility verification; FPL coordination; fire-alarm integration; HVAC
control modifications and delay timers; concrete and soil testing; permitting and inspections;
restoration; training; and closeout, all as detailed in the Contract Documents.
4
2.2 Complete and functional Work.
Contractor’s obligation is for a complete result. Work reasonably inferable from, incidental to, or
necessary to produce the intended result is included in the Contract Sum even if omitted from an
individual drawing, specification or bid line.
Contractor shall not exploit an error, omission or ambiguity and shall immediately notify the
City of any discovered discrepancy.
2.3 Standard of care and compliance.
Contractor shall perform diligently, safely and in a good and workmanlike manner, using properly
licensed and qualified personnel, in accordance with the Contract Documents, manufacturer
requirements, approved submittals, applicable codes, the Florida Building Code, National
Electrical Code, OSHA requirements, permit conditions, grant requirements and all applicable
federal, state, county and City laws.
Where requirements differ, Contractor shall comply with the more stringent requirement unless
the City directs otherwise in writing.
2.4 City-furnished equipment.
Contractor shall coordinate pickup or delivery from the manufacturer’s yard, inspect equipment
upon transfer, document condition, provide secure storage and weather protection, and assume
care, custody and control until Final Completion.
Contractor shall promptly report concealed or apparent damage and shall be responsible for loss
or damage caused by its handling, storage, installation, testing or failure to protect.
City-furnished equipment does not reduce Contractor’s responsibility for correct installation,
integration and operation, but Contractor is not responsible for an inherent manufacturing defect
that could not reasonably have been detected before installation and was not caused or worsened
by Contractor.
If delivery of City-furnished equipment is delayed through no fault of Contractor, Contractor shall
promptly notify the City, continue all unaffected Work, and resequence and coordinate the Work
to minimize any schedule impact. Contractor is entitled only to an extension equal to the actual,
documented critical-path delay that could not reasonably have been avoided through resequencing,
mitigation or performance of other Work. Any extension must be authorized by written Change
Order. Contractor is not entitled to additional compensation arising from the delayed delivery
unless the City expressly approves the compensation in a written Change Order.
5
2.5 Operational continuity.
Fire Station No. 1 is an occupied, continuously operating essential public-safety facility.
Contractor shall maintain safe access, security, life-safety systems, fire-rescue response capability
and continuous emergency-power capability throughout the Work.
Power interruptions, access restrictions or other impacts to fire-rescue operations shall occur only
at times approved in writing by the City Representative and Fire-Rescue, after Contractor submits
and obtains approval of a detailed outage, continuity and restoration plan.
Contractor shall provide at least seven (7) calendar days’ written notice unless the City approves
a shorter period. No approval relieves Contractor of responsibility for sequencing, safety,
temporary power or restoration.
Contractor shall provide, deliver, install, connect, fuel, operate, monitor, test, maintain, repair and
remove the temporary generator and all associated equipment necessary to maintain uninterrupted
emergency power throughout construction. Associated equipment includes all temporary fuel
tanks, cables, connections, transfer equipment, grounding, protection, barriers and other
components necessary for a safe, code-compliant and fully operational temporary emergency-
power system.
Before interrupting the existing emergency-power system, Contractor shall submit and obtain City
approval of a temporary-power, monitoring and emergency-response plan. Contractor shall
maintain sufficient fuel and qualified personnel and shall promptly respond to and correct any
failure or interruption. The temporary system shall remain operational until Final Completion
unless the City authorizes its earlier removal in writing after the permanent emergency-power
system has been successfully tested, commissioned and accepted for operation.
All costs associated with the temporary emergency-power system are included in the Contract
Sum. A failure of the temporary system caused by Contractor or its equipment does not entitle
Contractor to additional compensation or an extension of the Contract Time.
ARTICLE 3
CONTRACT SUM AND PRICING
3.1 Contract Sum.
Subject to additions and deductions authorized by written Change Order, the maximum amount
payable is ONE MILLION EIGHTY-FOUR THOUSAND THREE HUNDRED THIRTY
DOLLARS AND FIFTY CENTS ($1,084,330.50), inclusive of the permitting allowance and
contingency stated below.
The Contract Sum is not a guaranteed payment. Lump-sum items are payable based on accepted
progress, and unit-price items are payable only for actual quantities incorporated into the Work
and accepted by the City at the unit prices in Exhibit B.
6
Contractor bears any cost exceeding the Contract Sum unless first authorized by a Change Order.
3.2 Included costs; firm pricing.
Pricing includes all labor, supervision, materials, equipment, delivery, unloading, storage, crane
and rigging operations, temporary power, after-hours work required by the Contract Documents,
testing, fees, taxes not legally chargeable to the City, overhead, profit, insurance, bonds, escalation,
coordination, waste disposal and all other costs.
Contractor is not entitled to an adjustment for market changes, labor or material escalation, supply-
chain conditions, subcontractor pricing, ordinary weather, site access, quantities reasonably
estimable from the Contract Documents, or matters that Contractor knew or should have known
before bidding.
3.3 Permitting allowance.
The $25,000 permitting allowance may be used only for actual, documented permit and
governmental review fees approved by the City.
No overhead, profit or markup applies. Unused allowance remains City funds and reduces the final
Contract Sum. Costs above the allowance require prior written authorization by Change Order.
3.4 Contingency.
The $98,575.50 contingency is a City-controlled reserve and is not part of Contractor’s earned
compensation. Contractor may use contingency funds only for additional or changed Work
expressly authorized in advance by written Change Order. The City has no obligation to expend
any portion of the contingency, and any unused amount remains City funds and reduces the final
Contract Sum. Contractor has no claim for overhead, profit, anticipated profit or other
compensation on unused contingency.
3.5 No tax.
The City is exempt from Florida sales and use tax. Contractor shall not include taxes from which
the City is exempt and shall use the City’s exemption documentation only for this Project and only
as legally permitted.
ARTICLE 4
CONTRACT TIME, SCHEDULE AND DELAY
4.1 Time is of the essence.
Time is of the essence. Contractor shall commence only upon the City’s written Notice to Proceed
and within seven (7) calendar days after the commencement date stated therein. Costs incurred
before the Notice to Proceed are at Contractor’s sole risk, except documented bond and insurance
costs if the City terminates for convenience before commencement.
7
4.2 Completion deadlines.
Contractor shall achieve Substantial Completion within one hundred fifty (150) days after the
commencement date stated in the City’s Notice to Proceed and shall achieve Final Completion
within one hundred eighty (180) days after that commencement date, subject only to adjustments
authorized in accordance with the Contract Documents.
4.3 Baseline and updates.
Within ten (10) calendar days after execution, and before the Notice to Proceed, Contractor shall
submit a detailed critical-path schedule showing procurement, City-purchased equipment
coordination, submittals, permits, outages, temporary power, FPL activities, inspections, testing,
commissioning, punch list and closeout.
Contractor shall update the schedule at least monthly and with each payment application.
Acceptance of a schedule does not alter the Contract Time or shift responsibility to the City.
4.4 Excusable delay and notice.
Contractor is entitled to a day-for-day extension of the Contract Time only for the actual,
documented critical-path delay caused solely by an unforeseeable event beyond Contractor’s
control and not caused or contributed to by Contractor or its subcontractors.
Contractor shall provide written notice describing the event, anticipated impact and mitigation
measures within five (5) days after the event begins and shall submit a fully documented request
for an extension within ten (10) days after the impact can reasonably be quantified. Contractor
shall continuously mitigate the delay and provide supporting schedule updates requested by the
City.
Extensions for excusable delay shall not exceed thirty (30) days in the aggregate unless the City
Manager approves additional time in writing. If an excusable delay continues beyond thirty (30)
days, the City may terminate the Agreement for convenience without liability for anticipated profit,
extended overhead or other costs attributable to unperformed Work.
Concurrent delay is not compensable. Ordinary weather and reasonably foreseeable procurement
or supply-chain conditions do not constitute excusable delay. No extension is effective unless
authorized by written Change Order.
4.5 No damages for delay.
Except to the extent prohibited by law, Contractor’s sole remedy for an excusable delay is a
reasonable extension of time.
8
Contractor waives claims for delay, disruption, acceleration, loss of productivity, extended
overhead, standby or other time-related compensation, except for a delay caused solely by the
City’s active interference, bad faith, fraud, concealment of a material fact, or other circumstance
for which a no-damages-for-delay clause is unenforceable under Florida law.
4.6 Liquidated damages.
The Parties acknowledge that untimely completion will disrupt essential City operations and cause
administrative, inspection, project-management, temporary-power and other costs that are difficult
to determine precisely.
Contractor shall pay liquidated damages of ONE THOUSAND DOLLARS ($1,000.00) per
calendar day for each day Substantial Completion is late and FIVE HUNDRED DOLLARS
($500.00) per calendar day for each day after the Substantial Completion deadline that Final
Completion is late.
These amounts are agreed estimates of loss, not penalties, and may be deducted from amounts due.
Liquidated damages do not limit recovery for separate damages arising from defective work, third-
party claims, property damage, indemnity obligations, fraud, willful misconduct, or abandonment.
4.7 Recovery schedule.
If progress falls behind the accepted schedule or threatens a milestone, Contractor shall, without
additional cost, submit and implement a recovery plan, add labor or shifts, resequence work,
expedite materials and take other measures necessary to recover.
The City’s review, approval or acceptance of a recovery plan does not constitute a representation
that the plan will succeed, relieve Contractor of responsibility for the adequacy of the plan, or
modify the Contract Time or Contractor’s liability for delay.
ARTICLE 5
ADMINISTRATION, PERSONNEL AND SUBCONTRACTORS
5.1 Contractor control.
Contractor is solely responsible for construction means, methods, techniques, sequences,
procedures, Contractor coordination and safety. City review, inspection, testing, approval or
presence does not supervise personnel or relieve Contractor of responsibility for the Work.
5.2 Superintendent and key personnel.
Contractor shall maintain a competent and qualified superintendent at the Site whenever Work is
performed. The superintendent shall be authorized to act on Contractor’s behalf and shall be able
to communicate effectively with the City Representative, emergency personnel, inspectors,
subcontractors and others involved in the Work.
9
Key personnel identified in Contractor’s bid may not be replaced without the City’s prior written
approval. The City may require removal of any person who is unsafe, unqualified, disruptive,
violates City policy applicable to the Site, or otherwise impairs the Project. Replacement shall not
increase cost or time.
5.3 Subcontractors.
Within ten (10) calendar days after execution, Contractor shall submit a complete subcontractor
and supplier list. The City may reasonably object to a proposed subcontractor.
Contractor remains fully responsible for all acts, omissions, quality, safety and compliance of
subcontractors and suppliers as if performed by Contractor.
Every subcontract shall incorporate applicable Contract Documents, public-records, audit,
insurance, federal, E-Verify and flow-down requirements. No subcontract creates privity with the
City.
5.4 Independent contractor; no authority.
Contractor is an independent contractor and not an employee, agent, partner or joint venturer of
the City. Contractor has no authority to bind the City or incur obligations in the City’s name.
Contractor is solely responsible for employment taxes, wages, benefits and personnel direction.
ARTICLE 6
SITE CONDITIONS, PROTECTION AND COORDINATION
6.1 Site examination and utilities.
Contractor acknowledges that, before submitting its bid, it examined the Contract Documents and
Project Site and satisfied itself concerning the conditions affecting the Work, including access,
staging, occupied operations, existing improvements, utilities, subsurface work shown in the
Contract Documents and other conditions that were visible, disclosed, reasonably inferable, or
discoverable through a reasonable pre-bid investigation.
Contractor accepts responsibility for such conditions and waives any claim for additional
compensation or time arising from its failure to conduct an adequate investigation, verify
dimensions or quantities, review available information, or account for conditions that Contractor
knew or reasonably should have known before submitting its bid.
Before excavation or intrusive work, Contractor shall coordinate Sunshine 811 and any necessary
private utility locating, trace and field-verify underground utilities, pothole to verify potential
conflicts, and protect existing facilities. Utility information furnished by the City is for
Contractor’s assistance and does not relieve Contractor of its independent verification obligations.
Contractor shall bear all costs arising from its failure to perform the required investigation,
verification or protection.
10
6.2 Differing concealed conditions.
Subject to Contractor’s investigation and verification obligations under Section 6.1, if Contractor
encounters a concealed physical condition that materially differs from the conditions indicated in
the Contract Documents and could not reasonably have been discovered through the investigation
required by Section 6.1, Contractor shall immediately stop only the affected portion of the Work,
protect the condition from disturbance, continue all unaffected Work, and provide written notice
to the City before disturbing the condition and no later than two (2) days after discovery.
The notice shall describe the condition, explain why it was not reasonably discoverable before
bidding, identify the affected Work, and provide Contractor’s preliminary assessment of the
anticipated cost and critical-path schedule impact. Contractor shall preserve the condition for
inspection and provide all information requested by the City.
Contractor bears the burden of establishing that the condition was concealed, materially different,
not reasonably discoverable, and the direct cause of an unavoidable increase in cost or critical-path
delay. No adjustment to the Contract Sum or Contract Time is authorized unless the City
determines that the requirements of this Section have been satisfied and approves the adjustment
by written Change Order. Any adjustment shall be limited to the reasonable, actual and
documented direct cost and critical-path delay necessarily caused by the condition.
Contractor shall mitigate all resulting cost and delay. Failure to provide timely notice, preserve the
condition, continue unaffected Work, or comply with Section 6.1 is a waiver of the claim to the
extent the City is prejudiced or the claimed impact could have been avoided.
6.3 Protection and restoration.
Contractor shall protect City property, adjoining property, utilities, landscaping, pavements,
sidewalks and improvements; keep the Site secure, orderly and free of debris; and repair damage
caused by the Work to original or better condition.
The City may correct an unsafe condition or unrepaired damage after notice when practicable and
deduct the cost. Contractor shall remove waste lawfully and provide disposal records upon request.
Contractor shall continuously protect the facility and the Work from weather and shall maintain
the facility in a watertight condition throughout construction. Contractor shall furnish, install,
inspect, maintain, repair and remove all temporary roofing, coverings, enclosures, flashing,
drainage and other weather-protection measures necessary to prevent water intrusion and damage.
Contractor shall not open or remove any portion of the roof or exterior building envelope unless
adequate temporary weather protection is in place or can be completely installed before the end of
the workday or the onset of adverse weather, whichever occurs first. Contractor shall continuously
monitor weather conditions and shall immediately secure and protect the facility when rain, wind
or other adverse weather is anticipated.
11
Temporary weather protection shall be planned and maintained so that Fire Station No. 1 remains
fully operational and capable of supporting uninterrupted fire-rescue operations throughout the
roof replacement.
Contractor is responsible for all water intrusion and resulting damage, remediation, testing, repair,
operational disruption, cost and delay caused by inadequate, defective or improperly maintained
temporary weather protection or by Contractor’s failure to timely secure the facility. These
obligations do not increase the Contract Sum or Contract Time.
6.4 Hazardous materials.
Contractor shall not bring hazardous materials to the Site except in lawful quantities necessary for
the Work and with safety data sheets.
Upon encountering suspected pre-existing hazardous material not identified in the Contract
Documents, Contractor shall stop affected Work, secure the area and notify the City.
Contractor is responsible for spills, releases and contamination introduced, disturbed contrary to
instructions, or caused by Contractor, including response, reporting and remediation costs.
6.5 Security and public access.
Contractor shall comply with City security procedures, identification requirements and restrictions
on access to nonpublic areas of the Site. Contractor shall secure tools, keys and access credentials,
prevent unauthorized entry, and immediately report any security incident.
Contractor and its personnel shall comply with all applicable federal and Florida laws concerning
weapons and firearms. Nothing in this Agreement prohibits lawful possession or storage of a
firearm, including lawful storage in a private motor vehicle, or possession by an authorized law-
enforcement or security officer.
Illegal drugs and alcohol are prohibited at the Site. Photographs, recordings, publicity and use of
the City’s name, seal or logo require the City’s prior written approval, except for documentation
reasonably necessary to perform the Work or comply with law.
ARTICLE 7
PERMITS, SUBMITTALS, TESTING AND ACCEPTANCE
7.1 Permits and inspections.
Unless the Contract Documents expressly assign responsibility for a particular permit, inspection
or approval to the City, Contractor shall obtain and maintain all permits required for the Work;
schedule and coordinate all required inspections; obtain all necessary approvals from authorities
having jurisdiction; and close out all permits before Final Completion.
12
Contractor shall provide the City with copies of all permits, inspection reports, approvals and
permit-closeout documents. Contractor shall not cover, conceal or proceed with Work that requires
inspection until the required inspection has been completed and approval to proceed has been
obtained.
Contractor is responsible for all reinspection, retesting, corrective-work and related costs resulting
from defective or nonconforming Work, a failed inspection, premature concealment of Work, or
Contractor’s failure to properly schedule or coordinate an inspection.
7.2 Submittals.
Contractor shall prepare and submit all shop drawings, product data, samples, schedules,
coordination drawings and other submittals required by the Contract Documents sufficiently in
advance to permit review without delaying the Work.
Before submission, Contractor shall review, approve and stamp each submittal and verify its
accuracy, completeness, dimensions, quantities, field conditions, installation requirements and
coordination with other portions of the Work. The City may reject or return incomplete, inaccurate
or uncoordinated submittals without review. Contractor shall promptly correct and resubmit
rejected submittals at no additional cost or extension of time.
Contractor shall not fabricate, purchase or install Work requiring a submittal until the applicable
submittal has been reviewed. Work performed before review is at Contractor’s sole risk.
City or design-professional review is limited to general conformance with the Contract Documents
and does not relieve Contractor of responsibility for errors, omissions, dimensions, quantities, field
verification, coordination, construction means and methods, safety or performance.
Contractor shall specifically identify in writing every proposed deviation from the Contract
Documents when submitting it for review. Review of a submittal does not approve an unidentified
deviation or authorize an adjustment to the Contract Sum or Contract Time. Any such adjustment
requires a written Change Order.
7.3 Testing and commissioning.
Contractor shall provide all specified tests, including concrete cylinder and soil-density testing,
manufacturer start-up, load-bank or operational testing as required, ATS and annunciator testing,
fire-alarm integration, HVAC sequencing and grounding verification.
Testing shall be witnessed when requested. Failed tests shall be repeated after correction at
Contractor’s cost.
The system is not accepted until testing, commissioning and training are complete and written
reports are delivered.
13
7.4 Defective work.
The City may reject any Work that is defective, damaged, unsafe, improperly performed,
inadequately documented, or not in conformance with the Contract Documents, whether
discovered before or after payment, inspection, testing, occupancy or use.
Upon written notice from the City, Contractor shall promptly investigate the condition and, within
the time specified by the City, uncover, remove, correct, replace and retest the rejected Work.
Contractor shall also repair any damage to other Work or property resulting from the defective
Work or its correction. All resulting labor, materials, testing, inspection, design-professional,
permit and other costs shall be borne by Contractor without an increase in the Contract Sum or
Contract Time.
If Contractor fails to begin and diligently complete the required correction within the time
specified by the City, or immediately when an unsafe or emergency condition exists, the City may
take reasonable corrective action itself or through others. Contractor shall reimburse the City for
all resulting costs, or the City may deduct those costs from amounts otherwise due to Contractor.
The City’s correction of defective or nonconforming Work does not relieve Contractor or its surety
of responsibility for the Work, waive any warranty or other remedy, or constitute acceptance of
the defective condition. Contractor shall continue all unaffected Work while corrective action is
pending.
7.5 No acceptance by payment or use.
Inspection, payment, partial occupancy, operation, issuance of a certificate, or failure to discover
a defect does not constitute acceptance, waive a requirement or relieve Contractor or surety.
Acceptance occurs only by the City’s written determination of Substantial Completion or Final
Completion, as applicable.
ARTICLE 8
CHANGES AND CLAIMS
8.1 Written authorization required.
The City may order additions, deletions or revisions within the general scope of the Work by
written Change Order or Construction Change Directive signed by the City Manager or other City
official possessing lawful authority.
A Change Order shall be signed by the City and Contractor. A Construction Change Directive may
be issued by the City when the Parties have not agreed on the adjustment to the Contract Sum or
Contract Time. Contractor shall promptly proceed with the directed Work while preserving its
right to submit a claim in accordance with this Article.
14
Contractor shall not perform changed or extra Work without prior written authorization from an
authorized City official. Work performed without such authorization is at Contractor’s sole risk
and shall be deemed included in the Contract Sum.
No oral direction, field instruction, meeting note, email, submittal review, inspection, payment,
course of conduct or direction from an unauthorized person constitutes approval of additional
compensation or time.
8.2 Pricing changes.
The price of changed Work shall be determined in the following order:
1. Applicable unit prices established in Exhibit B;
2. A mutually agreed lump-sum amount supported by an itemized proposal; or
3. If directed by the City, actual and documented allowable costs incurred on a time-and-
material basis, subject to a not-to-exceed amount established by the City.
Allowable costs are limited to the reasonable, actual and documented cost of labor directly
performing the changed Work, materials incorporated into the Work, equipment actually used, and
approved subcontractor work. Labor costs shall be based on actual wages plus legally required
payroll taxes and insurance. Equipment charges shall not exceed the lower of Contractor’s actual
cost or customary local rental rates.
The following are included in Contractor’s markup and are not separately reimbursable: home-
office and field overhead, supervision not directly performing the changed Work, estimating,
scheduling, administrative personnel, small tools, vehicles, phones, computers, temporary
facilities, insurance, bonds, financing, legal and accounting expenses, inefficiency, loss of
productivity and other indirect costs.
The aggregate markup for all overhead and profit, including all Contractor, subcontractor and
lower-tier markups, shall not exceed ten percent (10%) of the allowable direct cost of the changed
Work. The ten-percent (10%) limitation is cumulative, applies regardless of the number of
contracting tiers, and may not be increased or circumvented through multiple or successive
markups. No markup is permitted on permit fees, taxes, insurance or bond premiums, or on another
markup. Deductive changes shall include a corresponding reduction for overhead and profit
calculated on the same basis.
Contractor shall submit quotations, invoices, payroll records, time sheets, equipment records,
subcontractor proposals and any other supporting documentation requested by the City.
Unsupported costs are not payable. The City may audit all records supporting changed Work.
For time-and-material Work, Contractor shall submit daily records identifying labor, materials and
equipment used. The City Representative’s signature verifies only that the identified resources
were present and does not establish entitlement, compensability, price or an extension of time.
Contractor shall not exceed a City-established not-to-exceed amount without prior written
authorization.
15
8.3 Claims and waiver.
As a condition precedent to any claim for additional compensation or time, Contractor shall
provide written notice to the City within five (5) days after the event giving rise to the claim and
before proceeding with the affected Work when reasonably practicable.
Contractor shall submit a fully documented claim within fifteen (15) days after the event or after
its impact can reasonably be determined. The claim must identify:
1. The contractual and factual basis for the claim;
2. The amount claimed and a detailed calculation;
3. The effect on the critical path and Contract Time;
4. The measures taken to avoid or mitigate the claimed impact; and
5. All supporting schedules, records, invoices, payroll information and other documentation.
Failure to comply with these notice and documentation requirements waives the claim to the extent
the City is prejudiced, or the claimed impact could have been avoided. Contractor shall continue
performing the Work while a claim is being reviewed or disputed.
8.4 No authority by design professional or inspector.
No architect, engineer, consultant, inspector, project manager, City Representative or field
representative may modify the Contract Sum or Contract Time unless that person has been
expressly authorized in writing to do so on behalf of the City.
Contractor proceeds at its own risk if it relies on contrary direction from an unauthorized person.
ARTICLE 9
PAYMENT, RETAINAGE AND CLOSEOUT
9.1 Schedule of values and payment applications.
Before submitting its first payment application, Contractor shall provide a complete and
balanced schedule of values acceptable to the City and consistent with the accepted price
schedule in Exhibit B.
Not than once each month, Contractor may submit an itemized payment application showing:
1. Actual Work completed and accepted;
2. Actual quantities of unit-price Work incorporated into the Project;
3. Approved stored materials, if any;
4. The amount previously paid and currently requested;
5. Retainage and other deductions; and
6. The remaining Contract Sum.
16
Each payment application shall include the updated Project schedule, applicable inspection and
testing documentation, , unconditional releases from Contractor and each applicable subcontractor
and supplier covering amounts paid from the preceding payment application, except amounts
identified in writing as subject to a good-faith dispute, and any additional supporting records
required by the City or Contract Documents. In lieu of the required releases, Contractor may
provide the written consent of its surety regarding the Project or payment in question as
contemplated by Section 255.05(11), Florida Statutes.
Submission of a payment application constitutes Contractor’s certification that the Work covered
by the application has been performed in accordance with the Contract Documents, that prior
payments have been properly applied, and that title to Work for which payment is requested will
pass to the City free of liens, claims, security interests and encumbrances.
9.2 Review and payment.
The City shall review and pay approved amounts in accordance with the Florida Local
Government Prompt Payment Act, Part VII of Chapter 218, Florida Statutes.
The City’s review or payment of an application does not constitute acceptance of the Work,
approval of quantities not actually incorporated into the Project, or a waiver of defective or
nonconforming Work.
Payment is subject to lawful appropriation and applicable grant requirements. The City shall not
use delays by a grantor to withhold an otherwise due and properly approved payment unless
permitted by law and disclosed in the Contract Documents.
9.3 Retainage.
The City shall retain five percent (5%) from progress payments, subject to Section 218.735, Florida
Statutes.
At fifty percent (50%) completion, the City will not withhold more than five percent (5%) retainage
and may reduce or release retainage as permitted by law. The City may continue to withhold
amounts reasonably necessary to protect against:
1. Defective, incomplete or nonconforming Work;
2. Filed or reasonably anticipated claims;
3. Failure to pay subcontractors or suppliers;
4. Damage to the City or another contractor;
5. An insufficient unpaid Contract balance;
6. Failure to maintain the Project schedule;
7. Accrued or anticipated liquidated damages;
8. Missing closeout, grant or payment documentation; and
9. Any other material breach of the Contract Documents.
17
9.4 Stored materials.
Payment for stored materials is within the City’s discretion and requires prior written approval.
Contractor shall provide proof of purchase and ownership, invoices, insurance, secure and
segregated storage, identification of the materials for this Project, inspection access and any
consent of surety requested by the City.
Off-site storage requires prior City approval of the location and additional documentation
requested by the City. Risk of loss, theft or damage remains with Contractor notwithstanding
payment by the City.
9.5 Conditions to final payment.
Final payment is conditioned upon Final Completion and the City’s receipt and acceptance of all
required closeout documents, including:
1. A final payment application;
2. Contractor’s final payment affidavit;
3. Unconditional final releases from Contractor and all subcontractors and suppliers;
4. Consent of surety to final payment;
5. Final inspections, approvals and permit closeout;
6. As-built drawings in the formats required by the City;
7. Operation and maintenance manuals;
8. Testing and commissioning reports;
9. Training records;
10. Spare parts, special tools, keys and access credentials;
11. Warranty documents registered in the City’s name;
12. Proof of lawful waste disposal;
13. Required federal and grant records; and
14. Any other closeout item required by the Contract Documents.
Acceptance of final payment waives Contractor’s claims except a claim specifically identified in
writing and expressly accepted by the City for reservation before final payment.
9.6 Setoff and withholding.
The City may withhold or set off amounts reasonably necessary to protect against defective Work,
third-party claims, failure to pay subcontractors or suppliers, property damage, liquidated
damages, an insufficient unpaid Contract balance, schedule default, missing records, overpayment
or any other breach of the Contract Documents.
After notice when reasonably practicable, the City may pay a claimant, correct defective Work,
cure a default or satisfy another obligation for which Contractor is responsible and deduct all
resulting costs from amounts otherwise due.
18
ARTICLE 10
BONDS, LIENS AND TITLE
10.1 Performance and payment bonds.
Within fourteen (14) days after notice of award and before execution of this Agreement or
commencement of the Work, Contractor shall furnish separate performance and payment bonds,
each in the full amount of the Contract Sum, on forms acceptable to the City.
Each bond shall be issued by a surety authorized to transact business in Florida, acceptable to the
City, and shall comply with Section 255.05, Florida Statutes.
The bonds shall remain effective through Final Completion and the correction of all warranty
obligations. Contractor shall increase the bond amounts to reflect increases in the Contract Sum.
The City will pay only an actual, documented additional bond premium expressly approved as part
of the applicable Change Order.
10.2 Public property; claims.
No construction lien or other encumbrance may attach to City property. Contractor shall keep the
Project, Work and City property free from liens and encumbrances arising from labor, services,
materials or equipment furnished for the Project.
Before commencing Work, Contractor shall record the payment bond in the public records of
Broward County as required by Section 255.05, Florida Statutes, and provide the City with a
certified copy of the recorded bond. The City is not required to make payment until it receives the
certified copy.
Upon receiving or becoming aware of a construction lien or other encumbrance asserted against
City property arising from the Work, Contractor shall promptly notify the City and shall, within
ten (10) days, cause the lien or encumbrance to be discharged, released, transferred to security or
otherwise removed from City property. Contractor shall provide the City with documentation
establishing the action taken.
Upon receiving or becoming aware of a notice of nonpayment, payment-bond claim or other
demand against the payment bond, Contractor shall promptly notify the City and surety. Within
ten (10) days, Contractor shall provide the City with a written status identifying the claimant, the
amount claimed, the basis of the claim, Contractor’s position and the actions being taken with
the surety. Contractor may contest a claim in good faith but shall diligently address the matter
and provide the City with material updates and documentation, including applicable
correspondence from the surety.
If Contractor fails to comply with this Section, or if an actual claim, default, lien or encumbrance
creates a material risk of loss to the City, the City may, to the extent permitted by law, withhold
sufficient funds, notify or make demand upon the surety, discharge or transfer an improper lien or
encumbrance, or take other reasonable action necessary to protect the City. Contractor shall
19
reimburse the City for resulting payments, costs and reasonable attorneys’ fees to the extent the
matter resulted from Contractor’s failure to perform or pay its obligations under the Contract
Documents, and the City may deduct those amounts from sums otherwise due.
Nothing in this Section limits a claimant’s lawful rights against the payment bond under Section
255.05, Florida Statutes, or makes the City responsible for Contractor’s payment obligations.
10.3 Title and risk of loss.
Title to materials and equipment for which the City has paid passes to the City upon payment.
Contractor warrants that the City receives good title free of liens, security interests and
encumbrances.
Risk of loss, theft or damage remains with Contractor until Final Completion and written
acceptance by the City, regardless of whether the City has paid for the affected Work, materials or
equipment.
ARTICLE 11
INSURANCE
11.1 Required insurance.
Contractor shall obtain and maintain all insurance coverages, limits, endorsements and other
requirements specified in Section 2.23 of ITB No. 26-009, which is incorporated into this
Agreement by reference.
Contractor shall not commence or continue Work until the required insurance has been submitted
to and approved by the City’s Risk Manager. Contractor shall maintain the required coverage
throughout performance of the Work and any applicable completed-operations and warranty
periods.
11.2 Evidence of coverage.
Contractor shall provide certificates of insurance and all endorsements required by the Contract
Documents. Certificate language alone does not satisfy a requirement for an endorsement.
Contractor shall provide updated evidence of coverage before expiration of any policy and shall
promptly notify the City of any cancellation, nonrenewal or material reduction in coverage.
11.3 Subcontractors.
Contractor shall require each subcontractor to maintain insurance appropriate to its Work and
meeting all applicable requirements of the Contract Documents.
20
Contractor shall obtain and review each subcontractor’s certificates of insurance and required
endorsements before the subcontractor begins Work and shall maintain those documents
throughout the subcontractor’s performance. Upon request, Contractor shall promptly provide
copies to the City.
Contractor is responsible for ensuring its subcontractors’ compliance with all insurance
requirements. A subcontractor’s failure to maintain required insurance does not relieve Contractor
of any obligation or liability under the Contract Documents.
11.4 Lapse in coverage.
Contractor and its subcontractors shall not perform Work while any required insurance is not in
effect. A lapse in required coverage constitutes a material breach. Any resulting delay is
nonexcusable and does not entitle Contractor to additional compensation or an extension of the
Contract Time.
ARTICLE 12
INDEMNIFICATION AND RESPONSIBILITY FOR LOSS
12.1 Indemnification.
To the fullest extent permitted by Section 725.06, Florida Statutes, Contractor shall indemnify and
hold harmless the City and its elected and appointed officials, officers, employees and agents from
liabilities, damages, losses and costs, including reasonable attorneys’ fees, to the extent caused by
the negligence, recklessness or intentional wrongful misconduct of Contractor or any person
employed or utilized by Contractor in performing the Contract Documents.
Contractor’s indemnification obligations are not limited by the availability or amount of insurance,
workers’ compensation benefits, or the Contract Sum. These obligations survive completion, final
payment and termination of the Agreement.
12.2 Defense and claims handling.
For any claim within the scope of Contractor’s indemnification obligations, Contractor shall
promptly assume and fund the defense using counsel reasonably acceptable to the City. The City
may participate in the defense with counsel of its choosing.
Contractor shall not settle any claim in a manner that imposes liability, an admission, a
nonmonetary obligation or a restriction upon the City without the City’s prior written consent.
Nothing in the Contract Documents requires the City to indemnify Contractor or any other person
or constitutes a waiver of the City’s sovereign immunity.
21
12.3 Property damage and personal injury.
Contractor is responsible for bodily injury, death, theft, loss and property damage caused by or
arising from the Work, Contractor-controlled Site conditions, or the acts or omissions of
Contractor, its subcontractors, suppliers or persons for whom Contractor is responsible.
Contractor shall immediately report any accident, injury, death, property damage, theft, utility
strike, spill or other material incident to the City. Contractor shall preserve relevant evidence and
cooperate with the City, applicable authorities and insurers in investigating and responding to the
incident.
ARTICLE 13
WARRANTY AND CORRECTION
13.1 General warranty.
Contractor warrants that all materials and equipment furnished for the Project will be new and of
good quality unless the Contract Documents expressly permit otherwise; that the Work will be free
from defects; that the Work will conform to the Contract Documents; and that the completed
system will perform its intended functions.
In addition to any longer manufacturer or specified warranty, Contractor shall correct defective or
nonconforming Work discovered within two (2) years after Substantial Completion. If corrective
Work is completed after Substantial Completion, the two-year correction period for that Work
begins upon completion and acceptance of the correction.
The correction period does not limit any longer warranty, other contractual remedy, or applicable
statute of limitations or repose.
13.2 Manufacturer and supplier warranties.
Contractor shall obtain, register and assign to the City all manufacturer, supplier and subcontractor
warranties applicable to the Work. Unless the City approves otherwise, those warranties shall
commence no earlier than Substantial Completion.
Contractor shall administer warranty claims on the City’s behalf and provide all labor, access,
removal, shipping, reinstallation, testing and coordination required for the City to receive the full
benefit of the warranties.
13.3 Warranty response.
For an emergency or failure affecting safety, essential operations or property, Contractor shall
respond within two (2) hours after notice and mobilize corrective action within four (4) hours.
For a nonemergency warranty matter, Contractor shall begin corrective action within two (2)
business days after notice and shall diligently proceed until the correction is completed.
22
If Contractor fails to respond or correct the condition within the required time, the City may
perform or arrange the corrective Work and recover all resulting costs from Contractor without
waiving any warranty or other remedy.
ARTICLE 14
TERMINATION, SUSPENSION AND CITY REMEDIES
14.1 Termination for cause.
The City may terminate all or any portion of the Work for cause if Contractor:
1. Fails to supply sufficient qualified workers, materials or equipment;
2. Fails to commence or diligently prosecute the Work;
3. Performs defective, nonconforming or unsafe Work;
4. Fails to pay subcontractors or suppliers;
5. Violates applicable law, grant requirements or the Contract Documents;
6. Fails to maintain a required license, bond or insurance coverage;
7. Becomes insolvent, makes an assignment for the benefit of creditors, or is the subject of
bankruptcy or receivership proceedings that materially impair performance;
8. Makes a material misrepresentation to the City;
9. Abandons the Project; or
10. Otherwise materially breaches the Contract Documents.
Except in the case of abandonment, fraud, an immediate safety emergency, loss of required
insurance or bond coverage, or failure to timely commence the Work, the City shall provide written
notice identifying the default and allow Contractor five (5) days to cure or to begin and diligently
pursue a cure acceptable to the City.
14.2 Remedies following default.
Following Contractor’s default, the City may:
1. Exclude Contractor from the Site;
2. Take possession of materials and equipment for which the City has paid;
3. Accept assignment of subcontracts and purchase orders;
4. Make demand upon the performance or payment bond;
5. Complete or correct the Work through others;
6. Withhold and set off amounts otherwise due;
7. Recover excess completion costs, design-professional fees, inspection costs,
administrative costs, liquidated damages and other direct damages caused by the default;
and
8. Exercise any other remedy available under the Contract Documents or law.
If a termination for cause is later determined to have been improper, the termination shall be treated
as a termination for convenience, and Contractor’s recovery shall be limited to the compensation
permitted under Section 14.3.
23
14.3 Termination for convenience.
The City may terminate all or any portion of the Agreement without cause upon thirty (30) days’
written notice or on an earlier date stated in the notice.
Upon receipt of the notice, Contractor shall:
1. Stop the Work as directed;
2. Protect completed and partially completed Work;
3. Cancel or assign commitments as directed by the City;
4. Mitigate all termination costs;
5. Deliver all City-owned or City-paid materials, equipment and Project records; and
6. Cooperate in an orderly transition of the Work.
The City shall pay Contractor for accepted Work properly performed through the effective
termination date, reasonable documented demobilization costs, and unavoidable cancellation
charges approved by the City, less prior payments, retainage and applicable offsets.
Contractor is not entitled to anticipated profit, unabsorbed overhead, lost opportunity,
consequential damages, or profit on Work not performed.
14.4 Suspension.
The City may suspend all or any portion of the Work for convenience, Contractor default, safety,
operational necessity, funding requirements or any other reasonable cause.
Contractor shall stop the affected Work as directed, protect the Work and Site, continue unaffected
Work, and mitigate the cost and schedule impact.
A suspension for convenience that solely causes a critical-path delay may support an extension
under Article 4. Contractor is not entitled to additional compensation except when the no-damages-
for-delay provision is unenforceable under Florida law.
14.5 Nonexclusive remedies.
The City’s rights and remedies are cumulative. The City’s failure or delay in enforcing a
requirement does not constitute a waiver.
The City may recover reasonable attorneys’ fees and costs incurred to enforce Contractor’s
indemnification, public-records, audit, lien-discharge, confidentiality, grant-compliance and
payment obligations, and as otherwise permitted by law.
24
ARTICLE 15
PUBLIC RECORDS, AUDIT AND GRANT RECORDS
15.1 Public records.
Contractor shall comply with Chapter 119, Florida Statutes, and Section 119.0701, Florida
Statutes.
Contractor shall:
1. Keep and maintain public records required to perform the Agreement;
2. Upon request from the City’s custodian of public records, provide the City with a copy of
requested records or allow the records to be inspected or copied within a reasonable time
at a cost that does not exceed the amount provided by law;
3. Ensure that public records exempt or confidential and exempt from disclosure are not
disclosed except as authorized by law for the duration of the Agreement and after
completion or termination if Contractor retains the records;
4. Upon completion or termination, transfer to the City, at no cost, all public records in
Contractor’s possession or keep and maintain the records as required by law; and
5. Provide electronic records in a format compatible with the City’s information-technology
systems.
IF CONTRACTOR HAS QUESTIONS REGARDING THE APPLICATION OF
CHAPTER 119, FLORIDA STATUTES, TO CONTRACTOR’S DUTY TO PROVIDE
PUBLIC RECORDS RELATING TO THIS AGREEMENT, CONTRACTOR SHALL
CONTACT THE CITY’S CUSTODIAN OF PUBLIC RECORDS:
ELORA RIERA, CITY CLERK
CITY OF DANIA BEACH
100 WEST DANIA BEACH BOULEVARD
DANIA BEACH, FLORIDA 33004
TELEPHONE: 954-924-6800
EMAIL: ERIERA@DANIABEACHFL.GOV
15.2 Records retention and audit access.
Contractor shall maintain complete, accurate and separately identifiable Project records, including
accounting, payroll, procurement, subcontract, schedule, correspondence, change-order, testing,
inspection and payment records.
Contractor shall retain the records for at least five (5) years after final payment or for any longer
period required by applicable law, grant requirements, audit, claim or litigation.
25
The City, the applicable grantor, the Federal Emergency Management Agency, the Florida
Division of Emergency Management, the United States Department of Homeland Security, the
Inspector General, the Comptroller General and their authorized representatives may inspect, copy
and audit Project records and interview Contractor personnel during reasonable times.
Unsupported or disallowed costs are not payable and, if previously paid, shall be reimbursed to
the City.
15.3 Cooperation and access.
Contractor shall provide timely access to the Site, Work, records and personnel for inspection,
monitoring and audit.
Contractor shall cooperate with all lawful reviews and investigations, timely respond to findings
attributable to Contractor, correct identified deficiencies, and reimburse the City for costs
disallowed because of Contractor’s act, omission or failure to maintain adequate documentation.
Contractor shall include the applicable public-records, retention, audit and access requirements in
every subcontract and purchase order. These obligations survive completion, final payment and
termination of the Agreement.
ARTICLE 16
FEDERAL AND STATE COMPLIANCE
16.1 Federal funding requirements.
Contractor acknowledges that federal disaster-assistance funds may finance all or a portion of the
Project.
Contractor shall comply with all applicable federal requirements incorporated into the Contract
Documents, including the requirements contained in ITB No. 26-009, applicable provisions of 2
C.F.R. Part 200 and Appendix II, Federal Emergency Management Agency requirements, and the
federal provisions contained in Exhibit C.
Contractor shall include all required federal provisions in its subcontracts and purchase orders and
is responsible for compliance by its subcontractors and lower-tier entities.
If a federal requirement is legally inapplicable to the Project, its inclusion does not make it
applicable. Contractor shall nevertheless provide the information and cooperation necessary for
the City or applicable grantor to determine whether a requirement applies.
16.2 Suspension and debarment.
Contractor certifies that neither Contractor nor any of its principals or affiliates is suspended,
debarred, excluded or otherwise ineligible to participate in a covered federal transaction.
26
Contractor shall comply with 2 C.F.R. Part 180, Subpart C, and 2 C.F.R. Part 3000, Subpart C,
and shall verify the eligibility of subcontractors and other participants in lower-tier covered
transactions.
Contractor shall immediately notify the City if Contractor or any principal, affiliate, subcontractor
or lower-tier participant becomes suspended, debarred, excluded or otherwise ineligible during
performance of the Agreement.
A false certification or failure to provide notice constitutes a material breach.
16.3 Lobbying.
Contractor shall submit all certifications and disclosures required by the Byrd Anti-Lobbying
Amendment, 31 U.S.C. § 1352.
Contractor certifies that it has not used and will not use federally appropriated funds to pay any
person or organization for influencing or attempting to influence an officer or employee of a
federal agency, Member of Congress, congressional officer or employee, or employee of a
Member of Congress in connection with a covered federal award.
Contractor shall disclose lobbying performed with nonfederal funds and shall obtain and forward
all required lower-tier certifications and disclosures.
16.4 E-Verify.
Contractor shall register with and use the E-Verify system for all newly hired employees as
required by Section 448.095, Florida Statutes.
Contractor shall obtain and retain the affidavits required by law from each subcontractor and shall
provide proof of compliance to the City upon request.
If the City has a good-faith belief that Contractor knowingly violated Section 448.09(1), Florida
Statutes, the City shall terminate the Agreement as required by law. If the City has a good-faith
belief that a subcontractor knowingly violated the law but Contractor otherwise complied,
Contractor shall immediately terminate the subcontract as required by law.
16.5 Public entity crimes and statutory eligibility.
Contractor certifies that it is eligible to contract with the City under Section 287.133, Florida
Statutes, and is not prohibited from contracting under Sections 287.134, 287.135 or 215.473,
Florida Statutes, as applicable.
Contractor shall immediately notify the City of any change in its eligibility or certification. The
City may terminate the Agreement for a false certification or statutory disqualification.
27
16.6 Human-trafficking affidavit.
Before execution of the Agreement, Contractor shall provide the affidavit required by Section
787.06, Florida Statutes, signed by an officer or authorized representative, attesting that Contractor
does not use coercion for labor or services.
The affidavit is incorporated into the Agreement by reference. A materially false attestation
constitutes a material breach and grounds for termination and referral to the appropriate authorities.
16.7 Licenses, registrations and taxes.
Contractor and its subcontractors shall obtain and maintain all licenses, registrations, certifications
and authorizations required to perform their respective portions of the Work and shall remain in
good standing throughout the Project.
Contractor is solely responsible for all taxes, assessments, unemployment contributions and other
governmental obligations attributable to its business, personnel and performance of the Work,
except taxes from which the City is legally exempt.
ARTICLE 17
CONFIDENTIALITY, DATA AND INTELLECTUAL PROPERTY
17.1 Protected information.
Contractor shall use nonpublic City information, building-security information, access credentials
and critical-infrastructure information solely to perform the Work.
Contractor shall restrict access to personnel who require the information to perform the Work and
shall employ reasonable administrative, technical and physical safeguards against unauthorized
access, use, loss or disclosure.
Contractor shall immediately notify the City of any actual or suspected loss, unauthorized access,
disclosure or security incident involving City information or systems and shall cooperate with the
City’s investigation and response.
Contractor shall not place nonpublic City information into a publicly available or consumer
artificial-intelligence system or use City information to train or improve an artificial-intelligence
model.
Nothing in this Section authorizes Contractor to withhold a nonexempt public record or otherwise
limits the application of Florida public-records law.
28
17.2 Project documents.
To the extent Contractor creates Project-specific schedules, reports, as-built drawings,
photographs, test results, commissioning data, manuals or other deliverables, the City owns the
copies delivered under the Agreement and may use, reproduce, modify and disclose them for City
purposes.
Contractor retains ownership of its pre-existing proprietary tools, methods and materials but grants
the City a perpetual, irrevocable, royalty-free license to use, reproduce and modify them to the
extent incorporated into a Project deliverable or reasonably necessary to operate, maintain, repair
or modify the Project.
Contractor warrants that Project deliverables will not infringe a patent, copyright, trade secret or
other proprietary right of a third party.
17.3 Publicity and City marks.
Contractor shall not issue publicity concerning the Project, advertise the contract award, or use the
City’s name, seal, logo or photographs of secure or nonpublic areas without the City’s prior written
approval.
This restriction does not prohibit a truthful disclosure required by law or the inclusion of basic
Project information in a contractor qualification statement after Final Completion, provided
Contractor does not imply City endorsement.
ARTICLE 18
DISPUTES, GOVERNING LAW AND SOVEREIGN IMMUNITY
18.1 Good-faith resolution and continued performance.
Contractor shall first submit a dispute to the City Representative for review. If unresolved,
Contractor may submit the dispute to the Public Services Director and then to the City Manager.
Pending resolution of a dispute, Contractor shall continue timely performance of the Work, and
the City shall continue to pay undisputed amounts properly due.
This dispute-review process does not extend a contractual notice or claim deadline and does not
limit the City’s remedies.
18.2 Governing law and venue.
Florida law governs the Contract Documents without regard to conflict-of-law principles.
Exclusive venue for any action arising from or relating to the Contract Documents lies in the state
courts located in Broward County, Florida, or, if federal jurisdiction exists, in the United States
District Court for the Southern District of Florida.
29
Contractor waives any objection based upon venue or forum non conveniens.
18.3 Jury-trial waiver.
TO THE EXTENT PERMITTED BY LAW, EACH PARTY KNOWINGLY AND
VOLUNTARILY WAIVES TRIAL BY JURY IN ANY ACTION ARISING FROM OR
RELATING TO THE CONTRACT DOCUMENTS.
18.4 Sovereign immunity.
Nothing in the Contract Documents waives or alters the City’s sovereign immunity or the
limitations established by Section 768.28, Florida Statutes.
No provision creates liability beyond that provided by law, and no obligation by the City to
indemnify Contractor or another person shall be implied.
18.5 Consequential damages.
To the extent permitted by law, Contractor waives claims against the City for lost profits on
other work, loss of financing, loss of business opportunity, special, incidental, punitive or
consequential damages.
This waiver does not limit the City’s right to recover damages from Contractor.
ARTICLE 19
MISCELLANEOUS
19.1 Notices.
Formal notices required by the Contract Documents shall be in writing and delivered by personal
delivery, nationally recognized overnight-delivery service, certified United States mail with
return receipt requested, or email with confirmation of receipt.
Notice is effective upon confirmed delivery to the following:
To the City:
Candido Sosa-Cruz, ICMA-CM, City Manager
City of Dania Beach
100 West Dania Beach Boulevard
Dania Beach, Florida 33004
30
With a copy to:
City Attorney
City of Dania Beach
100 West Dania Beach Boulevard
Dania Beach, Florida 33004
To Contractor:
S3S Construction, Inc.
9633 W. Broward Blvd., Suite 6
Plantation, Florida 33324
Project communications sent to the City Representative do not replace formal notice to the City
Manager when formal notice is required.
19.2 Assignment.
Contractor shall not assign, transfer, delegate or encumber the Agreement, its payment rights or
its claims without the City’s prior written consent.
An unauthorized assignment is void. The City may assign the Agreement to a governmental
successor or funding entity upon written notice to Contractor.
19.3 Appropriation and authority.
The City’s obligations are subject to lawful appropriation.
No City employee, officer, representative or consultant may bind the City beyond that person’s
lawfully delegated authority. Contractor is charged with knowledge of applicable authority and
may rely only upon a written instrument executed by an authorized City official.
19.4 No third-party beneficiaries.
The Contract Documents are solely for the benefit of the City and Contractor and create no right
or benefit in a subcontractor, supplier, surety, grantor, employee or other third party, except for
rights expressly created by a statutory bond or applicable law.
19.5 Severability and interpretation.
If any provision of the Contract Documents is determined to be invalid or unenforceable, the
provision shall be enforced to the maximum extent permitted by law, and the remaining provisions
remain effective.
31
Headings are for convenience only. The term “including” means “including without limitation.”
The singular includes the plural when appropriate.
The Parties acknowledge that the Agreement was reviewed by both Parties. No presumption or
rule of construction shall apply against a Party based upon authorship of the Agreement.
Obligations that by their nature extend beyond completion, final payment or termination survive.
19.6 Amendment and waiver.
An amendment or waiver is effective only in a written instrument executed by an authorized
representative of the Party against whom it is enforced.
A waiver on one occasion is not a continuing waiver. City review, approval, payment or failure to
enforce a requirement does not waive compliance unless the City expressly identifies the waived
requirement in writing.
19.7 Counterparts and electronic signatures.
The Agreement may be executed in counterparts, each of which is treated as an original and all of
which together constitute one instrument.
Legally valid electronic signatures have the same force and effect as original signatures.
19.8 Authority and representations.
Each person signing the Agreement represents that he or she has authority to bind the identified
Party.
Contractor represents that its legal name, organizational status, addresses, licenses and other
information provided to the City are accurate and that no undisclosed restriction prevents
Contractor from performing the Agreement.
SIGNATURES ON THE FOLLOWING PAGES
32
IN WITNESS OF THE FOREGOING, the parties have set their hand and seal the day
and year first written above.
CITY OF DANIA BEACH, FLORIDA,
a Florida municipal corporation
ELORA RIERA, MMC JOYCE L. DAVIS
CITY CLERK MAYOR
APPROVED AS TO LEGAL FORM
AND CORRECTNESS
EVE A. BOUTSIS, CITY ATTORNEY CANDIDO SOSA-CRUZ, ICMA-CM
CITY MANAGER
33
CONTRACTOR:
WITNESSES:
S3S CONSTRUCTION, INC., a Florida
corporation
SIGNATURE SIGNATURE
PRINT Name PRINT Name
SIGNATURE Title
PRINT Name
STATE OF FLORIDA
COUNTY OF BROWARD
The foregoing instrument was acknowledged before me by means of ☐ physical presence
or ☐ online notarization, on , 2026, by _______________ (name),
_______________________ (title), of S3S CONSTRUCTION, INC., a Florida corporation, who is
personally known to me or has produced as
identification.
NOTARY PUBLIC
My Commission Expires: State of Florida
34
EXHIBIT A
SCOPE OF WORK
The Scope of Work for the Fire Station No. 1 Wind Retrofit Project contained in ITB No. 26-
009, together with the applicable plans, technical specifications and addenda, is incorporated into
the Agreement by reference.
35
EXHIBIT B
CONTRACTOR’S ACCEPTED PRICE SCHEDULE
S3S Construction, Inc.’s accepted bid and three-page price schedule submitted in response to ITB
No. 26-009 are incorporated into the Agreement by reference, including all accepted unit prices,
the total Contract Sum of $1,084,330.50, the $25,000.00 permitting allowance, and the $98,575.50
City-controlled contingency.
Any terms, qualifications, assumptions, exceptions or conditions included in Contractor’s bid that
were not expressly accepted by the City are excluded.
36
EXHIBIT C
FEDERAL AND GRANT REQUIREMENTS
The federal requirements contained in ITB No. 26-009 and the applicable requirements of Hazard
Mitigation Grant Program Project No. DR-4337-285-R are incorporated into the Agreement by
reference, including all applicable Federal Emergency Management Agency and Florida Division
of Emergency Management requirements and the applicable provisions of 2 C.F.R. Part 200 and
Appendix II.