HomeMy WebLinkAboutR-2026-157 Authorization of Ranking and Awarding of Agreement ITB 26-023RESOLUTION NO. 2026-157
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA, AUTHORIZING THE AWARD OF INVITATION TO BID
(ITB) NO. 26-023, CHESTER BYRD PARK IMPROVEMENTS TO M&J
CONSULTING GROUP CORP., IN AN AMOUNT NOT TO EXCEED ONE
MILLION FOUR HUNDRED TWENTY-EIGHT THOUSAND THREE
HUNDRED NINETY-SEVEN DOLLARS AND NINETY-FOUR CENTS
($1,428,397.94); AUTHORIZING THE PROPER CITY OFFICIALS TO
EXECUTE AN AGREEMENT FOR SERVICES WITH M&J CONSULTING
GROUP CORP.; AND TO EXCEED THE ANNUAL SINGLE-VENDOR
PURCHASING THRESHOLD OF FIFTY THOUSAND DOLLARS
($50,000.00); PROVIDING FOR FUNDING; PROVIDING FOR CONFLICTS;
FURTHER, PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the Dania Beach Code of Ordinances, Chapter 2, Article 1, Section 2-10, “Monetary
thresholds for certain purchases and payment disbursement authorizations”, Subsection (a), sets the
monetary threshold at Fifty Thousand Dollars ($50,000.00) for a vendor each fiscal year; and
WHEREAS, the City of Dania Beach was awarded $200,000 in grant funding through the Florida
Recreation Development Assistance Program (FRDAP) with a $200,000 match in August 2023 for the
Chester Byrd Park Improvements Project (the “Project); and
WHEREAS, on November 18, 2025, the City Commission of the City of Dania Beach approved
Resolution 2025-183, entering into an agreement with Calvin, Giordano, and Associates, Inc. for the
Design Services related to the Project and authorized the Parks and Recreation Department to solicit
through formal bidding the construction services for the park improvements; and
WHEREAS, on September 8, 2026, the City issued ITB. No. 26-023 entitled “Chester Byrd Park
Improvements for the selection of a qualified firm for Construction Services for the Project; and
WHEREAS, on October 8, 2026, the City received six (6) responsive and qualified bids to ITB
No. 2024-018, shown below:
1. M&J Consulting Group Corp. $1,428,397.94
2. Behar Construction $1,433,178.26
3. Wrangler Construction $1,585,123.72
4. MBR Construction Inc. $1,627,773.23
5. West Construction Inc. $1,748,627.26
6. Regal Contractors Inc. $1,755,555.65; and
2 RESOLUTION #2026-157
WHEREAS, Procurement completed its review for responsiveness, as well as a review by the
design services team from Calvin, Giordano, and Associates, Inc., resulted in the selection of M&J
Consulting Group Corp., as the most responsive and responsible proposer; and
WHEREAS, the City Administration recommends that the City Commission award ITB No. 26-
023 to M&J Consulting Group Corp,. and authorize the proper City officials to execute an agreement for
Construction Services for the Project, which agreement is attached as Exhibit “A” and incorporated into
this Resolution by this reference; and
WHEREAS, the total project authorization shall not exceed $1,428,397.94; and
WHEREAS, funding for this project will be appropriated from Grant Account No. 103-72-64-
572-63-10.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF DANIA BEACH, FLORIDA:
Section 1. That the above “Whereas” clauses are ratified and confirmed, and they are
made a part of and incorporated into this Resolution by this reference.
Section 2. That the City Commission hereby authorizes the award of Invitation to Bid
(ITB) No. 26-023, Chester Byrd Park Improvements to M&J Consulting Group Corp. in the
amount of $1,428,397.94, which will exceed the annual vendor threshold of $50,000.00.
Section 3. That the City Commission hereby approves the Construction Agreement
between the City of Dania Beach and M&J Consulting Group Corp. in completion of the Chester
Byrd Park Improvements, which agreement is incorporated by this reference as Exhibit A.
Section 4. That the total project authorization, including a 10 percent contingency,
shall not exceed $1,428,397.94.
Section 5. That funding for this project will be appropriated from the Grant Fund
Account No. 103-72-64-572-63-10 in the amount of $1,428,397.94.
Section 6. That all resolutions or parts of resolutions in conflict with this Resolution
are repealed to the extent of such conflict.
Section 7. That this Resolution shall be effective immediately after passage.
3 RESOLUTION #2026-157
PASSED AND ADOPTED on November 17, 2026.
Motion by Commissioner Rimoli second by Commissioner Davis.
FINAL VOTE ON ADOPTION: Unanimous X
Yes No
Commissioner Joyce L. Davis ____ ____
Commissioner Luis Rimoli ____ ____
Commissioner Marco Salvino ABSENT
Vice Mayor Diana Fahmie ____ ____
Mayor Colman W. Ryan ____ ____
ATTEST:
ELORA RIERA, MMC COLMAN W. RYAN
CITY CLERK MAYOR
APPROVED AS TO FORM AND CORRECTNESS:
EVE A. BOUTSIS
CITY ATTORNEY
1
CONSTRUCTION AGREEMENT BETWEEN CITY OF DANIA BEACH, FLORIDA
AND
M & J CONSULTING GROUP CORP.
FOR
CHESTER BYRD PARK IMPROVEMENTS
ITB NO. 23-023
THIS CONSTRUCTION AGREEMENT (the “Agreement”) is entered into as of
____________, 20__ (the “Effective Date”), by and between the CITY OF DANIA BEACH,
FLORIDA, a Florida municipal corporation, with an address of 100 West Dania Beach Boulevard,
Dania Beach, Florida 33004 (the “City” or “Owner”), and M & J CONSULTING GROUP CORP.
a Florida corporation, authorized to transact business in Florida, with an address of 3350 SW 148
Avenue, Suite 110-9062, Miramar, Florida 33027(the “Contractor”). The City and Contractor may
each be referred to as a “Party” and together as the “Parties.”
RECITALS
WHEREAS, the City issued Invitation to Bid No. 26-023 for the Chester Byrd Park
Improvements at 1021 SW 12th Avenue, Dania Beach, Florida (the “Project”); and
WHEREAS, the Project includes demolition, site preparation, park amenities, hardscape,
parking, drainage, utility, electrical, lighting, landscaping, irrigation, and related improvements
shown in the Contract Documents; and
WHEREAS, the City is the recipient of Florida Recreation Development Assistance
Program funding under Florida Department of Environmental Protection Grant Agreement No.
P25011 (the “Grant Agreement”), which requires completion of the funded Project by April 30,
2027 and provides no extension; and
WHEREAS, Contractor submitted the lowest responsive and responsible Bid accepted by
the City, and by submitting its Bid acknowledged and agreed that this Agreement was a material
part of the solicitation and would govern the Work if awarded; and
WHEREAS, the City Commission authorized this Agreement by Resolution on November
17, 2026; and
WHEREAS, the Parties desire to state their complete agreement concerning the Work.
NOW, THEREFORE, for good and valuable consideration, the receipt and sufficiency of
which are acknowledged, the Parties agree as follows:
2
1. DEFINITIONS AND RULES OF INTERPRETATION
1.1 “Application for Payment” means Contractor’s written, itemized request for payment for
completed and accepted Work, prepared in the form required by the City and accompanied by all
supporting documentation required by the Contract Documents.
1.2 “Bid” means the bid submitted by Contractor in response to the ITB, including the completed
Bid Form, Bid Schedule, required certifications, and other required submissions, but excluding
any qualification, exception, assumption, proposed term, or other condition not expressly accepted
by the City in this Agreement or an addendum issued before Bid opening.
1.3 “Bid Schedule” means the schedule of lump-sum and unit-price items submitted with
Contractor’s Bid and accepted by the City, as corrected for mathematical errors in accordance with
the ITB.
1.4 “Change Order” means a written instrument executed by Contractor and the City through
officials having authority to bind the City that authorizes a change in the Work, Contract Sum,
Contract Time, or any combination of them. A field directive, email, meeting statement, inspection
comment, submittal response, or other communication is not a Change Order.
1.5 “City Representative” means the City Manager or the City Manager’s written designee
responsible for administering the Agreement. The City may designate a project manager, inspector,
or Design Professional to perform administrative functions, but no such person may amend the
Agreement or authorize additional compensation or time unless expressly authorized in writing by
the City.
1.6 “Contract Documents” means the documents identified and incorporated in Section 2,
together with properly executed amendments and Change Orders.
1.7 “Contract Sum” means the total amount payable by the City for Work actually performed
and accepted, calculated using the accepted lump-sum and unit prices contained in the Bid
Schedule and subject to allowances, actual quantities, additions, deductions, and other adjustments
authorized by the Contract Documents. The Contract Sum is not a guaranteed minimum payment.
1.8 “Contract Time” means the periods established in Section 4 for commencement, Substantial
Completion, and Final Completion, as adjusted only by a properly executed Change Order.
1.9 “Day” means calendar day unless the Contract Documents expressly state “business day.” If
an act is required on a day when City offices are closed, the act shall be performed by the next
business day, except that this rule does not extend the Contract Time or any completion deadline.
1.10 “Defective Work” means Work that is incomplete, damaged, deficient, unsuitable,
improperly installed, or not in conformance with the Contract Documents, approved submittals,
manufacturer requirements, permits, applicable law, or accepted construction practices.
3
1.11 “Design Professional” means the architect, engineer, landscape architect, or other licensed
professional designated by the City to provide design, construction-administration, inspection, or
certification services for the Project. The Design Professional has no authority to amend the
Agreement or authorize additional compensation or time unless expressly authorized in writing by
the City.
1.12 “Final Completion” means completion and acceptance of all Work, correction of all punch-
list and Defective Work, closure of applicable permits, and delivery of all releases, warranties,
record drawings, test results, approvals, manuals, certifications, grant documentation, and other
items required as conditions of final payment.
1.13 “Final Payment” means the final payment of the unpaid Contract Sum, including retainage
properly due, after the City determines that Final Completion and all conditions of final payment
have been satisfied.
1.14 “Grant Agreement” means FDEP Grant Agreement No. P25011 between the City and the
Florida Department of Environmental Protection, including its attachments, exhibits, approved
amendments, and requirements applicable to the Project.
1.15 “ITB” means the City’s Invitation to Bid No. 26-023 for the Chester Byrd Park
Improvements, together with all attachments and addenda issued before Bid opening.
1.16 “Notice to Proceed” or “NTP” means the City’s written notice directing Contractor to
commence the Work and establishing the date from which the Contract Time is measured. The
execution of this Agreement, issuance of a purchase order, or performance of preliminary
administrative activities does not constitute an NTP.
1.17 “Project” means the Chester Byrd Park Improvements described in the Contract Documents.
1.18 “Project Site” means Chester Byrd Park, located at 1021 SW 12th Avenue, Dania Beach,
Florida 33004, together with other areas made available by the City for performance of the Work.
1.19 “Subcontractor” means a person or entity having a direct or indirect contract with Contractor
or another subcontractor to perform any portion of the Work or furnish labor, materials, equipment,
or services for the Project. The term includes subcontractors of every tier unless the context
requires otherwise.
1.20 “Substantial Completion” means the stage when the Work is sufficiently complete in
accordance with the Contract Documents so that the City can lawfully, safely, and continuously
use the Project for its intended purpose, subject only to minor corrective or incomplete items that
do not materially interfere with such use, as determined and certified in writing by the City.
1.21 “Surety” means the surety company issuing the performance bond or payment bond required
by the Contract Documents.
4
1.22 “Work” means all labor, supervision, administration, materials, equipment, tools,
transportation, temporary facilities, testing, permits, coordination, documentation, closeout
services, and incidentals necessary to furnish a complete, operational, safe, code-compliant
Project, whether expressly stated or reasonably inferable from the Contract Documents.
1.23 Rules of Interpretation. Headings are for convenience only and do not limit meaning.
“Including” means “including without limitation.” The singular includes the plural and vice versa.
“Shall” and “must” impose mandatory obligations. A requirement imposed on Contractor includes
its Subcontractors and all persons and entities for whom Contractor is responsible. References to
statutes include amendments and successor provisions. No ambiguity shall be construed against
the City merely because the City prepared or provided a Contract Document, because the Contract
Documents were available for review and questions before Bid submission.
2. CONTRACT DOCUMENTS; PRECEDENCE; BIDDER ASSENT
2.1 Contract Documents. The following documents collectively constitute the “Contract
Documents” and are incorporated into this Agreement:
(a) amendments to this Agreement executed by the City and Contractor after the Effective
Date;
(b) Change Orders executed after the Effective Date;
(c) this Agreement, including its exhibits;
(d) addenda issued by the City before Bid opening;
(e) the Special Conditions;
(f) the Chester Byrd Park Improvements bid plans, drawings, technical specifications, and
Bid Form Notes;
(g) the General Terms and Conditions of the ITB;
(h) FDEP Grant Agreement No. P25011, including its applicable attachments, exhibits, and
approved amendments, but only to the extent applicable to the Project or required to be imposed
upon Contractor;
(i) the Notice to Bidders, Scope of Work, Instructions to Bidders, and other requirements
of the ITB;
(j) Contractor’s completed Bid Form and Bid Schedule;
5
(k) Contractor’s certifications, representations, qualifications, personnel commitments,
subcontractor information, and other required Bid submissions, but only to the extent they establish
an obligation or representation by Contractor and do not conflict with or attempt to modify another
Contract Document; and
(l) the performance bond and payment bond required by this Agreement.
2.2 Excluded Documents and Terms. The Contract Documents do not include, and the City does
not accept:
(a) qualifications, exceptions, exclusions, reservations, assumptions, proposed
substitutions, or proposed contractual terms included in Contractor’s Bid unless expressly accepted
by the City in an addendum issued before Bid opening or in this Agreement;
(b) Contractor quotations, proposals, acknowledgments, invoices, purchase-order terms,
website terms, standard conditions, or other unilateral documents;
(c) oral statements, representations, interpretations, or promises;
(d) preliminary drafts or prior versions of this Agreement or another Contract Document;
or
(e) shop drawings, product data, samples, schedules, submittals, requests for information,
meeting minutes, inspection reports, or other administrative documents, except to the limited
extent that a Contract Document expressly incorporates a specific portion of such document by a
duly authorized amendment or Change Order.
No excluded document or term shall modify the Work, Contract Sum, Contract Time, or allocation
of risk.
2.3 Order of Precedence. If an irreconcilable conflict exists among the Contract Documents, the
order listed in Section 2.1 controls, with the document listed first having the highest priority.
However:
(a) an amendment or Change Order controls only to the extent and for the subject matter
expressly addressed in that instrument;
(b) a specific provision controls over a general provision concerning the same subject;
(c) detailed technical requirements control over general descriptions of the same Work; and
(d) where two requirements can reasonably be performed together, both shall apply and
shall not be considered conflicting.
6
2.4 More Stringent Requirements. If the plans, specifications, Bid Form Notes, or other technical
requirements establish different standards of quality, quantity, performance, testing, or
workmanship that are not irreconcilable, Contractor shall provide the higher quality, greater
quantity, more stringent performance, or more complete Work without additional compensation.
This subsection does not authorize Contractor to disregard a stated dimension, design requirement,
or written direction from the City or Design Professional.
2.5 Duty to Identify Conflicts. Contractor shall carefully study and compare the Contract
Documents and promptly notify the City in writing of any error, inconsistency, ambiguity,
omission, or conflict discovered by Contractor.
Before Bid opening, a Bidder shall request clarification through the procedure established in the
ITB. After award, Contractor shall provide notice before performing the affected Work and shall
obtain the City’s written interpretation. Contractor shall not proceed based on its own
interpretation when the interpretation could affect cost, time, quality, safety, or grant compliance.
Failure to identify a matter that a reasonably prudent and experienced contractor should have
identified does not entitle Contractor to additional compensation or time.
2.6 Pre-Bid Questions and Pricing. Contractor acknowledges that it had the opportunity before
Bid opening to:
(a) review all Contract Documents;
(b) inspect the Project Site;
(c) request interpretations or clarifications;
(d) identify proposed substitutions or exceptions; and
(e) account in its Bid for the requirements and risks stated or reasonably inferable from the
Contract Documents.
Except for a concealed condition or other adjustment expressly authorized by this Agreement,
Contractor’s failure to request clarification before Bid opening does not relieve Contractor from
performing the Work or entitle Contractor to additional compensation or time.
2.7 Bidder Assent to Agreement. This Agreement was included in the ITB as the City’s required
form of agreement. By submitting its Bid, Contractor represented and agreed that:
(a) it reviewed and accepted this Agreement and the other Contract Documents;
(b) its Bid constitutes an offer to execute this Agreement without substantive revision if
awarded;
7
(c) any requested exception was required to be submitted and resolved through the pre-bid
question-and-addendum process;
(d) award does not create a right to negotiate or reopen any provision of this Agreement or
the allocation of risk established by the Contract Documents; and
(e) failure to timely execute this Agreement and furnish the required bonds and insurance
constitutes grounds for rescission of the award, enforcement of the Bid security, and award to
another Bidder.
2.8 Effect of Contractor’s Bid. Contractor’s Bid may supplement the Contract Documents only
by:
(a) establishing the accepted prices;
(b) identifying committed personnel, subcontractors, equipment, experience, and
performance representations; and
(c) imposing obligations on Contractor that exceed the minimum requirements of the ITB.
Contractor’s Bid may not reduce the Work, qualify Contractor’s obligations, alter the Contract
Time, shift risk to the City, or introduce additional terms unless the City expressly accepted the
particular deviation in an addendum issued before Bid opening or in this Agreement.
2.9 Administrative Review Does Not Amend Contract. Review, approval, acceptance, or lack
of objection by the City or Design Professional regarding a schedule, submittal, shop drawing,
request for information, pay application, inspection, test result, or other administrative document:
(a) is limited to the purpose for which the document was submitted;
(b) does not constitute a Change Order;
(c) does not authorize additional compensation or time;
(d) does not shift responsibility for errors, omissions, dimensions, quantities, coordination,
means, methods, safety, or compliance; and
(e) does not waive any requirement of the Contract Documents.
2.10 Bonds Do Not Limit Contractor’s Obligations. The performance bond and payment bond
provide additional security and do not modify, replace, or limit Contractor’s obligations under the
other Contract Documents. Any bond provision that affords the City less protection than required
by this Agreement or applicable law shall not reduce Contractor’s obligations or the City’s rights.
8
2.11 Entire Agreement. The Contract Documents constitute the complete and exclusive
agreement between the Parties concerning the Project and supersede all prior or contemporaneous
negotiations, communications, representations, drafts, and agreements concerning the Work.
Neither Party is relying on a statement or representation not contained in the Contract Documents.
2.12 Amendments. The Contract Documents may be modified only by a written amendment or
Change Order executed in accordance with this Agreement and applicable City approval
requirements. Oral direction, silence, email, meeting minutes, course of dealing, course of
performance, payment, inspection, or use of the Work shall not amend the Contract Documents or
establish apparent authority to do so.
3. SCOPE AND STANDARD OF PERFORMANCE
3.1 General Scope. Contractor shall furnish all labor, supervision, administration, materials,
equipment, tools, transportation, temporary facilities, testing, permitting, coordination,
documentation, and incidentals necessary to complete the Chester Byrd Park Improvements in
accordance with the Contract Documents.
The Work generally includes demolition and site preparation; tree protection, removal, and
relocation; the basketball court and park improvements; sidewalks, slabs, parking, driveway,
curbing, pavement markings, signage, fencing, and gates; drainage and utility improvements;
electrical and lighting improvements; landscaping and irrigation; site preparation for City-
purchased equipment and furnishings; preparation for the future restroom and splash pad;
restoration; testing; record drawings; and Project closeout.
This summary does not limit the more detailed requirements of the Contract Documents.
3.2 Complete Work. Contractor shall provide a complete, safe, functional, and code-compliant
Project suitable for its intended use. Work shown or described in any Contract Document, and
minor work reasonably inferable as necessary to complete, connect, support, test, protect, or make
operational the Work shown or described, is included in the Contract Sum unless expressly
identified as City-furnished, City-performed, or payable under an allowance.
This provision does not require Contractor to correct a material design error or provide a material
addition to the Project scope without an adjustment authorized under Section 7.
3.3 Standard of Performance. Contractor shall perform the Work in a good and workmanlike
manner using properly licensed, qualified, and experienced personnel and new materials unless
otherwise permitted. The Work shall comply with the Contract Documents, approved submittals,
manufacturer instructions, applicable permits, the Florida Building Code, accessibility
requirements, utility standards, and applicable law.
9
3.4 Review and Verification. Before commencing each portion of the Work, Contractor shall
review the applicable Contract Documents, examine existing conditions, and verify field
dimensions, elevations, locations, and quantities affecting that Work. Contractor shall promptly
notify the City of any apparent error, omission, inconsistency, dimensional conflict,
constructability concern, or code issue before proceeding with the affected Work.
Contractor is not responsible for the adequacy of the Project design unless design responsibility is
expressly delegated to Contractor, but remains responsible for errors or additional costs resulting
from its failure to identify a condition that a reasonably prudent and experienced contractor should
have identified.
3.5 Site Conditions. Contractor acknowledges that it had the opportunity required by the ITB to
inspect the Project Site and evaluate reasonably observable conditions affecting access, staging,
storage, deliveries, utilities, public protection, sequencing, and performance of the Work.
Contractor is not entitled to additional compensation or time for a condition it knew or reasonably
should have discovered, subject to the concealed-condition provisions of Section 7.
3.6 Quantities and Incidental Work. Quantities stated in the Bid Schedule are estimates unless
expressly stated otherwise. Payment for unit-price Work shall be based on actual quantities
installed, documented, and accepted.
Each Bid item includes the related excavation, dewatering, disposal, bedding, backfill,
compaction, connections, fittings, supports, testing, protection, restoration, and other incidental
work necessary to complete that item unless separately identified for payment.
3.7 City-Purchased Equipment and Furnishings. The City has purchased or will purchase the
equipment and furnishings identified in Bid Items 52-54, 79-80 and 82–83 through direct purchase
orders with designated vendors.
Unless otherwise directed by the City in writing:
(a) Contractor shall exclude the purchase price, delivery charge, and vendor and vendor
delivery charges for those items from its Bid. Contractor shall install the City-purchased equipment
and furnishings assigned to Contractor under the final Bid Documents. Contractor’s accepted
prices include all assigned installation labor, sitework, equipment, coordination, and incidental
Work required for a complete installation;
(b) Contractor shall provide the site preparation, supporting improvements, utility
coordination, grading, access, and other Work required by the plans and Bid Form Notes;
(c) Contractor shall coordinate its schedule and Work with the City and designated vendors
and provide reasonable access for delivery and any installation expressly assigned to a designated
vendor;
10
(d) Contractor shall verify the prepared areas, dimensions, elevations, clearances, and
utility locations before vendor installation and promptly report any apparent conflict, shortage,
damage, or defect; and
(e) Contractor shall be responsible for damage, rework, delay, or additional cost caused by its
deficient site preparation, protection, access, or coordination or installation.
The synthetic turf, aggregate base, concrete ribbon curb, and any other item expressly identified
in the final Bid Documents as vendor-installed shall be installed by the applicable designated
vendor. Contractor is not responsible for a designated vendor’s means, methods, workmanship, or
installation defects except to the extent caused or contributed to by Contractor. Contractor remains
responsible for its assigned site preparation, supporting Work, coordination, protection, and
access.
Contractor is not responsible for a designated vendor’s means, methods, workmanship, or
installation defects except to the extent caused or contributed to by Contractor.
3.7.1 Scope Clarifications. Notwithstanding any conflicting notation in the Contract
Documents:
(a) Bid Item 42 includes furnishing and installing the exfiltration trench. The word “Removed”
appearing in the bid form was an inadvertent editorial notation and does not remove the exfiltration
trench from the Contractor’s Work.
(b) The Work includes twelve (12) new solar light poles. The four additional light poles depicted
on the applicable plan are existing basketball-court light poles and are not additional new solar
light poles.
(c) The concrete ribbon curb is included in the City’s direct purchase order and will be furnished
and installed by the City’s vendor. The Contractor remains responsible for all required site
preparation and for coordinating with and providing site access to the vendor for delivery and
installation.
3.8 City-Performed Work. The City will perform the work expressly assigned to it in the Bid
Schedule or Bid Form Notes, including Bid Items 12, 17, and 18. Contractor shall not include a
charge for that work but shall coordinate its schedule, access, sequencing, and protection with the
City.
3.9 Coordination and Protection. Contractor shall coordinate its Work with the City, designated
vendors, utilities, and separate contractors; protect existing improvements, utilities, trees,
adjoining property, and the public; maintain required access and traffic controls; keep the Project
Site secure and orderly; remove debris regularly; and restore disturbed areas as required by the
Contract Documents.
Damage caused by Contractor or persons for whom Contractor is responsible shall be corrected at
no additional cost or time.
11
3.10 Means and Methods. Contractor is solely responsible for construction means, methods,
techniques, sequences, procedures, temporary works, safety precautions, and coordination of the
Work. Review, inspection, or observation by the City or Design Professional does not transfer that
responsibility or relieve Contractor from compliance with the Contract Documents.
3.11 Separate Contractors. The City may perform work with its own forces or separate
contractors. Contractor shall reasonably coordinate and cooperate with those parties without
disrupting the Project. Contractor is not entitled to additional compensation or time for
coordination reasonably contemplated by the Contract Documents.
4. TERM; COMMENCEMENT; COMPLETION; LIQUIDATED DAMAGES
4.1 Term. This Agreement begins on the Effective Date and continues through Final Completion
and final payment, unless earlier terminated in accordance with the Contract Documents.
Obligations that by their nature extend beyond completion or termination shall survive.
4.2 Notice to Proceed. Contractor shall not commence physical Work until the City issues a
written Notice to Proceed (“NTP”). The NTP shall establish the date from which the Contract Time
is measured. Contractor shall mobilize and commence the Work within seven (7) days after that
date.
Costs incurred before the NTP are at Contractor’s risk unless expressly authorized by the City in
writing. If the City terminates this Agreement for convenience before issuing the NTP, the City
may reimburse Contractor for reasonable, documented, and nonrecoverable costs of Project-
specific bonds and insurance required after award.
4.3 Completion. Contractor shall achieve:
(a) Substantial Completion within one hundred (100) calendar days after the date
established in the NTP; and
(b) Final Completion within one hundred thirty (130) calendar days after the date
established in the NTP.
Notwithstanding the foregoing, Contractor shall achieve Final Completion no later than April 15,
2027, unless FDEP approves a later Project Completion Date in writing and the City authorizes a
corresponding extension by Change Order.
The City anticipates issuing the NTP sufficiently in advance to provide the full Contract Time. If
the City proposes to issue the NTP after the date that would provide Contractor the full one hundred
thirty (130) calendar days before April 15, 2027, the Parties shall establish a revised schedule in
writing before physical Work begins. Contractor is not required to accept a reduction in the
Contract Time resulting solely from the City’s delayed issuance of the NTP.
4.4 Grant Deadline. Contractor acknowledges that the Project is partially funded under FDEP
Grant Agreement No. P25011, which establishes April 30, 2027 as the Project Completion Date
12
and states that no extension is available. The April 15, 2027 contractual deadline is intended to
preserve time for inspection, correction, acceptance, documentation, and grant closeout.
Contractor shall plan, staff, procure, coordinate, and perform the Work so that the contractual and
grant deadlines are met. No extension beyond April 15, 2027 is effective unless authorized as
provided in Section 4.3.
4.5 Project Schedule. Within ten (10) days after the NTP, Contractor shall submit a detailed
Project schedule showing the sequence and duration of material activities, required submittals and
approvals, procurement of long-lead items, coordination with City-designated vendors,
inspections, testing, Substantial Completion, punch-list correction, closeout, and Final
Completion.
Contractor shall update the schedule with each monthly Application for Payment. If progress falls
materially behind for reasons attributable to Contractor, Contractor shall submit and implement a
recovery schedule within five (5) days after the City’s written request. Contractor shall bear the
cost of recovering a delay for which it is responsible.
City review or acceptance of a schedule does not modify the Contract Time, shift responsibility to
the City, or authorize additional compensation.
4.6 Time Is of the Essence; Liquidated Damages. Time is of the essence. If Contractor fails to
achieve Substantial Completion or Final Completion within the applicable time, as properly
adjusted by Change Order, Contractor shall pay the City liquidated damages of One Thousand Six
Hundred Sixty-Five Dollars ($1,665.00) for each calendar day the applicable milestone remains
unachieved.
Liquidated damages for Substantial Completion cease when Substantial Completion is achieved.
Liquidated damages for Final Completion begin only after the Final Completion deadline and shall
not overlap with Substantial Completion liquidated damages for the same day.
The Parties agree that the City’s delay damages would be difficult to determine when this
Agreement is executed and that the stated amount is a reasonable estimate of anticipated
administrative, inspection, operational, grant-related, and loss-of-use costs and is not a penalty.
The City may deduct liquidated damages from amounts due or recover them from Contractor and
the performance bond.
4.7 Other Damages. Liquidated damages apply only to losses arising from delayed achievement
of the applicable completion milestone. They do not limit recovery for defective Work, property
damage, third-party claims, indemnification obligations, unauthorized charges, or grant funding
denied, reduced, recaptured, or required to be repaid because of Contractor’s deficient
documentation, unauthorized change, ineligible charge, defective Work, or other breach
independent of delay. The City shall not obtain a double recovery for the same loss.
13
4.8 Extensions. The Contract Time may be extended only by a written Change Order. The
grounds, notice requirements, documentation, and available remedies for delay are governed by
Section 8.
5. CONTRACT SUM AND PRICING
5.1 Contract Sum. The initial Contract Sum is $1,428,397.94, calculated using the lump-sum
prices and estimated quantities stated in Contractor’s accepted Bid Schedule. The amount payable
to Contractor shall be adjusted based on actual quantities of unit-price Work performed and
accepted, authorized use of allowances, and changes approved in accordance with the Contract
Documents.
The Contract Sum is not a guaranteed minimum payment or representation that the City will
require every estimated quantity.
5.2 Lump-Sum and Unit-Price Work.
(a) Lump-sum items shall be paid based on the percentage of that item satisfactorily
completed and accepted.
(b) Unit-price items shall be paid by multiplying the applicable Bid unit price by the actual
quantity incorporated into the Work, measured, documented, and accepted in accordance with the
Contract Documents.
(c) Contractor shall provide the City a reasonable opportunity to verify quantities before
Work is covered, removed, or otherwise becomes impracticable to measure.
(d) If the Bid Schedule contains a mathematical error, the unit price controls over an
extended total, and the corrected sum shall govern.
5.3 Estimated Quantities. Quantities stated in the Bid Schedule are estimates provided for bidding
and comparison purposes. Actual quantities may increase or decrease based on field conditions
and the City’s needs.
Adjustments based solely on actual quantities shall be calculated using the applicable Bid unit
prices and do not require renegotiation of those prices. A material change in the character or scope
of the Work shall be addressed under Section 7.
Contractor is not entitled to anticipated profit, overhead, or damages on estimated quantities or
Bid items that are not authorized or performed.
5.4 Costs Included in Prices. Except for costs expressly designated as an allowance or City
responsibility, the lump-sum and unit prices include all costs necessary to complete the Work,
including:
14
(a) labor, supervision, and administration;
(b) materials, equipment, tools, transportation, and delivery;
(c) temporary facilities, access, staging, maintenance of traffic, safety, security, and
cleanup;
(d) bonds, insurance, licenses, permits, fees, and taxes imposed upon Contractor;
(e) testing, inspection coordination, surveys, record drawings, warranties, and closeout;
(f) overhead and profit; and
(g) incidental and related work required for a complete Project.
Contractor is not entitled to additional compensation merely because a necessary component of
the Work is shown or described in one Contract Document but is not separately listed in the Bid
Schedule.
5.5 Firm Pricing. Contractor’s lump-sum and unit prices remain firm throughout the Contract
Time and include reasonably foreseeable changes in the cost or availability of labor, materials,
equipment, transportation, fuel, and other inputs.
Contractor is not entitled to escalation, surcharge, market adjustment, or other price increase
except to the extent expressly authorized by a Change Order for a change in the Work or another
adjustment specifically permitted by the Contract Documents.
5.6 Allowances. Allowances identified in the Bid Schedule, including Bid Items 5, 8, and 51 as
applicable, are reserved amounts and are not earned lump-sum compensation.
Allowance Work or expense shall:
(a) be incurred only after written authorization from the City;
(b) be reimbursed based on documented actual cost;
(c) be supported by invoices, receipts, proof of payment, and other documentation
reasonably required by the City; and
(d) not include markup unless the Contract Documents or the City’s written authorization
expressly permit it.
Any unused allowance shall be deducted from the Contract Sum at Project closeout. Contractor is
not entitled to overhead, profit, or damages on an unused allowance.
15
5.7 Markup on Changed Work. For changed Work priced on the basis of actual cost, Contractor
may apply a markup not exceeding ten percent (10%) to subcontracted labor, materials, equipment,
and third-party services.
The combined markup at all Contractor and subcontractor tiers shall not exceed ten percent (10%).
No markup is permitted on:
(a) taxes;
(b) bonds or insurance;
(c) permit, inspection, connection, or governmental fees;
(d) allowance expenditures unless expressly authorized;
(e) costs for which overhead or profit is already included; or
(f) another markup.
Credits for deleted Work shall include the overhead and profit included in the price of that Work.
Detailed pricing and documentation requirements for changed Work are governed by Section 7.
5.8 Taxes and City Direct Purchases. The City is exempt from applicable sales and use taxes.
Contractor shall pay all taxes legally imposed upon Contractor, its purchases, or its operations and
shall not include taxes from which the City is exempt as a separate charge to the City.
Contractor shall cooperate with any lawful City direct-purchase process identified in the Contract
Documents or later authorized by Change Order. Contractor shall not charge markup on City-
purchased materials or equipment and shall credit the Contract Sum for costs avoided through the
direct purchase.
6. APPLICATIONS FOR PAYMENT; RETAINAGE; FINAL PAYMENT
6.1 Schedule of Values. Before submitting its first Application for Payment, Contractor shall
provide a schedule of values allocating the Contract Sum among the Bid items and principal
components of the Work. The schedule shall be consistent with the accepted Bid Schedule and
sufficiently detailed to permit evaluation of progress.
The City may reject an unbalanced, unsupported, or insufficiently detailed schedule of values.
Acceptance of the schedule does not alter the Contract Sum or constitute acceptance of a price
assigned to any particular component.
6.2 Applications for Payment. Contractor may submit one Application for Payment each month
for Work satisfactorily performed through the stated payment period. Each Application for
Payment shall be submitted to the person or office identified by the City and shall include:
16
(a) the amount requested by Bid item and schedule-of-values component;
(b) quantities and percentages completed during the payment period;
(c) documentation supporting unit-price quantities;
(d) invoices and receipts for allowances and other reimbursable costs;
(e) an updated Project schedule;
(f) testing, inspection, and progress documentation reasonably required by the City;
(g) releases required under Section 6.5; and
(h) other documentation required by the Contract Documents or reasonably necessary for
City or grant review.
An Application for Payment is not proper until it contains the required information and
documentation.
6.3 Stored Materials. The City may, but is not required to, pay for materials or equipment suitably
stored at the Project Site or at another location approved in writing. Payment for stored materials
is conditioned upon Contractor providing evidence satisfactory to the City of:
(a) the purchase price and payment obligation;
(b) clear identification for use exclusively on the Project;
(c) proper storage, protection, and insurance;
(d) clear title, free of liens and competing claims;
(e) the City’s right to inspect the materials; and
(f) transfer of ownership to the City upon payment.
Payment does not relieve Contractor from responsibility for loss, damage, installation, testing, or
replacement until Final Completion.
6.4 Review and Payment. The City shall review, approve, reject, and pay Applications for
Payment in accordance with the Florida Local Government Prompt Payment Act, including
Sections 218.735 and 218.74, Florida Statutes.
If an Application for Payment is deficient, the City shall provide written notice identifying the
deficiency and corrective action required within the time provided by law. The City shall timely
pay any undisputed portion of a proper Application for Payment.
17
City approval or payment does not constitute acceptance of defective or incomplete Work, confirm
the accuracy of quantities or percentages, or waive any requirement of the Contract Documents.
6.5 Releases and Contractor Certification. Each Application for Payment shall include:
(a) Contractor’s conditional release for the Work covered by the current Application for
Payment;
(b) Contractor’s unconditional release through the preceding payment period;
(c) releases from subcontractors, suppliers, and materialmen whose Work was included in
the preceding paid Application for Payment; and
(d) Contractor’s certification that amounts previously received from the City have been
properly applied to pay obligations relating to the Project.
The City may require additional releases, affidavits, or bond documentation permitted by Section
255.05, Florida Statutes. Consent of Surety or other surety documentation does not substitute for
Contractor’s obligation to timely pay undisputed amounts owed to subcontractors and suppliers.
6.6 Retainage. The City shall withhold five percent (5%) from each progress payment as retainage,
subject to Sections 218.735, 255.077, and 255.078, Florida Statutes.
The City may release all or part of the retainage before Final Completion but is not required to do
so except as provided by law. Any early release does not constitute acceptance of Work, waive
correction or warranty obligations, or limit the City’s right to withhold other amounts authorized
by the Contract Documents.
6.7 Withholding Payment. In addition to retainage, the City may withhold from an Application
for Payment an amount reasonably necessary to protect the City from loss arising from:
(a) defective, damaged, or incomplete Work;
(b) claims, liens, notices of nonpayment, or reasonable evidence that a claim is likely;
(c) Contractor’s failure to pay subcontractors, suppliers, or laborers;
(d) damage to the City, another contractor, or third-party property;
(e) failure to maintain the Project schedule or reasonable evidence that the Work cannot be
completed within the Contract Time or unpaid Contract balance;
(f) liquidated damages;
18
(g) failure to provide required bonds, insurance, releases, records, or grant documentation;
(h) unauthorized or unsupported charges; or
(i) another material breach of the Contract Documents.
The City shall provide the written notice required by applicable law and shall release the
appropriate amount when the basis for withholding has been resolved. Withholding under this
subsection is separate from the five-percent retainage.
6.8 Substantial Completion and Completion List. Before the date Contractor claims Substantial
Completion, Contractor shall inspect the Work and submit a preliminary list of incomplete or
corrective items.
The City, Contractor, and Design Professional, if applicable, shall inspect the Work and develop
a single list of items required to render the Work complete, satisfactory, and acceptable. The list
shall include a reasonable estimated cost to complete each item and shall be finalized and delivered
to Contractor no later than the date the City certifies Substantial Completion.
Failure to include an item on the list does not relieve Contractor from its obligation to complete or
correct the Work. Contractor shall complete all listed items within the period between Substantial
Completion and Final Completion.
6.9 Payment Following Completion List. Upon receipt of a proper Application for Payment
following development of the completion list, the City shall pay the remaining Contract balance
and retainage as required by applicable law, less:
(a) an amount equal to one hundred fifty percent (150%) of the estimated cost to complete
the listed items;
(b) amounts subject to a good-faith written dispute;
(c) amounts subject to a claim under Section 255.05, Florida Statutes; and
(d) other amounts the City is lawfully entitled to withhold independently of retainage.
Upon completion of all listed items, Contractor may submit an Application for Payment for the
remaining amount. Warranty items arising after preparation of the completion list shall not delay
payment of retainage except as permitted by law.
6.10 Final Payment. Final payment is conditioned upon Final Completion and Contractor’s
delivery of the following, as applicable:
(a) a final Application for Payment;
(b) Contractor’s final affidavit and unconditional release;
19
(c) final releases from subcontractors, suppliers, and materialmen;
(d) consent of Surety to final payment;
(e) record drawings and final surveys;
(f) warranties, operation and maintenance information, and manufacturer documentation;
(g) final testing, inspection, and permit approvals;
(h) evidence that all correction and completion-list items have been completed;
(i) keys, access devices, and other items required for operation;
(j) final quantity and allowance reconciliation;
(k) required public records and grant-supporting documentation; and
(l) other closeout items required by the Contract Documents.
The City shall not require a release of a specifically identified, unresolved claim as a condition of
payment of an otherwise undisputed amount.
6.11 Effect of Final Payment. Acceptance of final payment constitutes Contractor’s waiver of
claims against the City arising from the Project, except claims specifically identified in writing as
unresolved before acceptance of final payment.
Final payment does not waive the City’s rights concerning defective or nonconforming Work,
warranties, latent defects, indemnification, fraud, record retention, audit findings, grant repayment,
or obligations that survive completion.
6.12 Payment of Subcontractors and Suppliers. Contractor shall pay subcontractors and
suppliers all undisputed amounts due from each City payment within ten (10) days after Contractor
receives the payment. Contractor shall require each subcontractor to pay its subcontractors and
suppliers within seven (7) days after receipt, as required by Section 218.735, Florida Statutes.
A disputed amount may be withheld only if the party whose payment is withheld receives written
notice stating the amount disputed and the action required to cure the dispute. All undisputed
amounts shall be timely paid.
Contractor remains solely responsible for payment of its subcontractors and suppliers. The City
has no contractual duty to them and may use joint checks or direct payments as a protective
measure without assuming such a duty.
20
6.13 Grant Reimbursement. Payment by FDEP or reimbursement of the City under the Grant
Agreement is not a condition precedent to payment for Work otherwise properly performed,
documented, and payable under this Agreement.
The City may withhold or recover an amount if FDEP denies, reduces, recaptures, or requires
repayment of funding because of Contractor’s breach, ineligible charge, deficient documentation,
unauthorized change, defective Work, or untimely performance.
7. CHANGES IN THE WORK
7.1 City-Directed Changes. The City may order additions, deletions, revisions, resequencing, or
other changes within the general scope of the Project. An adjustment to the Contract Sum or
Contract Time is effective only through:
(a) a written Change Order executed by Contractor and the City through officials
authorized to bind the City; or
(b) a written directive issued under Section 7.4 requiring Contractor to proceed before the
adjustment is agreed upon.
A Change Order shall identify the change in the Work and any resulting adjustment to the Contract
Sum and Contract Time. Except as expressly stated in the Change Order, all other Contract
Documents remain unchanged.
7.2 No Unauthorized Changes. Contractor shall not perform additional or changed Work without
prior written authorization from the City. Oral instructions, field discussions, meeting minutes,
inspection comments, responses to requests for information, review of submittals, emails, or
conduct at the Project Site do not authorize additional compensation or time unless they expressly
constitute a written directive under Section 7.4 or are incorporated into an executed Change Order.
Contractor proceeds at its own risk if it performs additional or changed Work without the
authorization required by this Section.
7.3 Change Proposals. When the City requests a proposal for changed Work, Contractor shall
submit a complete written proposal within seven (7) days, unless the City establishes another
reasonable period. The proposal shall include:
(a) a clear description of the proposed change;
(b) itemized labor hours and rates;
(c) material quantities and prices;
(d) equipment costs and applicable rates;
(e) subcontractor and supplier quotations;
21
(f) applicable taxes and permitted markup;
(g) credits for deleted or replaced Work;
(h) the proposed adjustment to the Contract Sum;
(i) the proposed adjustment to the Contract Time, supported by an analysis showing the
effect on the critical path; and
(j) other documentation reasonably necessary to evaluate the proposal.
Contractor shall not include unsupported lump sums, duplicative markup, or costs already included
in the Contract Sum.
7.4 Written Directive to Proceed. If the Parties have not agreed upon the price or time associated
with a change, the City may issue a written directive requiring Contractor to proceed with the
changed Work while the adjustment remains unresolved.
Contractor shall proceed promptly and maintain detailed records of labor, materials, equipment,
subcontractor costs, and schedule effects. The adjustment shall thereafter be determined under the
pricing and claim procedures of the Contract Documents.
A written directive to proceed does not constitute acceptance of Contractor’s proposed price or
time adjustment.
7.5 Pricing of Changes. The adjustment for changed Work shall be determined using one or more
of the following methods, as selected or approved by the City:
(a) applicable unit prices contained in the Bid Schedule;
(b) an agreed lump sum;
(c) verified actual cost plus the markup permitted by Section 5.7; or
(d) another method agreed upon in writing.
If an existing unit price reasonably applies to changed Work of substantially the same character
and performed under substantially similar conditions, that unit price shall govern. If the character,
quantity, or conditions materially differ, the Parties shall determine an equitable adjustment.
Credits for deleted Work shall include the labor, materials, equipment, subcontractor costs,
overhead, and profit included in the price of that Work.
22
7.6 Time Adjustments. A proposal for changed Work shall identify any requested adjustment to
the Contract Time. If Contractor does not identify a time impact in its proposal, the Change Order
shall be presumed to have no effect on the Contract Time unless the impact could not reasonably
have been determined at that time.
An extension is permitted only to the extent the change delays the critical path after reasonable
mitigation. A Change Order extending the Contract Time beyond the outside completion date
stated in Section 4 requires any necessary FDEP approval.
7.7 Concealed or Unknown Conditions. If Contractor encounters a subsurface or concealed
physical condition that:
(a) materially differs from a condition indicated in the Contract Documents; or
(b) is of an unusual nature and materially differs from conditions ordinarily encountered
and generally recognized as inherent in work of the character required,
Contractor shall stop the affected Work, protect the condition, and notify the City in writing before
disturbing it. The City shall promptly investigate and determine whether a change is warranted.
Contractor is not entitled to an adjustment for a condition it knew or reasonably should have
discovered through the site investigation, utility-location process, or review required by the
Contract Documents. Contractor’s failure to provide notice before disturbing the condition waives
an adjustment to the extent the failure prejudices the City’s ability to investigate or mitigate the
condition.
7.8 Emergency Work. In an emergency threatening injury, loss of life, or material damage to
property or the Work, Contractor shall take reasonable action necessary to prevent or minimize
harm and shall notify the City as soon as practicable.
If the emergency was not caused by Contractor or a person for whom Contractor is responsible,
any appropriate adjustment shall be determined under this Section. Contractor shall not perform
nonemergency corrective or additional Work beyond what is reasonably necessary to address the
immediate threat without written City authorization.
7.9 Grant-Related Changes. Contractor shall not materially alter a Project Element funded under
FDEP Grant Agreement No. P25011 without prior written City authorization. Contractor
acknowledges that FDEP approval may be required before the City can authorize the change.
The City’s request for a proposal, consideration of a substitution, or submission of a proposed
change to FDEP does not authorize Contractor to proceed.
7.10 Processing of Change-Order Price Quotes. A price quote submitted in response to a change
requested or issued by the City shall comply with Section 7.3 and shall be clearly identified as a
“Change-Order Price Quote Submitted Under Section 218.755, Florida Statutes.” It shall be
23
submitted to the City Representative at the address or electronic location designated in the NTP or
subsequent written notice.
The City shall approve or deny a complete and compliant price quote and provide written notice
of its decision within thirty-five (35) days after receipt, as required by Section 218.755, Florida
Statutes. A denial shall identify the deficiencies and the actions necessary to correct them. Nothing
in this Agreement alters the City’s statutory obligations or the legal effect of failing to provide the
required notice.
7.11 Contractor-Initiated Requests. If Contractor believes that an instruction, event, or condition
not initiated by the City entitles it to additional compensation or time, Contractor shall provide
notice and submit its request in accordance with Section 20. A Contractor-initiated request is not
authorized Work and does not modify the Contract Documents unless accepted through a Change
Order.
8. DELAYS AND EXTENSIONS
8.1 Contractor Responsibility. Contractor shall prosecute the Work diligently and coordinate
labor, materials, equipment, subcontractors, permits, inspections, and vendor activities to achieve
Substantial Completion and Final Completion within the Contract Time.
Contractor shall anticipate and account for delays ordinarily associated with construction of this
type, including normal weather, routine governmental review, ordinary procurement conditions,
and coordination reasonably contemplated by the Contract Documents.
8.2 Excusable Delay. Contractor may receive a reasonable extension of the Contract Time to the
extent performance of a critical-path activity is delayed by an event that:
(a) was beyond Contractor’s reasonable control;
(b) was not caused or contributed to by Contractor or a person for whom Contractor is
responsible;
(c) could not reasonably have been anticipated or avoided;
(d) could not reasonably have been overcome through mitigation, resequencing, or use of
available float; and
(e) actually delayed completion of the Work.
Potential excusable delays include an authorized City change, differing site condition qualifying
under Section 7.7, abnormal governmental action, labor dispute not limited to Contractor’s
workforce, unavoidable casualty, declared emergency, and unusually severe weather.
24
8.3 Noncompensable Delay. Except as provided in Section 8.4, Contractor’s sole remedy for an
excusable delay is a reasonable extension of the Contract Time. Contractor is not entitled to
additional compensation for delays caused by weather, casualty, declared emergency, industry-
wide labor dispute, governmental action not caused by the City, or another event beyond the
control of both Parties.
8.4 Compensable Delay. Contractor may receive an equitable adjustment of the Contract Sum for
reasonable, documented direct costs resulting from a critical-path delay caused solely by:
(a) a City-directed change in the Work;
(b) an unreasonable City-ordered suspension not caused by Contractor;
(c) the City’s failure to provide access or information at the time expressly required by the
Contract Documents; or
(d) another material breach by the City.
Any adjustment is subject to Contractor’s compliance with the notice, documentation, mitigation,
and Change Order requirements of the Contract Documents. Contractor is not entitled to
consequential damages, lost profits, loss of productivity unsupported by contemporaneous records,
or home-office overhead calculated by a formula unless expressly approved in a Change Order.
8.5 Contractor-Caused and Concurrent Delay. Contractor is not entitled to additional
compensation or time for delay caused by:
(a) inadequate staffing, supervision, planning, or coordination;
(b) late or deficient submittals;
(c) failure to timely order materials or equipment;
(d) reasonably foreseeable labor, material, or equipment availability;
(e) subcontractor or supplier default, except to the extent caused by a separate qualifying
excusable event;
(f) defective or nonconforming Work;
(g) failure to obtain required permits or inspections in a timely manner;
(h) failure to maintain required bonds or insurance; or
(i) another act or omission of Contractor or a person for whom Contractor is responsible.
25
If an excusable delay occurs concurrently with a Contractor-caused delay and Contractor cannot
reasonably separate their effects, Contractor is entitled to neither additional compensation nor an
extension for the concurrent period. If the effects can be separated through a reliable critical-path
analysis, an adjustment may be allowed only for the independently demonstrated excusable
portion.
8.6 Weather Delay. Contractor is entitled to an extension for unusually severe weather only if the
weather:
(a) was materially more severe than reasonably anticipated for the location and season;
(b) prevented performance of critical-path Work despite reasonable protective measures;
and
(c) was documented by contemporaneous Project records and reliable weather data from
the nearest appropriate reporting station.
Normal seasonal weather and the reasonably anticipated effects of rain, heat, wind, and wet-site
conditions are included in the Contract Time. An extension for unusually severe weather shall be
limited to the actual critical-path delay after reasonable mitigation.
8.7 City-Purchased Equipment and Separate Vendors. Contractor shall coordinate its schedule
with the City and the vendors furnishing or installing City-purchased equipment and furnishings.
Contractor is not entitled to an adjustment for delay caused by its failure to timely coordinate,
prepare the site, provide access, or identify an apparent conflict. If timely delivery or installation
by a City-designated vendor is delayed for reasons not caused by Contractor and the delay affects
the critical path, Contractor may receive a reasonable extension.
Additional compensation is available only if the delay was caused by the City’s unreasonable act
or omission and satisfies Section 8.4.
8.8 Notice and Documentation. Contractor shall notify the City in writing within seven (7) days
after Contractor becomes aware, or reasonably should have become aware, of an event that may
delay the Work. The notice shall describe the event, its anticipated effect, affected activities, and
mitigation being undertaken.
Within fourteen (14) days after the effect can reasonably be determined, Contractor shall provide:
(a) the dates and duration of the delay;
(b) the affected critical-path activities;
(c) an updated schedule analysis;
(d) measures taken to avoid or mitigate the delay;
26
(e) the extension and compensation, if any, requested; and
(f) supporting cost and Project records.
If the delay continues, Contractor shall provide reasonable periodic updates. Failure to provide
timely notice or documentation waives the requested adjustment only to the extent the City is
materially prejudiced by that failure.
8.9 Mitigation and Continued Performance. Contractor shall take reasonable steps to avoid and
mitigate delay, including resequencing Work, reallocating resources, expediting submittals or
procurement when reasonable, and continuing unaffected Work.
Contractor shall not suspend or slow performance because a request for additional compensation
or time is pending unless the City directs otherwise in writing.
8.10 Float. Float in the Project schedule is available to the Project and is not exclusively owned
by either Party. An extension is permitted only to the extent an excusable delay consumes available
float and delays the applicable contractual completion milestone.
8.11 No Constructive Acceleration. Contractor is not entitled to compensation for acceleration
unless the City issues a written directive requiring completion earlier than the date established by
the Contract Documents after accounting for approved extensions.
The City’s enforcement of an existing completion deadline, request for a recovery schedule, or
rejection of an unsupported extension request does not constitute acceleration.
8.12 Grant Deadline. Contractor acknowledges the grant-related deadlines stated in Section 4. An
excusable delay may entitle Contractor to an extension under this Section, but no extension beyond
the applicable outside completion date is effective unless FDEP approves the required extension
and the City authorizes it by Change Order.
If FDEP does not approve an extension for an otherwise excusable delay, the Parties shall
promptly evaluate lawful mitigation, acceleration, scope adjustment, suspension, or termination.
Contractor is not required to absorb the cost of acceleration caused solely by a compensable City
delay unless the City authorizes that cost by Change Order.
9. PROJECT ADMINISTRATION; SUBMITTALS; INSPECTION; TESTING
9.1 Contractor’s Supervision. Contractor shall supervise and direct the Work and is responsible
for coordinating all portions of the Work. Contractor shall designate a competent superintendent
who:
(a) is experienced in projects of similar scope and complexity;
(b) is authorized to act on Contractor’s behalf;
27
(c) shall be present at the Project Site whenever material Work is being performed; and
(d) shall not be replaced without prior notice to and approval by the City, except when
immediate replacement is necessary because of an emergency or separation from employment.
Communications given to the superintendent concerning routine Project administration are binding
upon Contractor but do not amend the Contract Documents or authorize additional compensation
or time.
9.2 City Administration. The City Representative and any designated project manager, inspector,
or Design Professional may administer the Contract Documents, observe the Work, review
submittals, evaluate Applications for Payment, interpret technical requirements, and determine
whether the Work generally conforms to the Contract Documents.
No such person may amend the Agreement, authorize additional compensation or time, or waive
a requirement of the Contract Documents unless expressly authorized in writing by the City.
9.3 Project Meetings and Reports. Contractor shall participate in preconstruction, progress,
coordination, and closeout meetings reasonably required by the City. Contractor shall provide
current information regarding:
(a) progress and schedule;
(b) submittals and procurement;
(c) inspections and testing;
(d) coordination with utilities and City-designated vendors;
(e) pending changes or claims;
(f) safety and site conditions; and
(g) matters that may affect cost, time, quality, or grant compliance.
Contractor shall maintain daily reports identifying personnel, subcontractors, equipment, Work
performed, deliveries, weather, inspections, testing, delays, and material events. Reports shall be
available to the City upon request.
9.4 Submittal Schedule. Contractor shall prepare and maintain a submittal schedule coordinated
with the Project schedule. The schedule shall allow reasonable time for Contractor review, City or
Design Professional review, resubmission, procurement, fabrication, and installation without
delaying the Work.
Contractor is not entitled to additional compensation or time arising from a late, incomplete,
inaccurate, or uncoordinated submittal.
28
9.5 Contractor Review of Submittals. Before submission to the City or Design Professional,
Contractor shall review and approve each shop drawing, product-data submission, sample,
delegated-design document, and other submittal.
Contractor’s approval represents that it has:
(a) verified materials, field measurements, quantities, dimensions, and existing conditions;
(b) coordinated the submittal with other portions of the Work;
(c) confirmed compliance with the Contract Documents; and
(d) clearly identified each proposed deviation or substitution.
Submittals not reviewed and approved by Contractor, or containing unidentified deviations, may
be returned without review.
9.6 Review of Submittals. City or Design Professional review is limited to determining general
conformance with the design intent and Contract Documents. Review does not relieve Contractor
from responsibility for:
(a) dimensions, quantities, or field measurements;
(b) errors or omissions in a submittal;
(c) coordination of the Work;
(d) construction means, methods, sequences, procedures, or safety;
(e) compliance with laws, permits, or manufacturer requirements; or
(f) deviations not clearly identified in writing.
Contractor shall not fabricate or install Work requiring a submittal until the applicable submittal
has been reviewed. Review of a specific item does not approve an unmarked deviation or a change
to the Contract Sum or Contract Time.
9.7 Requests for Information. Contractor shall submit a written request for information when
clarification of the Contract Documents is reasonably necessary. Each request shall:
(a) identify the applicable drawing, specification, or requirement;
(b) describe the issue clearly;
(c) state when a response is needed to avoid delay; and
29
(d) include Contractor’s proposed interpretation or solution when reasonably available.
A response to a request for information interprets the existing Contract Documents and is not
authorization for additional compensation or time. If Contractor believes the response changes the
Work, Contractor shall provide notice and proceed under Sections 7 and 20.
9.8 Access and Inspection. The City, Design Professional, FDEP, building officials, and other
authorized governmental representatives may inspect the Work and Project records at reasonable
times. Contractor shall provide safe access and reasonable assistance for inspection.
Contractor shall notify the appropriate inspector sufficiently in advance before Work is covered or
becomes inaccessible. If Contractor covers Work before a required inspection, Contractor shall
uncover, replace, and restore the Work at its expense.
Inspection, lack of inspection, failure to identify a defect, use, or occupancy does not constitute
acceptance of defective Work or relieve Contractor of responsibility for compliance.
9.9 Testing. Contractor shall arrange and pay for testing required by the Contract Documents,
permits, applicable law, and authorities having jurisdiction, including materials, density,
compaction, pressure, disinfection, bacteriological, electrical, operational, and other testing
applicable to the Work, unless a Contract Document expressly assigns a particular test to the City.
Testing shall be performed by qualified laboratories, agencies, or individuals acceptable to the City
and independent of Contractor when required by law or the Contract Documents. Contractor shall
coordinate testing, provide required samples and access, and furnish test results promptly to the
City.
9.10 City-Provided Testing. If the Contract Documents assign a test to the City, Contractor shall
provide reasonable advance notice and prepare the Work for testing. Contractor shall remain
responsible for coordinating the test with its schedule.
If Work fails a test or Contractor fails to provide adequate notice or access, Contractor shall pay
the cost of retesting and resulting inspection, removal, repair, and restoration. If compliant Work
is delayed solely because the City fails to timely perform a City-assigned test after proper notice,
Contractor may request an adjustment under Section 8.
9.11 Defective or Nonconforming Work. The City or Design Professional may reject Work that
does not conform to the Contract Documents. Contractor shall promptly correct, remove, or
replace rejected Work and shall bear the resulting costs, including testing, inspection, professional
services, and restoration of other affected work.
If Contractor disputes the rejection, it shall preserve its claim under Section 20 but shall proceed
as directed unless the City provides written direction otherwise.
9.12 Record Drawings and Closeout Records. Contractor shall maintain current field-marked
drawings showing actual locations, dimensions, elevations, utilities, concealed conditions, and
30
approved changes. Contractor shall not defer preparation of record information until the end of the
Project.
Before Final Completion, Contractor shall provide final record drawings, surveys, test reports,
inspection records, permits, approvals, warranties, manuals, photographs, and other closeout
documentation required by the Contract Documents. Documents required to be signed and sealed
shall be prepared by an appropriately licensed Florida professional.
10. PERMITS; UTILITIES; ENVIRONMENTAL AND LEGAL COMPLIANCE
10.1 Compliance with Laws. Contractor shall perform the Work in accordance with all applicable
federal, state, county, and City laws, codes, ordinances, rules, regulations, permits, and lawful
orders of authorities having jurisdiction.
Contractor shall promptly notify the City of an apparent conflict between a legal requirement and
a Contract Document before performing the affected Work. Contractor is not responsible for
determining whether the Project design complies with law unless design responsibility is expressly
delegated to Contractor, but Contractor shall not proceed with Work it knows or reasonably should
know violates an applicable requirement.
10.2 Permits and Approvals. Unless expressly assigned to the City, Contractor shall obtain,
maintain, comply with, and close all permits, licenses, approvals, and inspections required for the
Work. Contractor shall:
(a) timely prepare and submit required applications and supporting documents;
(b) coordinate reviews and inspections with authorities having jurisdiction;
(c) keep permits and approved documents available at the Project Site;
(d) promptly provide the City copies of permits, inspection reports, notices, and approvals;
and
(e) obtain final approval or closure of each permit before Final Completion.
Contractor shall not be entitled to additional compensation or time resulting from its late,
incomplete, or deficient permit submission or failure to comply with permit requirements.
10.3 Permit and Governmental Fees. Contractor shall pay permit, inspection, connection,
capacity, and governmental fees in the first instance unless the City directs otherwise.
Reimbursement shall be limited to fees expressly included in an allowance or identified as
reimbursable in the Contract Documents.
Reimbursable fees shall be paid at documented actual cost without markup and supported by
receipts or other proof acceptable to the City. Any unused allowance shall be credited to the City.
31
Dewatering and NPDES permit fees shall be reimbursed as provided in the ITB. Potable-water
permit, connection, capacity, and utility fees shall be administered under Bid Item 90, except for
fees expressly included in another Bid item under the Addenda.
10.4 Existing Utilities. Before excavation or other Work that may affect utilities, Contractor shall:
(a) contact the applicable utility-notification system;
(b) review available utility information;
(c) coordinate with utility owners and the City;
(d) field-locate and verify utilities within the affected area; and
(e) use appropriate methods to protect existing facilities.
The location of existing utilities shown in the Contract Documents is approximate unless expressly
stated otherwise. Contractor shall immediately stop affected Work and notify the City and utility
owner if it encounters an unidentified, mismarked, or conflicting utility.
An adjustment for an unknown utility shall be governed by Sections 7 and 8. No adjustment is due
to the extent the condition should have been identified through required utility-location or
verification procedures.
10.5 Utility Interruptions and Connections. Contractor shall not interrupt, disconnect, or modify
an existing utility without prior approval from the City and the affected utility owner. Contractor
shall provide required notice, coordinate temporary service when necessary, and schedule
interruptions to minimize disruption.
Contractor shall perform utility connections, testing, disinfection, clearance, and restoration in
accordance with the Contract Documents and utility-owner requirements. Contractor is
responsible for unauthorized interruptions and damage caused by its Work.
10.6 Environmental Protection. Contractor shall comply with applicable environmental
requirements and the approved stormwater-pollution-prevention and erosion-control measures.
Contractor’s responsibilities include, as applicable:
(a) erosion and sediment control;
(b) inlet and surface-water protection;
(c) dewatering and discharge controls;
(d) dust, mud, and noise control;
(e) prevention of contaminated runoff;
32
(f) lawful handling, transportation, and disposal of waste and excavated material;
(g) required inspections, monitoring, maintenance, and reporting; and
(h) final stabilization and removal of temporary controls.
Contractor shall maintain environmental controls throughout the period they are required and shall
promptly correct deficient controls.
10.7 Spills and Contractor-Caused Contamination. Contractor shall prevent spills and releases
arising from its operations. If a spill or release occurs, Contractor shall immediately:
(a) protect persons and property;
(b) stop and contain the release;
(c) notify the City and authorities as required by law;
(d) perform required cleanup and remediation; and
(e) provide the City documentation of the incident and corrective action.
Contractor is responsible for costs, fines, penalties, testing, remediation, and delay to the extent
caused by Contractor or persons for whom Contractor is responsible.
10.8 Preexisting Hazardous Materials. Contractor is not responsible for remediation of
hazardous material or contamination that existed at the Project Site before Contractor’s operations
and was not identified in the Contract Documents or reasonably discoverable during required site
investigation.
If Contractor encounters suspected hazardous material or contamination, it shall stop affected
Work, secure the area, avoid disturbing the condition, and promptly notify the City. The City shall
determine the appropriate investigation and response. Any adjustment shall be governed by
Sections 7 and 8.
Contractor is responsible for a preexisting condition to the extent its negligent or unauthorized
actions disturb, spread, or increase the condition or resulting costs.
10.9 Trench and Excavation Safety. Contractor shall comply with the Florida Trench Safety Act,
Section 553.60 et seq., Florida Statutes, applicable OSHA requirements, and the trench-safety
method identified in its Bid.
Contractor’s prices include the cost of required trench-safety systems and excavation protection.
Contractor shall maintain documentation required by law and shall not change the identified
compliance method without providing the City any required revised documentation.
33
10.10 Violations and Corrective Action. Contractor shall promptly notify the City of any citation,
notice of violation, stop-work order, environmental complaint, or governmental enforcement
action relating to the Work.
Contractor shall promptly correct a violation caused by Contractor without additional
compensation or time. If a violation results from a requirement of the Contract Documents that
Contractor could not reasonably have identified before performing the affected Work, any
adjustment shall be determined under Sections 7 and 8.
11. GRANT REQUIREMENTS
11.1 Grant Funding. Contractor acknowledges that the Project is partially funded through Florida
Department of Environmental Protection Grant Agreement No. P25011 under the Florida
Recreation Development Assistance Program.
The Grant Agreement provides a maximum State award of $200,000, requires a $200,000 City
match, establishes April 30, 2027 as the Project Completion Date, and states that no extension is
available. Contractor shall comply with the grant requirements applicable to its Work and shall
reasonably assist the City in satisfying its obligations to FDEP.
11.2 Applicable Grant Requirements. Contractor is responsible only for provisions of the Grant
Agreement that:
(a) expressly apply to contractors or subcontractors;
(b) relate to the performance, documentation, inspection, or acceptance of the Work;
(c) must be included in lower-tier contracts; or
(d) require Contractor’s cooperation for the City to obtain or retain grant funding.
A provision applicable solely to the City in its capacity as the FDEP grantee does not create an
independent obligation of Contractor except to provide the cooperation and documentation
reasonably required for City compliance.
11.3 Authorized Project Elements. Contractor shall perform the Work consistently with the
Project elements approved by FDEP, including the new exercise equipment, fencing, landscaping,
and walking trail and the renovation of the basketball court, picnic shelter, and playground.
Contractor shall not materially alter, eliminate, substitute, or relocate an approved Project element
without prior written authorization from the City. Contractor acknowledges that FDEP approval
may be required before the City can authorize a material change.
A request for a substitution, proposed Change Order, or submission of a proposed revision to FDEP
does not authorize Contractor to proceed with the affected change.
34
11.4 Notice to Commence. Contractor shall not begin grant-funded physical Work until the City
issues the NTP required by Section 4. The City is responsible for obtaining any required FDEP
Notice to Commence before issuing the NTP.
Contractor may rely on the City’s NTP as confirmation that the City has obtained the governmental
authorization necessary to commence the Project, except for permits and approvals expressly
assigned to Contractor.
11.5 Documentation and Reimbursement Support. Contractor shall maintain and provide
records sufficient to establish that the Work and costs submitted for payment are eligible,
reasonable, properly authorized, and directly related to the Project. Required records include, as
applicable:
(a) detailed invoices and Applications for Payment;
(b) actual unit-price quantities and measurement records;
(c) invoices, receipts, and proof of payment for allowances and reimbursable costs;
(d) subcontractor and supplier invoices;
(e) labor, material, and equipment records supporting changed Work;
(f) procurement and pricing documentation reasonably requested by the City;
(g) inspection, testing, permit, and acceptance records;
(h) progress photographs and record drawings; and
(i) other Project documentation reasonably required for FDEP review, audit, or closeout.
Contractor shall provide requested documentation promptly and in sufficient time for the City to
meet its reporting, reimbursement, and closeout deadlines.
11.6 Inspections, Audits, and Access to Records. Contractor shall permit the City, FDEP, the
Florida Chief Financial Officer, the Florida Auditor General, the applicable Inspector General, and
their authorized representatives to inspect the Work and review or copy Project records at
reasonable times.
Contractor shall cooperate with a lawful audit, investigation, inspection, or grant-compliance
review and shall require its subcontractors to provide corresponding access to records relating to
the Project.
Inspection, review, or reimbursement by FDEP does not constitute acceptance of defective Work
or relieve Contractor of an obligation under the Contract Documents.
35
11.7 Record Retention. Contractor shall retain Project records for at least five (5) years after Final
Completion and for any longer period required by:
(a) the Grant Agreement;
(b) applicable Florida records-retention schedules;
(c) an unresolved audit, investigation, claim, or litigation; or
(d) applicable law.
Contractor shall include corresponding record-retention and access requirements in its
subcontracts.
11.8 Grant-Eligible Costs. Contractor shall not knowingly submit an ineligible, unsupported,
unauthorized, or duplicative cost. Equipment purchases are not eligible for grant reimbursement
under the Grant Agreement, and Contractor shall not characterize a purchase as a grant-
reimbursable cost when the Grant Agreement excludes it.
This limitation does not prevent payment for Contractor’s eligible labor, site preparation,
equipment rental, installation-related Work, or other authorized services merely because the City
separately purchased park equipment or furnishings.
11.9 Contractor Payment and Grant Reimbursement. FDEP reimbursement of the City is not
a condition precedent to payment for Work properly authorized, performed, documented, and
payable under this Agreement.
The City may withhold or recover an amount to the extent FDEP denies, reduces, recaptures, or
requires repayment of grant funding because of Contractor’s:
(a) untimely or incomplete performance;
(b) defective or nonconforming Work;
(c) unauthorized change to an approved Project element;
(d) ineligible, unsupported, or inaccurate charge;
(e) failure to maintain or provide required records; or
(f) other breach of the Contract Documents.
Contractor shall not be responsible for loss of grant funding caused solely by the City’s failure to
satisfy an obligation not assigned to Contractor. The City shall not obtain double recovery for a
loss already compensated through liquidated damages or another remedy.
36
11.10 Flow-Down to Subcontractors. Contractor shall include applicable grant-performance,
documentation, record-retention, audit-access, and compliance requirements in each subcontract
relating to the Project.
Contractor remains responsible for its subcontractors’ compliance and shall not contend that a
subcontractor’s failure excuses Contractor’s performance.
11.11 No Third-Party Rights. The Grant Agreement does not create a contractual relationship
between Contractor and FDEP. Contractor has no right to payment directly from FDEP, and FDEP
assumes no contractual obligation to Contractor or its subcontractors under this Agreement.
12. SUBCONTRACTORS AND PERSONNEL
12.1 Contractor shall submit a subcontractor list and may not substitute a listed key subcontractor
or key person without prior written City approval. Approval does not create a contractual
relationship with the City or relieve Contractor of full responsibility.
12.2 Contractor shall bind subcontractors to the Contract Documents to the extent applicable and
require written subcontracts, prompt payment, insurance, safety, licensing, public-records
compliance, grant records, warranties, and indemnity consistent with this Agreement.
12.3 The City may require removal from the Project of any person who is unsafe, unqualified,
disorderly, abusive, or materially interferes with City operations. Contractor shall promptly
provide a qualified replacement at no added cost or time.
12.4 Contractor shall not assign this Agreement, delegate material duties, or transfer a controlling
interest without the City’s prior written consent. Any unauthorized assignment is void and grounds
for termination.
13. SAFETY AND SITE SECURITY
13.1 Contractor is solely responsible for initiating, maintaining, and supervising all safety
programs and precautions, including protection of workers, City personnel, park users, pedestrians,
motorists, property, and the public. Contractor shall comply with OSHA and all applicable safety
laws and immediately correct unsafe conditions.
13.2 Contractor shall secure and fence construction areas, maintain approved traffic and pedestrian
controls, preserve emergency access, and prevent unauthorized public entry. The park environment
and presence of children require enhanced care in barriers, housekeeping, equipment security, and
daily shutdown.
13.3 Contractor shall promptly report any injury, property damage, utility strike, spill, safety
citation, or significant near miss and provide written incident documentation within twenty-four
(24) hours. Reporting does not admit liability or relieve Contractor of other duties.
37
13.4 In an emergency, Contractor shall act immediately to prevent threatened harm and then notify
the City. The City may stop unsafe Work. A safety stop caused by Contractor is not grounds for
additional time or compensation.
14. BONDS AND INSURANCE
14.1 Performance and Payment Bonds. Within fourteen (14) days after notice of award and
before issuance of the NTP, Contractor shall furnish performance and payment bonds, each in the
full Contract Sum, on the City’s project-specific forms and executed by a surety authorized to
transact business in Florida and acceptable to the City.
The bonds shall comply with Section 255.05, Florida Statutes, and identify the correct Contractor,
Surety, City, contract number, bond number, Project address, and general description of the
Chester Byrd Park Improvements.
Contractor shall record the bonds in the public records of Broward County and provide the City
certified copies and recording information before commencing Work. The City shall not be
required to make payment until Contractor has satisfied these requirements.
14.2 Bond Coverage. The bonds shall remain effective through Final Completion and for any
additional period required by the bond forms, Contract Documents, or applicable law.
Contractor shall provide any bond rider or other surety documentation reasonably required because
of an increase in the Contract Sum or other material modification. The Surety’s consent is not
required for a change unless expressly required by applicable law or the accepted bond form.
14.3 Insurance. Before commencing Work, Contractor shall obtain and maintain the insurance
required by the ITB and its insurance exhibit. Coverage shall remain in effect for the periods
specified in those requirements, including applicable completed-operations and warranty periods.
The City may require additional insurance during performance only if:
(a) Contractor proposes a material change in its operations or means and methods that
creates a risk not reasonably contemplated when Bids were submitted;
(b) the additional coverage is required by law; or
(c) Contractor and the City agree to the requirement through a Change Order addressing
any resulting adjustment.
Required insurance does not limit Contractor’s liability under the Contract Documents. Contractor
is responsible for all deductibles and self-insured retentions.
14.4 Policy Requirements. Policies shall include the additional-insured, primary-and-
noncontributory, waiver-of-subrogation, completed-operations, and notice provisions required by
the ITB and insurance exhibit.
38
Certificates of insurance do not amend policy terms or independently establish compliance.
Contractor shall provide copies of required endorsements or policies upon reasonable request and
shall ensure that its Subcontractors maintain the insurance applicable to their Work.
14.5 Continuing Compliance. Contractor shall provide renewal certificates and required
endorsements before coverage expires. Contractor shall promptly notify the City of cancellation,
nonrenewal, material reduction, or lapse of required coverage.
Contractor shall not perform affected Work while required bonds or insurance are not in effect. A
lapse caused by Contractor is a material breach and does not entitle Contractor to additional
compensation or time. The City may withhold payment, stop the affected Work, or exercise other
remedies under the Contract Documents until compliance is restored.
15. CORRECTION; WARRANTY; TITLE
15.1 Contractor’s Warranty. Contractor warrants that:
(a) materials and equipment furnished by Contractor are new and of good quality unless
otherwise permitted by the Contract Documents;
(b) the Work will be free from defects in materials and workmanship;
(c) the Work will conform to the Contract Documents, approved submittals, applicable law,
permits, and manufacturer requirements; and
(d) the City will receive clear title to the Work, materials, and equipment furnished by
Contractor, free of liens and claims.
Work not conforming to these requirements, including an unauthorized substitution, is defective.
15.2 Correction of Defective Work. Contractor shall promptly correct, remove, or replace
defective, damaged, or nonconforming Work identified before or after Substantial Completion.
Contractor shall bear the resulting costs, including investigation, testing, inspection, removal,
professional services, access, and restoration of other affected work.
If Contractor fails to begin and diligently pursue required correction after written notice, the City
may correct the condition and deduct its reasonable costs from amounts due or recover them from
Contractor and Surety. Immediate action may be taken without prior notice when reasonably
necessary to protect persons, property, or the Work.
15.3 Correction Period. For one (1) year after Substantial Completion, or for a longer period
stated in the Contract Documents or applicable manufacturer warranty, Contractor shall correct
covered defects after receiving notice from the City.
39
The correction period for Work corrected or replaced during that period shall continue for one (1)
year after completion of the correction or replacement. This obligation supplements and does not
limit other warranties, latent-defect claims, indemnification obligations, or applicable statutes of
limitation or repose.
15.4 Manufacturer and Supplier Warranties. Contractor shall obtain all available manufacturer,
supplier, and Subcontractor warranties required by the Contract Documents. To the extent
permitted by the warranty issuer, each warranty shall be registered in the City’s name and for the
City’s sole benefit.
Before Final Completion, Contractor shall provide the City with executed warranty documents,
required registrations, effective dates, claim procedures, and contact information. Contractor shall
assist the City in enforcing those warranties and remains responsible for its own obligations
regardless of another available warranty.
15.5 Warranty Exclusions. Contractor’s warranty does not cover damage or a defect to the extent
caused by:
(a) abuse or misuse by the City or a third party after the City accepts control of the affected
Work;
(b) a modification not performed or authorized by Contractor;
(c) improper or insufficient maintenance contrary to written maintenance requirements
provided to the City;
(d) improper operation contrary to written operating instructions provided to the City; or
(e) normal wear and tear.
Contractor bears the burden of demonstrating that an exclusion applies. An exclusion does not
relieve Contractor from responsibility to the extent its defective Work caused or contributed to the
condition.
15.6 City-Purchased Equipment. Contractor does not warrant the manufacture or installation of
equipment or furnishings purchased by the City and installed by a City-designated vendor.
Contractor remains responsible for:
(a) its site preparation and supporting Work;
(b) utility and dimensional coordination assigned to Contractor;
(c) protection and handling within Contractor’s control;
(d) damage caused by Contractor; and
40
(e) defects resulting from Contractor’s failure to timely identify an apparent conflict or
nonconforming condition.
Contractor shall cooperate with the City and designated vendor in documenting and pursuing an
applicable vendor or manufacturer warranty. The Contractor’s warranty does not apply to the
concrete ribbon curb furnished and installed by the City’s vendor, except that the Contractor
remains responsible for its own site-preparation and coordination work associated with the ribbon
curb.
15.7 Landscape and Establishment Obligations. Warranty and establishment obligations for
landscaping, relocated trees, irrigation, and related Work shall continue for the periods stated in
the plans, specifications, or Bid Form Notes. If no different period is stated, the one-year correction
period in Section 15.3 applies.
16. INDEMNIFICATION
16.1 To the fullest extent permitted by Section 725.06, Florida Statutes, Contractor shall indemnify
and hold harmless the City and its elected officials, officers, employees, and agents from liabilities,
damages, losses, and costs, including reasonable attorneys’ fees, to the extent caused by the
negligence, recklessness, or intentionally wrongful conduct of Contractor or persons employed or
utilized by Contractor in performance of the Contract Documents.
16.2 Contractor shall defend and indemnify the City from claims, liens, bond claims, and demands
for payment by Contractor’s subcontractors, suppliers, laborers, or others furnishing labor,
materials, or equipment, except to the extent caused by the City’s failure to pay an undisputed
amount finally determined due to Contractor.
16.3 Contractor shall be responsible for fines, penalties, remediation costs, and grant repayment
or loss to the extent caused by its violation, breach, or deficient documentation. These obligations
are not limited by insurance, bonds, or the Contract Sum and survive completion or termination.
16.4 Nothing in this Agreement waives the City’s sovereign immunity or limits under Section
768.28, Florida Statutes, or creates liability beyond that provided by law. Nothing requires the City
to indemnify Contractor.
17. DEFAULT AND CITY REMEDIES
17.1 Contractor Default. Contractor is in default if it:
(a) fails to commence or diligently prosecute the Work;
(b) fails to provide adequate qualified workers, supervision, materials, or equipment;
(c) fails to pay Subcontractors or suppliers undisputed amounts when due;
(d) performs defective or nonconforming Work and fails to timely correct it;
41
(e) violates applicable law, permit, or material safety requirement;
(f) fails to maintain required bonds or insurance;
(g) fails to provide required records, releases, schedules, or grant documentation;
(h) abandons the Work;
(i) becomes insolvent or subject to a bankruptcy or receivership proceeding that materially
impairs performance, to the extent remedies are permitted by applicable law; or
(j) otherwise materially breaches a Contract Document.
17.2 Notice and Opportunity to Cure. Except as provided below, the City shall provide written
notice describing the default and allow Contractor five (5) days after receipt to cure the default or,
if it cannot reasonably be cured within five (5) days, to begin the cure and diligently complete it
within a period acceptable to the City.
The City may take immediate protective action or terminate without an additional cure period
when reasonably necessary because of:
(a) an emergency threatening persons or property;
(b) abandonment of the Work;
(c) failure to timely commence the Work;
(d) lapse of required bonds or insurance;
(e) unlawful conduct or a material safety violation; or
(f) a default that is not reasonably capable of cure.
The City shall comply with any separate notice or procedural requirements necessary to preserve
its rights against the Surety under the performance bond. Compliance with the bond does not
extend Contractor’s contractual cure period unless the City agrees otherwise in writing.
17.3 City Remedies. Upon Contractor’s default, the City may, to the extent appropriate:
(a) stop all or part of the Work;
(b) reject or withhold payment as permitted by the Contract Documents and applicable law;
(c) require Contractor to increase staffing, supervision, materials, or equipment;
(d) supplement Contractor’s forces or arrange for correction or completion of the Work;
42
(e) take possession of materials and equipment incorporated into the Work or purchased
for the Project to which the City has obtained title through payment;
(f) use Contractor-owned tools, construction equipment, or temporary facilities located at
the Project Site only to the extent permitted by the performance bond, applicable law, or a separate
written agreement;
(g) terminate Contractor’s right to proceed with all or part of the Work;
(h) make demand upon the performance or payment bond;
(i) recover completion costs, liquidated damages, and other damages permitted by the
Contract Documents; and
(j) exercise any other cumulative legal or equitable remedy.
Before supplementing Contractor’s forces or arranging completion, the City shall provide notice
reasonably appropriate under the circumstances unless immediate action is necessary to protect
persons, property, the Project schedule, or grant funding.
17.4 Termination for Cause. If the City terminates Contractor’s right to proceed for cause,
Contractor is not entitled to further payment until the terminated Work is completed and the City’s
completion costs and damages are determined.
If the unpaid Contract balance exceeds the City’s completion costs, damages, and other amounts
recoverable under the Contract Documents, the remaining amount shall be paid as required by law.
If those costs and damages exceed the unpaid balance, Contractor and Surety shall be liable for
the difference to the extent provided by the Contract Documents and bonds.
If a termination for cause is finally determined to have been improper, the termination shall be
treated as a termination for convenience under Section 18, and Contractor’s recovery shall be
limited accordingly.
18. TERMINATION OR SUSPENSION FOR CONVENIENCE; FUNDING
18.1 The City may terminate all or part of the Agreement for convenience upon written notice.
Contractor shall stop as directed, protect Work, cancel commitments where practicable, and deliver
materials and records. The City shall pay for conforming Work performed through the termination
date and reasonable, documented demobilization costs, less prior payments and amounts due the
City. Contractor is not entitled to anticipatory profit, consequential damages, unabsorbed
overhead, or recovery on unperformed Work.
18.2 The City may suspend Work by written order. Contractor shall protect the Work and mitigate
cost and delay. If a suspension is caused solely by the City and is unreasonable in duration, an
equitable adjustment may be made by Change Order, subject to notice and documentation
43
requirements. No adjustment is due for a suspension caused by Contractor, safety, weather,
permitting, grant review contemplated by the Contract Documents, or legal compliance.
18.3 City obligations are subject to lawfully available and appropriated funds. If funds are
unavailable, the City may reduce scope, suspend, or terminate without liability beyond amounts
payable under Section 18.1. This clause does not permit the City to avoid payment for accepted
Work from funds legally available for that purpose.
19. PUBLIC RECORDS
19.1 Contractor shall comply with Chapter 119, Florida Statutes, and Section 119.0701, if
applicable. Contractor shall keep and maintain public records required to perform the service;
provide requested records or allow inspection and copying within a reasonable time at lawful cost;
and ensure confidential or exempt records are not disclosed except as authorized by law.
19.2 Upon completion or termination, Contractor shall, at the City’s election, transfer at no cost
all public records to the City or keep and maintain them as required by law. Electronic records
shall be supplied in a format compatible with the City’s systems. If records are transferred,
Contractor shall destroy duplicate confidential or exempt records as required by law.
19.3 IF CONTRACTOR HAS QUESTIONS REGARDING THE APPLICATION OF
CHAPTER 119, FLORIDA STATUTES, TO CONTRACTOR’S DUTY TO PROVIDE
PUBLIC RECORDS RELATING TO THIS AGREEMENT, CONTACT THE CITY’S
CUSTODIAN OF PUBLIC RECORDS: ELORA RIERA, CITY CLERK, 100 WEST
DANIA BEACH BOULEVARD, DANIA BEACH, FLORIDA 33004; TELEPHONE (954)
924-6800, EXT. 3623; EMAIL ERIERA@DANIABEACHFL.GOV.
19.4 Failure to comply is a material breach. The City may enforce this Section, recover reasonable
enforcement costs where permitted by law, and withhold payment until required records are
provided.
20. CLAIMS AND DISPUTE RESOLUTION
20.1 Notice of Claim. If Contractor believes it is entitled to additional compensation, an extension
of time, or other relief, Contractor shall provide written notice to the City within seven (7) days
after Contractor knew or reasonably should have known of the event giving rise to the claim.
The notice shall identify the event, the relief requested, and the known or anticipated effect on cost
and time. Contractor shall not perform disputed additional Work without the authorization required
by Section 7, except for emergency Work or Work performed under a written directive to proceed.
20.2 Supporting Documentation. Within fourteen (14) days after the effect of the event can
reasonably be determined, Contractor shall submit:
44
(a) the factual and contractual basis of the claim;
(b) an itemized calculation of additional compensation requested;
(c) supporting labor, material, equipment, subcontractor, and other cost records;
(d) any requested extension of time and supporting critical-path analysis;
(e) actions taken to avoid or mitigate the effect; and
(f) a certification that the claim is accurate, complete, and submitted in good faith.
If the effects continue, Contractor shall provide reasonable periodic updates and a final statement
after the effects end.
20.3 Effect of Failure to Provide Notice. Compliance with the applicable notice and
documentation requirements is a condition precedent to Contractor’s claim to the extent the City
is materially prejudiced by Contractor’s failure to comply.
If another section establishes a more specific notice or submission requirement for a particular
claim, Contractor shall comply with both provisions to the extent they can reasonably be read
together. The more specific provision controls in the event of an irreconcilable conflict.
20.4 Continued Performance. Contractor shall continue performing the Work during the review
or resolution of a claim or dispute unless the City directs otherwise in writing. Contractor shall
comply with written City directives while preserving its claim.
The City shall continue to pay undisputed amounts properly due under the Contract Documents.
20.5 Good-Faith Resolution. Before filing litigation, the Parties shall attempt in good faith to
resolve the dispute through a meeting between the City Representative and Contractor’s project
representative. If not resolved, either Party may request review by the City Manager or designee
and an authorized executive of Contractor.
The review process does not waive a claim or defense, extend a contractual or statutory deadline,
or prevent either Party from seeking emergency judicial relief. Contractor shall comply with any
administrative claim or dispute procedure required by applicable City ordinance.
20.6 Governing Law and Venue. This Agreement is governed by Florida law. Exclusive venue
for any litigation arising from or relating to the Agreement shall lie in the state courts located in
Broward County, Florida, or, if federal jurisdiction exists, the United States District Court for the
Southern District of Florida.
EACH PARTY KNOWINGLY AND VOLUNTARILY WAIVES TRIAL BY JURY TO THE
FULLEST EXTENT PERMITTED BY LAW.
45
Nothing in this Agreement constitutes consent by the City to arbitration or a waiver of sovereign
immunity or any limitation provided by Section 768.28, Florida Statutes.
20.7 Attorneys’ Fees and Costs. Each Party shall bear its own attorneys’ fees and costs in a
dispute arising from this Agreement except to the extent recovery is expressly authorized by
applicable law, an indemnification obligation, or another specific provision of the Contract
Documents.
20.8 Waiver of Contractor’s Consequential Damages. Contractor waives claims against the City
for consequential, special, or incidental damages, including lost profits on other work, loss of
business opportunity, loss of bonding capacity, and business interruption.
This waiver does not prevent Contractor from recovering compensation expressly authorized by a
Change Order or direct costs recoverable under Section 8.4. The City does not waive its right to
recover damages resulting from Contractor’s breach, subject to the prohibition against double
recovery.
21. NOTICES
21.1 Form and Delivery. A notice required under the Contract Documents shall be in writing and
delivered by:
(a) personal delivery;
(b) nationally recognized overnight courier;
(c) certified United States mail, return receipt requested; or
(d) email, provided the sender receives confirmation of receipt from the recipient.
Notice is effective upon actual delivery. Refusal of delivery constitutes receipt. Routine Project
communications, meeting minutes, submittals, inspection reports, and other administrative
correspondence do not constitute contractual notice unless the communication expressly states that
it is notice under this Agreement and is delivered in accordance with this Section.
21.2 Notices to the City. Notices to the City shall be delivered to:
Candido Sosa-Cruz, City Manager
City of Dania Beach
100 West Dania Beach Boulevard
Dania Beach, Florida 33004
Email: csosacruz@daniabeachfl.gov
46
With a copy to:
Eve A. Boutsis, City Attorney
City of Dania Beach
100 West Dania Beach Boulevard
Dania Beach, Florida 33004
Email: eboutsis@daniabeachfl.gov
A copy may also be required to the City Representative identified in the NTP. Delivery only to a
project manager, inspector, consultant, or Design Professional does not constitute notice to the
City unless that person has been expressly designated in writing to receive contractual notices.
21.3 Notices to Contractor. Notices to Contractor shall be delivered to:
Cesar De Luna, VP-CGC
M & J Consulting Group, Corp.
3350 SW 148th Avenue, Suite 110-9062
Miramar, Florida 33027
Email: cesar@mjgeneralcontractors.com
With a copy to any additional representative identified by Contractor in writing.
21.4 Change of Address. A Party may change its notice address or designated recipient by
providing written notice in accordance with this Section. The change is effective upon receipt.
21.5 Emergency and Field Communications. This Section does not prevent oral or electronic
communications reasonably necessary for emergencies, safety, scheduling, inspections, or daily
administration. When the Contract Documents require formal written notice, the communicating
Party shall provide notice complying with this Section within the applicable time.
22. MISCELLANEOUS AND STATUTORY COMPLIANCE
22.1 Independent Contractor. Contractor is an independent contractor and is not an officer,
employee, agent, joint venturer, or partner of the City. Contractor has no authority to bind the City
or incur an obligation on the City’s behalf.
Contractor is solely responsible for its personnel, compensation, payroll, taxes, benefits,
supervision, and employment obligations.
22.2 No Waiver. A waiver is effective only if stated in writing by a City official authorized to
grant it. A waiver concerning one act, default, or provision does not waive another act, default, or
provision.
Payment, inspection, review, acceptance, use, silence, or failure to enforce a requirement
immediately does not constitute a waiver. Rights and remedies under the Contract Documents are
cumulative.
47
22.3 Severability. If a provision of the Contract Documents is determined to be invalid or
unenforceable, it shall be enforced to the maximum extent permitted by law, and the remaining
provisions shall remain effective unless the invalid provision defeats the essential purpose of the
Agreement.
22.4 Survival. Obligations concerning final payment, correction of Work, warranties,
indemnification, public records, grant records, audits, claims, dispute resolution, and other
obligations that by their nature continue beyond completion or termination shall survive.
22.5 E-Verify. Contractor shall register with and use the E-Verify system to verify the work-
authorization status of all new employees as required by Section 448.095, Florida Statutes.
Contractor shall require each Subcontractor to register with and use E-Verify and to provide
Contractor the affidavit required by that statute. Contractor shall retain each affidavit for the
duration of the Agreement and provide it to the City upon request.
If the City has a good-faith belief that Contractor knowingly violated Section 448.09(1), Florida
Statutes, the City shall terminate the Agreement as required by law. If the City has a good-faith
belief that a Subcontractor knowingly violated the applicable requirements but Contractor
otherwise complied, the City shall notify Contractor, and Contractor shall immediately terminate
the subcontract.
A termination required under Section 448.095 is not a breach by the City. Contractor is liable for
additional costs incurred by the City as a result of a termination as provided by law.
22.6 Public Contracting Eligibility. Contractor represents that it and its affiliates are eligible to
contract with the City and are not prohibited from doing business with a public entity under
applicable Florida law, including laws concerning:
(a) public-entity crimes;
(b) discriminatory vendors;
(c) antitrust violations;
(d) suspended vendors;
(e) scrutinized companies and entities;
(f) boycotts of Israel; and
(g) entities associated with foreign countries of concern.
Contractor shall promptly notify the City if a representation or certification concerning its
eligibility becomes inaccurate during the Agreement.
48
The City may terminate the Agreement if Contractor submitted a false certification or becomes
ineligible or subject to termination under applicable law, including Section 287.135, Florida
Statutes.
22.7 Human-Trafficking Affidavit. Contractor shall provide the affidavit required by Section
787.06(14), Florida Statutes, signed by an officer or authorized representative under penalty of
perjury and attesting that Contractor does not use coercion for labor or services as defined by that
statute.
Contractor represents that the affidavit submitted with its Bid remains accurate as of the Effective
Date and shall provide a new affidavit upon any renewal or extension if required by law.
22.8 Nondiscrimination. Contractor shall not unlawfully discriminate in performing the Work
and shall comply with applicable equal-employment, civil-rights, and accessibility laws. If
Contractor certified that it maintains a drug-free workplace, Contractor shall maintain that program
throughout performance of the Agreement.
22.9 Accuracy of Representations. Contractor represents that its Bid, certifications, affidavits,
and other submissions are complete and accurate; that it is duly organized, licensed, and authorized
to perform the Work; that execution and performance of this Agreement do not violate another
obligation; and that the person executing the Agreement is authorized to bind Contractor.
A material misrepresentation or false certification constitutes a default and may subject Contractor
to statutory remedies in addition to the remedies under the Contract Documents.
22.10 No Third-Party Beneficiaries. Except for the City parties protected by an express
indemnification provision and claimants having statutory rights under the payment bond, the
Contract Documents are solely for the benefit of the City and Contractor and do not create a
contractual right in another person or entity.
22.11 Counterparts and Electronic Signatures. The Agreement may be executed in
counterparts, each of which is deemed an original and all of which constitute one instrument.
Electronic signatures and copies shall have the same effect as original signatures to the extent
permitted by law.
The Effective Date is the date on which the last Party executes the Agreement. Execution does not
authorize commencement of physical Work before the NTP.
22.12 Exhibits. The following exhibits are incorporated into the Agreement:
(a) Exhibit A – Accepted Bid Form and Bid Schedule;
(b) Exhibit B – Chester Byrd Park Improvements Bid Plans and Specifications;
(c) Exhibit C – Final Revised Bid Form Notes issued with Addenda 3 and 6, dated [DATE];
(d) Exhibit D – FDEP Grant Agreement No. P25011;
(e) Exhibit E – Insurance Requirements;
(f) Exhibit F – Performance Bond;
49
(g) Exhibit G – Payment Bond; and
(h) Exhibit H – Addenda Nos. 1 through 6 issued before Bid opening.
The exhibits identified above are incorporated by reference to the corresponding documents
included in the ITB and need not be physically duplicated as attachments to this Agreement. Each
exhibit and addendum shall be identified by its applicable title, date, or number.
SIGNATURES ON THE FOLLOWING PAGES
50
IN WITNESS OF THE FOREGOING, the parties have set their hand and seal the day
and year first written above.
CITY OF DANIA BEACH, FLORIDA,
a Florida municipal corporation
ELORA RIERA, MMC COLMAN RYAN
CITY CLERK MAYOR
APPROVED AS TO LEGAL FORM
AND CORRECTNESS
EVE A. BOUTSIS, CITY ATTORNEY CANDIDO SOSA-CRUZ, ICMA-CM
CITY MANAGER
51
CONTRACTOR:
WITNESSES: M & J CONSULTING GROUP CORP.
a Florida corporation
SIGNATURE SIGNATURE
PRINT Name PRINT Name
SIGNATURE Title
PRINT Name
STATE OF FLORIDA
COUNTY OF BROWARD
The foregoing instrument was acknowledged before me by means of ☐ physical presence
or ☐ online notarization, on , 2026, by _______________ (name),
_______________________ (title), of M & J Consulting Group Corp., a Florida corporation, who
is personally known to me or has produced as
identification.
NOTARY PUBLIC
My Commission Expires: State of Florida