HomeMy WebLinkAboutR-2021-120 Broward MPO Commitment 2045 Metropolitan Transportation Plan (MTP)RESOLUTION NO.2021-120
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA, SUPPORTING BROWARD COUNTY METROPOLITAN
PLANNING ORGANIZATION' S ("MPO") COMMITMENT 2045
METROPOLITAN TRANSPORTATION PLAN (MTP) AND THE CITY OF
DANIA BEACH PROJECTS IDENTIFIED IN SUCH PLAN; PROVIDING FOR
CONFLICTS; FURTHER, PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the Broward Metropolitan Planning Organization ("MPO") in the 2045
Metropolitan Transportation Plan ("MTP") - Affordable and Unfunded Roadway Transportation
Plan Projects List has identified projects within the City of Dania Beach ("City"); and
WHEREAS, Resolution No. 2019-102 supported the City of Dania Beach's projects
included in the Broward Metropolitan Planning Organization's Commitment 2045 MTP; and
WHEREAS, the MPO approved the Commitment 2045 Metropolitan Transportation Plan
("MTP") Cost Feasible Plan on December 12, 2019; and
WHEREAS, the City supports the MPO's "Complete Streets and other Localized
Initiatives Program ("CSLIP"), and adhering to the federal "Local Agency Program ("LAP"), and
more specifically, the City's MPO project approved for NW 1st Street from Bryan Road to US-
1/SR 5; and
WHEREAS, the City is also obtaining MPO funding for its project along N 22°d
Avenue/SW 12 Avenue from Sheridan Street to Stirling Road; and
WHEREAS, the transportation projects in the City have been identified as a transportation
need and are currently ranked projects in the approved draft 2045 Metropolitan Transportation
Plan Cost Feasible Plan, a copy of which is attached as Exhibit "A" and is incorporated into this
Resolution by this reference, with other unranked projects included in the "needs and unfunded"
portion of the MTP; and
WHEREAS, the City Commission deems it to be in the best interest of the citizens and
residents of the City of Dania Beach to continue to support the projects included in the Broward
MPO's MTP Roadway and CSLIP programs and the programmed projects in the Broward MPO's
2021-2025 Transportation Improvement Program ("TIP");
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF DANIA BEACH, FLORIDA:
Section 1. That the foregoing "WHEREAS" clauses are ratified and confirmed as
being true and correct and they are made a specific part of this Resolution.
Section 2. That the City continues to support the transportation projects identified in
this Resolution for inclusion with the MPO MTP Cost Feasible Plan, as well as other projects that
should be included in the "needs and unfunded" portion of the Plan, and more specifically, those
projects identified above.
Section 3. That the City Manager is authorized to do all that is necessary and expedient
in order to carry out the aims of this Resolution.
Section 4. That all resolutions or parts of resolutions in conflict with this Resolution
are repealed to the extent of such conflict.
Section 5. That this Resolution shall take effect immediately upon adoption.
PASSED AND ADOPTED on August 24, 2021.
U1I Y ULLFdl-
APPROVED AS TO
TAMARA J.
MAYOR
CORRECTNESS:
2 RESOLUTION #2021-120
EXHIBIT `A'
City of Dania Beach
Commitment 2045 Metropolitan Transportation Plan (MTP)
Cost Feasible Project List
PROJECT NAME
LOCATION
PROJECT DESCRIPTION
SR 8221 Sheridan St
Sheridan St
Expand roadway from 4 lanes to
From:
6 lanes
• Dixie Hwy
To:
• US1
Old Griffin Rd
Old Griffin Rd / Griffin Rd
Reconfiguration of the
Intersection
intersection and roadway of Old
From:
Griffin Rd and Griffin Rd.
• Bryan Rd
Includes capacity improvements
To:
for westbound Old Griffin Rd
• Griffin Rd
from Bryan Rd. to Griffin Rd
• Improved si nalization timing
US1 / 595 Westbound
US1
• Improve intersection alignments
on -ramp
From:
along US1 and add additional
• 17d' Street
lane to US1 / 1-595 westbound
To:
on ramp to help reduce queuing
• 1-595
on US1.
West Dania Beach
West Dania Beach Blvd
• Roadway improvements
Blvd Corridor
From:
. Intersection improvements on
• US1
local roads,
To:------
Bfid -evei,6 0-- nMf----
• Bryan Rd
• Signalization intersection at
Bryan Rd,
• Improvements to railroad
crossing.
• Potential ROW acquisition,
South Florida Rail
South Florida Rail
• Grade Separation for Stirling Rd
Corridor
Corridor
at the CSX RR
From:
• Stirling Rd
To:
• CSX RR
Ravenswood Rd
Ravenswood Rd
Expand roadway from 2 lanes to
From:
4 lanes
• SW 42"d St
To:
• Griffin Rd
Page 1 of 3
EXHIBIT `A'
City of Dania Beach
Commitment 2045 Metropolitan Transportation Plan (MTP)
Needs and Unfunded Project List
PROJECT NAME
LOCATION
PROJECT DESCRIPTION
JA Ely Boulevard
Ely Boulevard
.
Enhanced sidewalks, ADA ramps,
From:
paving, drainage and bike lanes
•
Stirling Rd.
.
Project has been coordinated with
To:
the City of Hollywood
•
Sheridan St.
South Broward 1-95
1-95
.
PD&E for 1-95 interchange
Interchange PD&E
From:
expansion and improvements at
Griffin Rd
Griffin Road, Stirling Road and
To:
Sheridan Street
•
Sheridan St
•
Project will be coordinated with
Hollywood, Fort Lauderdale and
FDOT
SR 5/US 1
USA
•
Upgrades to support enhanced bus
From:
service along US-1
•
Aventura Mall
To:
•
Downtown Fort
Lauderdale
Terminal
SE 5th Ave
SE 5th Ave
a
Reconstruct roadway to include
From:
multimodal improvement for
•
Dania Beach
pedestrians, bicycles and transit
Blvd
•
As an extension and in coordination
To:
with the NE 14'h Ave project
•
Sheridan St
(Hollywood)
Intersections of SW
SW 40 AVE
Geometric Improvements
40th Ave at Griffin
•
Intersection at
Expand number of turn lanes and
Road and Stirling
Stirling Rd
storage
Road
.
Intersection at
Signalization timing
Griffin Rd
Intersection of US-1 &
US1
Roadway, railroad, signal and turn
Old Griffin Road
Intersection at
lane improvements
(including US-1
Old Griffin Rd
Bridge)
Page 2 of 3
EXHIBIT'A'
City of Dania Beach
Commitment 2045 Metropolitan Transportation Plan (MTP)
Needs and Unfunded Project List
PROJECT NAME
LOCATION
PROJECT DESCRIPTION
Bryan Road
Bryan Rd
Widen ROW and roadway expansion
From:
from 2 lanes to 4 lanes
• Stirling Rd
To:
• Griffin Rd