HomeMy WebLinkAboutR-2000-182 RESOLUTION NO. 2000-182
A RESOLUTION OF THE CITY OF DANIA BEACH,
FLORIDA, APPROVING FOUR (4) CHANGE ORDERS
AMOUNTING TO $6,499.00 SUBMITTED BY CORAL-TECH
ASSOCIATES FOR REMODELING OF THE BSO
RESTROOMS, PROVIDING THAT THE ORIGINAL
CONTRACT AMOUNT OF $49,800.00 SHALL BE
INCREASED TO $56,299.00 FOR SAID PROJECT;
PROVIDING FOR CONFLICTS; FURTHER, PROVIDING
FOR AN EFFECTIVE DATE.
BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA;
Section 1. That those four (4) Change Orders amounting to $6,499.00 submitted
by Coral-Tech Associates for remodeling of the BSO restroom, increasing the original
contract price from $49,800.00 to $56,299.00, in substantial form as Exhibit "A", are
approved and the appropriate city officials are authorized to execute them.
Section 2. The City Manager and City Attorney are authorized to make minor
revisions to said Change Orders as are deemed necessary and proper for the best
interests of the City.
Section 3. That all resolutions or parts of resolutions in conflict with this resolution
are repealed to the extent of such conflict.
Section 4. That this resolution shall be in force and take effect immediately upon
its passage and adoption.
PASSED AND ADOPTED THIS 14t"� of,�f�vemb er, 000.
MAYOR - COMMISSIONER
NER
ATTEST: ROLL CALL:
MAYOR M -YES
VICE-MAYOR OR BE BERTINO- YES
SHERYL ,HAPMAN COMMISSIONER CALI - YES
ACTING CITY CLERK COMMISSIONER ETLING -YES
COMMISSIONER MIKES- YES
APPROVED AS TO F RnM D CORRECTNESS:
BY:
THOMASIJ. A SB O
CITY ATTORNEY
RESOLUTION NO. 2000- 182
CHANGE OWNER
ARCHITECT
ORDER CONTRACTOR
AIA DOCUMENT G701 FIELD ❑
OTHER ❑
PROJECT: HANDICAP TOILET ROOMS CHANGE ORDER NUMBER: ONE(1)
(name,address) CITY OF DANIA BEACH
100 WEST DANIA BLVD. DANIA BEACH, FL DATE: OCTOBER 20, 2000
TO CONTRACTOR: CORAL-TECH ASSOCIATES, INC. ARCHITECT'S PROJECT NO: N/A
(name, address) 10211 WEST SAMPLE ROAD SUITE 207 CONTRACT DATE: MAY 25, 2000
CORAL SPRINGS, FL 33065 CONTRACT FOR: GENERAL CONSTRUCTION
The Contract is changed as follows:
REPAIRS PAIRS TO PVC CONDENSER WATER PIPING ADD $500.00
Not valid until signed by the Owner, Architect and Contractor.
The original (Contract Sum) was----------------------------------------------- $ 49,800.00
Net change by previously authorized Change Orders------------------------------ $ 0.00
The (Contract Sum) prior to this Change Order was-------------------------------- $ 49,800.00
The (Contract Sum) will be (increased) (eleereasecl�
f""ehang by this Change Order in the amount of---------------------- $ 500.00
The new(Contract Sum) including this Change Order will be--------------------- $ 50,300.00
The Contract Time will be(increased)(d,",.,d)(u11e1131tsd)by ONE(1) ( 1 )days.
The date of Substantial Completion as of the date of this Change Order therefore is TO BE DETERMINED
NOTE: This summary does not reflect changes in the Contract Sum,Contract Time or Guaranteed Maximum Price which have been authorized be
Construction Change Directive.
CORAL-TECH ASSOCIATES, INC. CITY OF DANIA BEACH, FLORIDA
ARCHITECT, CONTRACTOR OWNER
10211 WEST SAMPLE ROAD 100 WEST DANIA BEACH BLVD.
Address Address
Address
CORAL Alwas 33065 DANIA B C LORIDA 33004 _
BY BY
DATE DATE L DATE
AIA DOCUMENT G701 * CHANGE ORDER* 1997 EDITION*AIA-1987*THE
AMERICAN INSTITUTE OF ARCHITECTS,1735 NEW YORK AVE.,N.W.,WASHINGTON,D.C.20006 G701-1987
DANIABCH.001
5
October 20, 2000
Mr. Ken Koch
City of Dania Beach, Florida
100 West Dania Beach Boulevard
Dania Beach, Florida 33004
Re: Request for Change Order No. One (1)
Handicap Toilet Rooms and Alterations
Broward County Sheriffs Offices
Dania Beach City Hall
CTA FILE NO: 0004-26
Dear Mr. Koch:
In accordance with your directives, we are submitting our request for change order
applicable to repairs to unforseen embedded piping within concrete slabs of the subject
project, as follows:
Repairs to PVC Condenser Water Piping
Pipe, fittings & accessories $ 41.00
Demolition hammer & equipment 75.00
Plumber 220.00
Project manager 71.00
Subtotal $407.00
Contractor's Overhead 40.70
Subtotal $447.70
Contractor's Fee 44.77
Subtotal $492.47
Contractor's Bond 7.39
TOTAL $499.86
TOTAL AMOUNT OF THIS REQUEST - $500.00
10211 WEST SAMPLE ROAD
SUITE 207
CORAL SPRINGS,FLORIDA 33065
954-753-7252
FAX:954-341-7116
Mr. Ken Koch
Request for Change Order No. One (1)
Handicap Toilet Rooms and Alterations
Broward County Sheriffs Offices
Dania Beach City Hall
CTA FILE NO: 0004-26
October 20, 2000
Page 2.
At this time it appears that the additional work impacted construction progress for a period
of one (1) day. The actual impact on the scheduled completion date will be reviewed in
conjunction with affected construction activities of the project and an additional request will
be submitted for an extension of contract time.
As this work has been completed, we are requesting that a change order be executed at
your earliest opportunity.
Thank you for your kind assistance and cooperation.
Very truly yours,
CORAL-T C AS OCIATES, INC.
JOHN J. VIA , CCE
President
Enclosures
cc: Mr. Joel Miller, Project Manager
daniabch.0510800
CHANGE OWNER
ARCHITECT
ORDER CONTRACTOR
AIA DOCUMENT G701 FIELD ❑
OTHER ❑
PROJECT: HANDICAP TOILET ROOMS CHANGE ORDER NUMBER: TWO (2)
(name,address) CITY OF DANIA BEACH
100 WEST DANIA BLVD. DANIA BEACH,FL DATE: OCTOBER 20, 2000
TO CONTRACTOR: CORAL-TECH ASSOCIATES, INC. ARCHITECT'S PROJECT NO: N/A
(name, address) 10211 WEST SAMPLE ROAD CONTRACT DATE: MAY 25, 2000
SUITE 207
CORAL SPRINGS, FL 33065 CONTRACT FOR: GENERAL CONSTRUCTION
The Contract is changed as follows:
DEMOLITION AND RE-CONSTRUCTION OF PARTITION BETWEEN MEN'S AND
WOMEN'S ROOMS PER ATTACHED REQUEST FOR CHANGE ORDER NO. TWO (2) ADD $ 940.00
Not valid until signed by the Owner, Architect and Contractor.
The original (Contract Sum) was------------------------------------------------- $ 49,800.00
Net change by previously authorized Change Orders------------------------------ $ 500.00
The (Contract Sum) prior to this Change Order was-------------------------------- $ 50,300.00
The (Contract Sum) will be (increased)
Fwnehanged� by this Change Order in the amount of---------------------- $ 940.00
The new(Contract Sum) including this Change Order will be-------------------- $ 51,240.00
The Contract Time will be(increased)Edeepee9e4 by TWO(2) ( 2 )days.
The date of Substantial Completion as of the date of this Change Order therefore is TO BE DETERMINED
NOTE: This summary does not reflect changes in the Contract Sum,Contract Time or Guaranteed Maximum Price which have been authorized be
Construction Change Directive.
1 " 1 CORAL-TECH ASSOCIATES, INC. CITY OF DANIA BEACH, FLORIDA
ARCHITECT CONTRACTOR OWNER
10211 WEST SAMPLE ROAD 100 WEEV D IA REACH BLVD.
Address Address Address
CORAL L 3 5 DANIA L IDA 33004
BY BY
DATE DATE DATE t 0 b
AIA DOCUMENT G701 * CHANGE ORDER* 1997 EDITION*AIA- 1987*THE
AMERICAN INSTITUTE OF ARCHITECTS,1735 NEW YORK AVE.,N.W.,WASHINGTON,D.C.20006 G701-1987
DANIABCH.002
July 19, 2000
Mr. Ken Koch
City of Dania Beach, Florida
100 West Dania Beach Boulevard
Dania Beach, Florida 33004
Re: Request for Change Order No. Two (2)
Handicap Toilet Rooms and Alterations
Broward County Sheriffs Offices
Dania Beach City Hall
CTA FILE NO: 0004-26
Dear Mr. Koch:
In accordance with unforseen conditions, we are submitting our request for change order
applicable to removal and replacement of an existing partition for the subject project, as
follows:
Demolish and Re-construct Partition between IMen's and Women's Rooms
Demolition 110 sf @ $ 1.50 $ 165.00
Trash removal 30.00
New drywall partition 110 sf @ $ 4.00 440.00
Project manager 2 hr @ $65.00 130.00
Subtotal $765.00
Contractor's Overhead 76.50
Subtotal $841.50
Contractor's Fee 84.15
Subtotal $925.65
Contractor's Bond 13.88
TOTAL $939.53
TOTAL AMOUNT OF THIS REQUEST $940.00
10211 WEST SAMPLE ROAD
SUITE 207
CORAL SPRINGS,FLORIDA 33065
954-753-7252
FAX:954-341-7116
Mr. Ken Koch
Request for Change Order No. Two (2)
Handicap Toilet Rooms and Alterations
Broward County Sheriffs Offices
Dania Beach City Hall
CTA FILE NO: 0004-26
July 19, 2000
Page 2.
At this time it appears that the additional work will impact construction progress for a period
of two (2) days. The actual impact on the scheduled completion date will be reviewed in
conjunction with affected construction activities of the project and an additional request will
be submitted for an extension of contract time.
As this work has been completed, we are requesting that a change order be executed at
your earliest opportunity.
Thank you for your kind assistance and cooperation.
Very truly yours,
CORAL-TECH ASS CIATESPCCE
INC.
JOHN VJ. 1
President
cc: Mr. Joel Miller, Project Manager
daniabch.0120500
CHANGE OWNER
ARCHITECT
ORDER CONTRACTOR
El
AIA DOCUMENT G701 FIELD
OTHER ❑
0—
PROJECT: HANDICAP TOILET ROOMS CHANGE ORDER NUMBER: THREE
(name,address) CITY OF DANIA BEACH (3)
100 WEST DANIA BLVD., DANIA BEACH, FL DATE: AUGUST 4, 2000
TO CONTRACTOR: CORAL-TECH ASSOCIATES, INC. ARCHITECT'S PROJECT NO: N/A
(name, address) 10211 WEST SAMPLE ROAD CONTRACT DATE: MAY 25, 2000
SUITE 207
CORAL SPRINGS, FL 33065 CONTRACT FOR: GENERAL CONSTRUCTION
The Contract is changed as follows:
A. ADDITIONAL ELECTRICAL WORK AT FIRST FLOOR
B. CONSTRUCT ADDITIONAL CHASE WALL AT FIRST FLOOR
PER ATTACHED REQUEST FOR CHANGE ORDER NO: THREE(3). ADD $1,659.00
0
Not valid until signed by the Owner, Architect and Contractor.
The original (Contract Sum) was------------------------------------------------- $ 49,800.00
Net change by previously authorized Change Orders------------------------------ $ 1,440.00
The (Contract Sum) prior to this Change Order was-------------------------------- $ 51,240.00
The (Contract Sum) will be (increased) (daereesed4
Eby this Change Order in the amount of---------------------- $ 1,659.00
The new(Contract Sum) including this Change Order will be-------------------- $ 52,899.00
The Contract Time will be(increased)(deereRsed�Eumehanged)by FOUR(4) ( 4 )days.
The date of Substantial Completion as of the date of this Change Order therefore is TO BE DETERMINED
NOTE: This summary does not reflect changes in the Contract Sum,Contract Time or Guaranteed Maximum Price which have been authorized be
Construction Change Directive.
CORAL-TECH ASSOCIATES, INC. CITY OF DANIA BEACH, FLORIDA
ARCHITECT CONTRACTOR OWNER
10211 WEST SAMPLE ROAD 100 WEST DANIA BEACH BLVD.
Address Address Address
CORALS 065 DANIA B , LORIDA 33004
BY BY
DATE DATE DATE
AIA DOCUMENT G701 * CHANGE ORDER* 1997 EDITION*AIA- 1987*THE
AMERICAN INSTITUTE OF ARCHITECTS,1735 NEW YORK AVE.,N.W.,WASHINGTON,D.C.20006 G701-1987
DANIABCH.003
mm
August 4, 2000
Mr. Ken Koch
City of Dania Beach, Florida
100 West Dania Beach Boulevard
Dania Beach, Florida 33004
Re: Request for Change Order No: Three (3)
Handicap Toilet Rooms and Alterations
Broward County Sheriffs Offices
Dania Beach City Hall
CTA FILE NO: 0004-26
Dear Mr. Koch:
In accordance with directives received for modifications to the original scope of work for the
project, we are submitting our request for change order, as follows:
A. Additional Electrical Work at First Floor
Furnish and install conduit, wire, devices, fixtures and wall plates for additional
convenience outlets, surface mounted lighting fixture and wall switch, in locations as
directed.
Electrical material and fixture $321.00
Electrical labor 360.00
Total $681.00
o. CLnStr,..Ct Additiona': Chase Wall at First Floor
Furnish labor and material for new chase wall of metal framing and drywall at South side
of Men's and Women's restrooms.
Drywall chase wall 180 sf @ $ 3.00 $540.00
Project manager 2 hr @ $65.00 130.00
Total $670.00
10211 WEST SAMPLE ROAD
SUITE 207
CORAL SPRINGS,FLORIDA 33065
954-753-7252
FAX:954-341-7116
INS=
Mr. Ken Koch
Request for Change Order No: Three (3)
Handicap Toilet Rooms and Alterations
Broward County Sheriffs Offices
Dania Beach City Hall
CTA FILE NO: 0004-26
August 4, 2000
Page 2.
Summary
A. Additional Electrical Work at First Floor $ 681.00
B. Construct Additional Chase Wall at First Floor 670.00
Subtotal $1,351.00
Contractor's Overhead 135.10
Subtotal $1,486.10
Contractor's Fee 148.61
® Subtotal $1,634.71
Contractor's Bond 24.52
TOTAL $1,659.23
TOTAL AMOUNT OF THIS REQUEST $1,659.00
It appears that the stated modifications will impact construction progress for a period of four(4)
days. The actual impact on the scheduled completion date will be reviewed in conjunction with
affected construction activities of the project and an additional request will be submitted for an
extension of contract time.
As you know this work has been expedited to avoid prolonged delays to the project. We are
requesting that this change order be executed at your earliest opportunity.
Should you have any questions, please call at your convenience.
Very truly yours,
CO OC TES, INC.
K, CCE
President
® Enclosures
cc: Joel Miller, Project Manager
daniabchbso.0140600
CHANGE OWNER
ORDER ARCHITECT ❑
CONTRACTOR
AIA DOCUMENT G701 FIELD ❑
OTHER ❑
PROJECT: HANDICAP TOILET ROOMS CHANGE ORDER NUMBER: FOUR 4
(name, address) CITY OF DANIA BEACH ( )
100 WEST DANIA BLVD., DANIA BEACH, FL DATE: OCTOBER 20, 2000
TO CONTRACTOR: CORAL-TECH ASSOCIATES, INC. ARCHITECT'S PROJECT NO: N/A
(name, address) 10211 WEST SAMPLE ROAD
SUITE 207 CONTRACT DATE: MAY 25, 2000
CORAL SPRINGS, FL 33065 CONTRACT FOR: GENERAL CONSTRUCTION
The Contract is changed as follows:
ADDITIONAL GENERAL REQUIREMENTS FOR MULTI-PHASE
RENOVATIONS TO REST ROOMS PER REQUEST FOR CHANGE ORDER NO. FOUR(4) ADD $3,400.00
0
Not valid until signed by the Owner, Architect and Contractor.
The original (Contract Sum) was------------------------------------------------- $ 49,800.00
Net change by previously authorized Change Orders------------------------------ $ 3,099.00
The (Contract Sum) prior to this Change Order was-------------------------------- $ 52,899.00
The (Contract Sum)will be (increased) (�deereased.)
EHROka by this Change Order in the amount of---------------------- $ 3,400.00
The new(Contract Sum) including this Change Order will be----------=--- $ 56,299.00
The Contract Time will be(increased) (makaAgW�by TWENTY FOUR (24) ( 24 )days.
The date of Substantial Completion as of the date of this Change Order therefore is TO BE DETERMINED
NOTE: This summary does not reflect changes in the Contract Sum,Contract Time or Guaranteed Maximum Price which have been authorized be
Construction Change Directive.
Aflk CORAL-TECH ASSOCIATES, INC. CITY OF DANIA BEACH, FLORIDA
ARCHITECT CONTRACTOR OWNER
10211 WEST SAMPLE ROAD 100 WEST DANIA BEACH BLVD.
Address Address Address
CO I S, 065 DANIA B C , -ORIDA 33004
BY BY
DATE DATE DATE
AIA DOCUMENT G701 *CHANGE ORDER* 1997 EDITION*AIA- 1987*THE
AMERICAN INSTITUTE OF ARCHITECTS,1735 NEW YORK AVE.,N.W.,WASHINGTON,D.C.20006 G701-1987
DANIABCH.004
October 20, 2000
Mr. Ken Koch
City of Dania Beach, Florida
100 West Dania Beach Boulevard
Dania Beach, Florida 33004
Re: Request for Change Order No: Four (4)
Handicap Toilet Rooms and Alterations
Broward County Sheriffs Offices
Dania Beach City Hall
CTA FILE NO: 0004-26
Dear Mr. Koch:
In accordance with directives received from your office,to perform renovations to existing rest rooms
in multi-phase sequences which were not originally described in the contract documents, we are
submitting our request for change order, as follows:
Additional General Requirements for Multi-Phase Renovations to Rest Rooms
Construction Supervisor $1,044.00
Project Manager 1,150.00
Temporary Facilities 574.00
Subtotal $2,768.00
0 Contractor's Overhead 276.80
Subtotal $3,044.80
Contractor's Fee 304.48
Subtotal $3,349.28
Contractor's Bond 50.24
TOTAL $3,399.52
TOTAL AMOUNT OF THIS REQUEST $3,400.00
This request also includes an extension of contract time in the amount of twenty four (24) days,
based on the completion date of September 22, 2000. We are requesting that this change order be
executed at your earliest opportunity.
Should you have any questions, please call at your convenience.
Very trul urs,
CORA - C
n
JOHN OVI , CCE
Preside
Enclosures
cc: Joel Miller, Project Manager
10211 WEST SAMPLE ROAD
daniabchbso.0520800
SUITE 207
CORAL SPRINGS,FLORIDA 33065
954-753-7252
FAX:954-341-7116
® RESOLUTION NO. 2000-076
RESOLUTION OF THE CITY OF DANIA BEACH,
FLORIDA, ACCEPTING THE BID PROPOSAL
SUBMITTED BY CORAL-TECH ASSOCIATES, INC. AND
AUTHORIZING THE PROPER CITY OFFICIALS,
SUBJECT TO CERTAIN TERMS AND CONDITIONS, TO
EXECUTE AN AGREEMENT WITH CORAL-TECH
ASSOCIATES, INC. FOR LABOR AND MATERIALS
NECESSARY FOR RENOVATION AND HANDICAP
CONVERSION OF RESTROOMS IN BSO OFFICES AT
CITY HALL; PROVIDING FOR CONFLICTS; FURTHER,
PROVIDING FOR AN EFFECTIVE DATE.
BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA;
Section 1. That the Dania Beach City Commission accepts the bid proposal
submitted by Coral-Tech Associates, Inc. in the amount of $49,800.00, based upon
competitive bids, for renovation and handicap conversion of restrooms in BSO offices at
City Hall.
Section 2. That the certain agreement between the City of Dania Beach and
Coral-Tech Associates, Inc. for labor and materials necessary for renovation and
handicap conversion of restrooms in BSO offices at City Hall, in substantial form as
Exhibit "A", attached, is approved and the appropriate city officials are authorized to
execute it. The City Manager and City Attorney are authorized to make minor revisions
to such Agreement as are deemed necessary and proper for the best interests of the
City. Such Agreement and award of the bid shall not be deemed accepted by the City
unless and until the City has completed its execution of the Agreement.
Section 3. That all resolutions or parts of resolutions in conflict with this
resolution are repealed to the extent of such conflict.
Section 4. That this resolution shall be in force and take effect immediately upon
its passage and adoption.
RESOLUTION NO. 2000-076
PASSED AND ADOPTED THIS 23 d DAY OF MAY, 2000.
i
C.K. ELY
MAYOR — COMMISSIONER
ATTEST: ROLL CALL:
^ MAYOR McELYEA - YES
VICE-MAYOR BERTINO-YES
SHERYL CHAPMAN COMMISSIONER CALI -YES
ACTING CITY CLERK COMMISSIONER ETLING - YES
APPROVED AS TO FO M AND CORRECTNESS:
BY:
TH M . ANSBRO
CITY ATTORNEY
RESOLUTION NO. 2000-076
AGENDA REQUEST FORM
CITY OF DANIA BEACH
AGENDA ITEM Noo.47
1. DATE OF COMMISSION MEETING: NOVEMBER 14, 2000
2. DESCRIPTION OF AGENDA ITEM: CONSTRUCTION CHANGE ORDERS
3. COMMISSION ACTION BEING REQUESTED:
Adopt Resolution or Ordinance ❑ Expenditure Award Bid/RFP ❑
Presentation ❑ General approval of item ❑ Continued from meeting ❑
Other(please explain) ❑
4. SUMMARY EXPLANATION & BACKGROUND:
Approve additional funds to pay for change orders submitted by Coral-Tech and
Associates for extra work during BSO Restroom Remodel Project
5. ATTACHED EXHIBITS AND ADDITIONAL BACKUP MATERIALS (PLEASE LIST):
Memo from Koch to Smith; Change Orders#'s 1-4 from Coral Tech and Associates
6. FOR PURCHASING REQUESTS ONLY: Dept: City Hall I Amount: $1499.00
7. Fund: GENERAL: WATER: ❑ SEWER: ❑ STORMWATER: ❑
Account name: Account#:
Finance Director Approval: Date:
Submitted by:
Kenneth H. Koch, Building Official Date: October 27,2000
Growth Management Department
City Manager Date
I
Memorandum
sTo: Michael Smith, City Manager
s rom: Ken Koch, Building Official -
Date: 10/27/00
Re: Change Orders to BSO Restroom Remodel Contract
The work has been completed on this project by the contractor, Coral-Tech Associates. The
final invoice has been submitted, together with four change orders for additional work that
was encountered during the course of construction.These orders are:
1. Repairs to PVC Condenser Water Piping.
During initial demolition of an existing floor slab, the contractor broke a pipe
that carries cooling water for the a/c systems in both BSO and Growth
Management. This was an unforeseen condition, as no existing as-built plans
exist that would identify the location of the pipe, so no one could have been
aware of its existence in that location.
2. Demolish and Re-Construct Partition Between Men's and Women's Rooms
As construction proceeded in the early stages, it was discovered that one of the
walls that was initially intended to remain in place was in such poor condition
that it had to be removed and replaced.
3. Additional Electric Work and Additional Chase Wall
During the mid-point in construction, the sheriff asked for additional electric
receptacles and an additional ceiling light fixture to be installed. Also, in order to
accommodate the installation of the new plumbing fixtures without having to cut
into an existing block wall, a second framed "chase" wall was built on the face of
the existing block wall.
s In
October 27, 2000
4. Additional General Requirements for Multi-Phase
Since the four restrooms could not all be remodeled at one time (the 2 on the
first floor were done first with the second floor 2 being kept available for use),
an additional cost was necessary for the contractor to bring his sub-contractors
back in twice to perform the work in two phases. The contractor is allowed to
collect supervision, management, and overhead and profit on top of these costs.
I have reviewed all of the change orders for accuracy, and I agree the charges are
both warranted and fair.
The total additional change orders amount to $6499.00. In the original Purchase
Order, we encumbered $5000.00 on top of the bid amount of $49,800.00 to
cover potential change orders. An additional $1499.00 is necessary to pay the
contractor in total for work completed.
The contractor has performed according to the plans, specifications and contract
documents. We are satisfied with the quality of the work and the timeliness of
the project.
I recommend payment of the additional $1499.00, with funds to be drawn from
our contingency accounts.
2