HomeMy WebLinkAboutR-2007-045 Iicon Contractors WM Bid Award RESOLUTION NO. 2007-045
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA, RELATING TO THE AWARD OF AN AGREEMENT
USING STATE REVOLVING FUNDS; AUTHORIZING THE AWARD OF BID
TO IKON CONTRACTORS CORPORATION FOR CONSTRUCTION
ACTIVITIES ASSOCIATED WITH CONSTRUCTION OF THE WATER
MAIN LOOPING DANIA BEACH BOULEVARD WATER MAIN FOR THE
CITY WATER SYSTEM IN THE AMOUNT OF $553,238.05; AUTHORIZING
THE PROPER CITY OFFICIALS TO EXECUTE THE AGREEMENT;
DESIGNATING AUTHORIZED REPRESENTATIVES; PROVIDING FOR
CONFLICTS; FURTHER, PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the City Commission adopted Resolution 2002-120 approving the Water,
Wastewater and Stormwater Facilities Plan; and
WHEREAS, construction of the Water Main Looping Dania Beach Boulevard Water
Main project was among the projects identified in the Water, Wastewater and Stormwater
Facilities Plan; and
WHEREAS, on January 26, 2007 the City received bids for the construction of the Water
Main Looping Dania Beach Boulevard Water Main project; and
WHEREAS, there were four bidders for the project; and
WHEREAS, the bids were evaluated as follows:
licon Contractors Corporation $553,238.05*
MEF Construction, Inc. $649,750.00
Development& Communication Group of Florida, Inc. $842,320.00
Ranger Construction South $1,166,989.75; and
* Note there were two minor errors in addition in IICON's bid.
WHEREAS, the City bid selection team, including the project management consultant
recommend that the low bidder, Iicon Contractors Corporation, be selected to perform the work
and the bid be awarded to that company in the amount of$553,238.05;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF
THE CITY OF DANIA BEACH, FLORIDA:
Section 1. That the foregoing WHEREAS clauses are true and correct and are
incorporated by this reference.
Section 2. That the bid shall be awarded to the low bidder, Iicon Contractors
Corporation in the amount of$553,238.05 and the proper City officials are authorized to execute
the contract for the work; provided, however that no contract will become effective unless and
until City officials complete execution of it. Funding for the contract shall be derived from SRF
loan monies (loan amendment will be forthcoming to meet full funding needs).
Section 3. That the City Manager is designated as the authorized representative to
provide the assurances and commitments required by the loan application.
Section 4. That the City Manager is authorized to delegate responsibility to
appropriate City staff to carry out technical, financial, and administrative activities associated
with the loan agreement.
Section 5. That all resolutions or part of resolutions in conflict with any of the
provisions of this Resolution are repealed.
Section 6. That this Resolution shall become effective immediately upon its passage
and adoption.
PASSED AND ADOPTED on February 27, 2007.
PATRICIA FLURY
MAYOR—COMMISSIONER
2 RESOLUTION #2007-045
ATTEST:
LOUISE STILSON,CMC
CITY CLERK
APPROVED AS TO FORM D CORRECTNESS:
BY: r
THOMA J. A S
CITY ATTO EY
3 RESOLUTION 42007-045
AGREEMENT
THIS IS AN AGREEMENT, entered into on Int9,1f L' # 1Y , 2007
BETWEEN the Owner: City of Dania Beach
100 West Dania Beach Blvd.
Dania Beach, Florida 33004
and the Contractor: IICON Contractors Corporation
123 North Krome Avenue
Homestead, FL 33030
The Project is: Water Main Looping Project Phase I
(Name and location) Dania Beach Blvd., from U.S. 1 east to Gulfstream Road
Dania Beach, FL 33004
The Consultant is: Metric Engineering
(Name and address) 13940 SW 1361h Street, Suite 200
Miami, FL 33186
The Owner and Contractor agree as follows:
ARTICLE 1.0
THE CONTRACT DOCUMENTS
The Contract Documents consist of this Agreement, Conditions of the Contract (General,
Supplementary and other Conditions), Drawings, Specifications, addenda issued prior to
execution of this Agreement, other documents listed in this Agreement and Modifications
issued after execution of this Agreement; these form the Contract, and are as fully a part
of the Contract as if attached to this Agreement or repeated in it. The Contract represents
the entire and integrated agreement between the parties to it and supersedes prior
negotiations, representations or agreements, either written or oral. The Contract
Documents shall not be changed and are not subject to negotiation.
1
ARTICLE 2.0
THE WORK OF THIS CONTRACT
The Contractor shall execute the entire Work described in the Contract Documents except
to the extent specifically indicated in the Contract Documents to be the responsibility of
others, or as follows, if applicable:
ARTICLE 3.0
DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
3.1 The Date of Commencement is the date from which the Contract Time is
measured, and shall be the date set forth in the NOTICE TO PROCEED as issued by the
Owner. Should the Contractor incur costs prior to the issuance of the NOTICE TO
PROCEED, any such costs shall be incurred at the Contractor's risk, and the Owner shall
not reimburse the Contractor for any such costs under any circumstances.
Notwithstanding the foregoing, Owner may reimburse Contractor for actual costs
incurred relating to performance and payment bonds and insurance, with submittal of
invoices, in the event that Owner terminates this Contract for convenience, as provided in
the General Conditions. If Contractor fails to commence the Work within one (1) week
of the date set forth in the NOTICE TO PROCEED, Owner may terminate the Contract
immediately, without providing an opportunity to cure.
3.2 The Contractor shall achieve Substantial Completion not later than one hundred
fifty (150) calendar days, and Final Completion of the entire Work not later than one
hundred eighty (180) calendar days, each commencing with the date set forth in the
NOTICE TO PROCEED as issued by the Owner, subject to adjustments of this Contract
Time as provided in the Contract Documents.
The parties have agreed that since they are unable to ascertain the amount of damages
which would be suffered by OWNER as a result of CONTRACTOR's failure to timely
complete all Work required by the date set forth above, the amount of one tenth of one
percent (0.10%) of the contract value, inclusive of adjustments, per day, but not less than
Five Hundred Dollars ($500.00) per day, which amount has been agreed to by the parties,
is considered to be Owner's liquidated damages, and it is not a penalty. It shall be
assessed against the CONTRACTOR until substantial and final completion is achieved.
2
ARTICLE 4.0
CONTRACTSUM
4.1 The Owner shall pay the Contractor, for the Contractor's performance of the Work
the Contract Sum of Five Hundred Fifty Three Thousand Two Hundred and Thirty
Eight and Five Cents ($553,238.05), subject to additions and deductions as provided in
the Contract Documents.
4.2 The Contract Sum is based upon the cost agreed upon by the parties, for the
satisfactory performance of the Work in accordance with the Contract Documents.
4.3 The value of any Work covered by a Change Order or of any claim for an increase
or decrease in the Contract Sum shall be determined in one of the following ways at the
Owner's option:
(A) Where the Work involved is covered by unit prices contained in the
Contract Documents, by application of unit prices to the quantities of items
involved without additional fees.
(B) By mutual acceptance of a lump sum price.
ARTICLE 5.0
PROGRESS PAYMENTS
5.1 Based upon Applications for Payment submitted to the Consultant by the
Contractor and Certifications of Payment issued by the Consultant, the Owner shall make
progress payments on account of the Contract Sum to the Contractor as provided below,
elsewhere in the Contract Documents and in accordance with Part VII of Chapter 218,
Florida Statutes, as it may be amended from time to time, entitled the "Local Government
Prompt Payment Act."
5.2 The period covered by each Application for Payment shall be one calendar month
ending on the last day of the month, or as follows:
5.3 Each Application for Payment shall be based upon the Schedule of Values
submitted by the Contractor in accordance with the Contract Documents. The Schedule
of Values shall allocate the entire Contract Sum among the various portions of the Work
and be prepared in such form and supported by such data to substantiate its accuracy as
the Consultant may require. This Schedule, unless objected to by the Consultant, shall be
used as a basis for reviewing the Contractor's Applications for Payment.
5.4 Applications for Payment shall indicate the percentage of completion of each
portion of the Work as of the end of the period covered by the Application for Payment.
3
5.5 Subject to the provisions of the Contract Documents, the amount of each progress
payment shall be computed as follows:
(A) Take that portion of the Contract Sum properly allocable to completed Work
as determined by multiplying the percentage of completion of each portion of
the Work by the share of the total Contract Sum allocated to that portion of
the Work in the Schedule of Values, less retainage of ten percent (10%) until
50-percent completion and after 50-percent completion, reduce to five percent
(5%) the amount of retainage withheld from each subsequent progress
payment.
(B) Add that portion of the Contract Sum properly allocable to materials and
equipment delivered and installed, less the applicable retainage. No sums
shall be due for materials stored on or off site not yet installed.
(C) Subtract the aggregate of previous payments made by the Owner; and
(D) Subtract amounts, if any, which the Consultant has withheld or nullified.
5.6 Each Application for Payment after the first Application shall be accompanied by
a Certification of Payment form, provided by the Owner, from the Contractor and each
Supplier and Subcontractor, in amounts equal to those stated in the PRIOR Application
for the Contractor and each Subcontractor and each Subcontractor, Material/Labor
Supplier so due payment. The Application For Payment For Retainage shall be
accompanied by a final Certification of Payment and Release of Claim form from the
Contractor, each Supplier and Subcontractor in amounts equal to those stated in the
Schedule of Values.
ARTICLE 6.0
FINAL PAYMENT
Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made
by the Owner to the Contractor when (1) the Contract has been fully performed by the
Contractor except for the Contractor's responsibility to correct nonconforming Work, if
any, which obligation survives final payment and continues thereafter; and (2) a final
Certification of Payment has been issued by the Consultant; such final payment shall be
made by the Owner not more than 30 days after the issuance of the Consultant's final
Certification of Payment, (3) final Certification of Payment has been furnished from the
Contractor, Suppliers and Subcontractors; and (4) a Consent of Surety, if any, for final
payment.
4
ARTICLE 7.0
MISCELLANEOUS PROVISIONS
7.1 Where reference is made in this Agreement to a provision of the General
Conditions or other Contract Documents, the reference refers to that provision as
amended or supplemented by other provisions of the Contract Documents.
7.2 Other governmental entities may elect to purchase the goods and services
specified in this Agreement, which shall be made available upon the same terms and
conditions as those specified in this Agreement.
ARTICLE 8.0
TERMINATION OR SUSPENSION
8.1 The Contract may be terminated by the Owner or the Contractor as provided in
the General Conditions.
8.2 The Work may be suspended by the Owner as provided in the General Conditions.
ARTICLE 9.0
ENUMERATION OF CONTRACT DOCUMENTS
9.1 The Contract Documents, except for Modifications issued after execution of this
Agreement, are enumerated as follows:
9.1.1 The Agreement is this executed Agreement between Owner and Contractor.
9.1.2 The General Conditions are the General Conditions of the Contract for
Construction.
9.1.3 The Supplemental and other conditions of the Contract are those contained in the
Contract Documents dated November, 2006.
9.1.4 The Specifications are those contained in the Contract Documents listed in the
Table of Contents.
9.1.5 The Drawings are dated November, 2006, unless a different date is shown below:
Drawings are listed in 00004.
5
9.1.6 The Addendum, if any, is in Section 00900 and summarized below:
Number Date
WM-1 Key Sheet
WM-2 Location Map &Notes
WM-3 Tabulation of Quantities
WM-4 To WMA 1 12" Water Main Extension Plan and Profile
WM-12 12" Water Main Extension Standard Detail
9.1.7 The Certification of Payment forms and Project Closeout Forms are those
contained in the Contract Documents.
9.1.8 Other documents forming part of the Contract Documents are as follows:
00001 TITLE PAGE
00002 PROJECT DATA
00003 TABLE OF CONTENTS
00004 LIST OF DRAWINGS
00010 NOTICE TO BIDDERS
00020 NOTICE OF APPARENT LOW BIDDER
00100 INSTRUCTIONS TO BIDDERS
00110 NOTICE OF PRE-BID CONFERENCE
00200 SOIL INVESTIGATION REPORT— when applicable
00300 *BID FORM
00400 *INSURANCE AGENT STATEMENT
00410 *BID SECURITY FORM
00420 *CONTRACTOR'S SWORN QUALIFICATION STATEMENT
00430 *ACKNOWLEDGMENT OF INSPECTION
00440 *PUBLIC ENTITY CRIMES STATEMENT
00450 *NON-COLLUSION AFFIDAVIT
00460 *CONFORMANCE WITH FLORIDA TRENCH SAFETY ACT
00470 *INDEPENDENCE AFFIDAVIT
00500 AGREEMENT BETWEEN OWNER & CONTRACTOR
00510 ACKNOWLEDGMENT IF INDIVIDUAL
00520 ACKNOWLEDGMENT IF PARTNERSHIP
00530 ACKNOWLEDGMENT IF CORPORATION
00600 PERFORMANCE BOND
00610 PAYMENT BOND
00620 CERTIFICATE(S) OF INSURANCE
00630 CONFORMANCE WITH OSHA STANDARDS
00640 HAZCOM TRAINING/INFORMATION
00700 GENERAL CONDITIONS
00800 SUPPLEMENTAL CONDITIONS
00900 ADDENDUM
00910 WARRANTY BOND
6
00920 CERTIFICATION OF PAYMENT AND PAY ESTIMATE APPROVAL
FORM
00930 CERTIFICATION OF PAYMENT AND PARTIAL RELEASE OF
CLAIM
00940 CERTIFICATION OF PAYMENT AND FINAL RELEASE OF CLAIM
00950 CONSENT OF SURETY
00960 PROJECT CLOSEOUT
00970 CLOSEOUT PACKAGE CHECKLIST
NOTE:* Indicates sections (forms) requiring execution (signatures) to validate
the bid or proposal.
IN WITNESS OF THE FOREGOING, the parties have set their hands and seals effective
the day and year written above.
CITY :
CITY OF DANIA BEACH,
a Florida Municipal Corporation
ATTEST: l
6Lc�L[ 4/JU By:
Louise Stilson, City Clerk Patricia Flury, Mayor
IvaQ Pato, ity- anager
" /y , 200?
Approved For Form and Correctness Approved as to "Scope Of Services"
i
'1
,�
By: 11 6 By:
Thomas J. nsbr ; Ci y Attorney Dominic Orlando, P lic Services Director
1 'OT , 200 200-7
7
CONTRACTOR:
IICON CONTRACTORS CORPORATION
i
Signature
Print Name, Title
200_1
(CORPORATE SEAL, if applicable)
STATE OF Flo-ndCt )
ss:
COUNTY OF i( ligrnr D��
Sworn to and subscribed before me on Q3 t 2007 , by
who (che�V4 is personally
known to me or [ ] has produced as
identification.
No lic, State of
Yokairy Ylaana Tavarez
Print or Type Name of Notary Public
NOTARY FLBLICSTATE OF FLORIDA
My commission expires: Y•okairy Yleaoa Tavarez
Commissiao =DD383306
Expires; JAN. 03, 2009
Bonded Thru Adar_do Bond'ng Co.,Inc.
8