RESOLUTION NO. 33-98
A RESOLUTION OF THE CITY OF DANIA, FLORIDA,
APPROVING A CHANGE ORDER AS SUBMITTED BY
UNITED UNDERGROUND CONTRACTOR CORP.
RELATING TO THE NORTHWEST SIDEWALK &
LANDSCAPE IMPROVEMENTS PROGRAM, UNDER THE
BROWARD COUNTY COMMUNITY DEVELOPMENT
BLOCK GRANT PROGRAM, REDUCING THE ORIGINAL
CONTRACT PRICE FROM $189,980.00 TO $175,000.00;
AND PROVIDING FOR AN EFFECTIVE DATE.
BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF DANIA,
FLORIDA;
Section 1. That the Change Order submitted by United Underground Contractor
Corp. relating to the Northwest Sidewalk & Landscape Improvements Program, under
the Broward County Community Development Block Grant Program, reducing the
original contract price from $189,980.00 to $175,000.00; a copy of which is attached
hereto and made a part hereof as Exhibit"A", be and the same is hereby approved and
the appropriate city officials are hereby directed to execute same.
Section 2. That all resolutions or parts of resolutions in conflict herewith be and
the same are hereby repealed to the extent of such conflict.
Section 3. That this resolution shall be in force and take effect immediately upon
its passage and adoption.
PASSED AND ADOPTED THIS 10 DAY OF March 1998.
� I Cam..
MAYOR-COMMISSIONER
ATTEST: O '
CITY CLERK-AUDITOR
APPROVED� AS TO FORM AND CORRECTNESS:
CIYY NE
Resolution No. 33-98
I
CHANGE ORDER
No. 1
1 PROJECT: Northwest Sidewalk and Landscape Improvements
DATE OF ISSUANCE 3/2/98 EFFECTIVE DATE 3/2/98
OWNER: CITY OF DANIA, FLORIDA
OWNER CONTRACT NO.: 97-1724 ENGINEER CONTRACT NO: 97-1724
CONTRACTOR: United Underground ENGINEER: Calvin, Giordano & Associates, Inc.
Contractor Corp
You are directed to make the following changes in the Contract Documents
Description: Reduction of quantities of pavers, trees, and testing allowance
Reason for Change Order: Reduce construction cost to match CDBG
Attachments: Letter
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times
Substantial Completion: April 13, 1998
g 189,980.00 Ready for final payment:
aye or dates
Net changes from previous Change Orders No. NA to No. NA Net change from previous Change Orders No. NA to No. NA
J $ .0- aDys
Contract Price prior to this Change Order
Contract Times prior to this Change Order
Substantial Completion: April 13, 1998
ig 189,980.00 Ready for final payment: days or dates
Net decrease of this Change Order Net Increase (decrease) of this Change Order
g 14,980.00 ays
Contract Price with all approved Change Orders Contract Times with all approved Change Orders
Substantial Completion: April 13, 1998
g 175,000.00 Ready for final payment:
aye or OMS
By:�M NDED: AC 'P
is ar a tnc is a mit / ague ar u la, resident
Calvin, Giordano&Associates, Inc. City of Dania nited Underground Contractor Corp.
Date: 313I18 Date: Date: 3��afi
p07.1724\eng\cor,\ChgOrd\Chg-Ord.001 1 ��
s
Calvin, Giordano tr Associates, Inc.
Engineers Surveyors Planners
February 26, 1998
Kevin Dick, Assistant to the City Manager
CITY OF DANIA
100 West Dania Beach Boulevard
Dania, FL 33004
Re: NW Sidewalk & Landscape Improvements
CGA Project No, 97-1724 ;! ,,
Dear Mr. Dick:
Bids were opened on the above referenced project on September 11, 1997. The low
responsive bidder was United Underground Contractor Corp. with a bid of
$189,980.00. The Community Development Block Grant provided only $175,000.00
for construction. Therefore, $14,980 in construction items needed to be eliminated
from the work. This letter is written to address the changes required to achieve this
cost reduction.
Line Item 3 of the bid is for the installation of 7,600 square feet of Uni Eco-Stone
concrete pavers. The cost is $4.80 per square foot. 1,488 square feet of Uni Eco-Stone
will be eliminated (while an equal amount of sod is added) saving $6,280. The new
total will be 6,112 square feet of Uni Eco-Stone,
Line Item 7 of the bid is for the installation of 50 Live Oak trees. The cost is $285.00
per tree. 20 trees will be eliminated saving$5,700. The new total will be 30 Live Oak
to., trees.
r] 2 Oalm W B"wM .
SUM 120
Hollmt d,Florida 33020 Line Item 9 of the bid is a cash allowance for testing and laboratory services. The
(954)921.7781. .. allowance is $5,000.00. $3,000 will be cut from this item. The new•total will be
(9S4)921.8807 far $2,000 for testing and laboratory services.
O 6401 SAP.87th Anus
snug I I I These three reductions save $14,980. Therefore, the construction cost is reduced to
Miaml,Flodda 33173
(305)279.6210 $175,000.
!�(305)279.6323 fu
O 400 South Atu"fan Asnw .' .
Stdtc ass
Ww film Hach,Hodds 33401
(561)83S.0052
(561)835.0076 fu
P\97-1 724\eng\corr\eng\I rws0226
i
A
Kevin Dick, Assistant to the City Manager
February 26, 1998
Page 2
Should you have any questions, please do not hesitate to contact this office.
Sincerely, .
CALVIN, GIORDANO &ASSOCIATES, INC.
Richard W. Saltrick, P.E.
Project Manager
RWS/pal
c: Miguel A. Carbuccia, President,United Underground