HomeMy WebLinkAboutR-1999-033 r
i-
r,
7
j
r
RESOLUTION NO. 33-99
A RESOLUTION OF THE CITY OF DANIA BEACH,
FLORIDA, APPROVING CHANGE ORDER NO. 2 IN THE
AMOUNT OF $21,899.00 AS SUBMITTED BY COASTAL
CONTRACTING & DEVELOPMENT; INCREASING THE
CONTRACT PRICE FROM $635,845.00 TO $657,744.00
FOR RENOVATION OF FIRE STATION NO. 1; FURTHER,
PROVIDING FOR AN EFFECTIVE DATE.
BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA;
WHEREAS, the Dania Beach City Commission, on January 12, 1999, adopted
Resolution number 01-99 approving a Change Order submitted by Coastal Contracting
& Development reducing the original contract price of $637,250.00 to $635,845.00 for
renovations of Fire Station No. 1; and
WHEREAS, Coastal Contracting & Development has submitted a second
Change Order in the amount of$21,899.00 increasing the contract price of$635,845.00
to $657,744.00; and
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF DANIA BEACH, FLORIDA:
Section 1. That Change Order No. 2 as submitted by Coastal Contracting &
Development in the amount of$21,899.00 increasing the contract price from
$635,845.00 to $657,744.00 for renovation of Fire Station No. 1, in substantial form as
Exhibit"A", is approved and the appropriate city officials are hereby directed to execute
it.
Section 2. That all resolutions or parts of resolutions in conflict with this
resolution are repealed to the extent of such conflict.
1 RESOLUTION NO. 33-99
L
Y -
' r
7
Section 3. That this resolution shall be in force and take effect immediately upon
its passage and adoption.
PASSED AND ADOPTED THIS 23rd DAY OF F\EBRUAR��Y, 1999.
MAYOR—COMMISSIONER
ATTESTS /% ROLL CALL:
tl MAYOR CALI -YES
CITY CLERK' VICE-MAYOR ETLING -YES
COMMISSIONER BERTINO-YES
COMMISSIONER MIKES-YES
APPROVED AS TO FORM COMMISSIONER HYDE -YES
AND CORRECTNESS:
i
By: n
THOMA J. A BRO
CITY ATTORNEY
2 RESOLUTION NO. 33-99
t-
t
r
7
f
1
CHANGE, OWNER ❑
ORDER ARCHITECT ❑
CONTRACTOR ❑
A1A DOCUMENT G701 FIELD ❑
OTHER ❑
PROJECT: Dania Fire Station No. 1 CHANGE ORDER NUMBER: 2 (Two)
(name, address) 116 W. Dania Beach Blvd. DATE: February 18, 1999
Dania, FL
TO CONTRACTOR: ARCHITECT'S PROJECT NO: 971108
(name, address) Coastal Contracting & Development CONTRACT DATE: 10/9/98
807 N. Northlake Drive
Hollywood, FL 33019 CONTRACT FOR: Fire Station No. 1 Renovat:
The Contract is changed as follows:
1) Front Slab $ 6,703.00
2) Rear Slab 3,644.00
3) Rear of building (demo concrete, grade and sod) 879.00
4) New Sidewalk 975.00
5) Built-in desk in Lieutenant's Office 1,000.00
6) Built-in desk for Battalion Chief. 1,200.00
7) Move walls 300.00
8) "Knock down" to interior painted walls 2,500.00
9) Line striping on Bay floor 778.00
10) Add fence 10' 300.00
11) Cabinets in Kitchen above refrigerator 900.00
(cont'd. ..)
Not valid until signed by the Owner, Architect and Contractor.
The original(Contract Sum)(Guaranteed Maximum Price)was ... . . . . . . . . . . . . . . ... . . . .$637,250.00
Net change by previously authorized Change Orders . ... ... . . . . . . . . . . . . . . . . . .. . . ...1 (1,405.00)
The(Contract Sum)(Guaranteed Maximum Price)prior to this Change Order was. . . .. . ... .f 635,845.00
The(Centric(Sum)(Guaranteed Maximum Price)will be(increased)(draclx c")
(LNXXNW by this Change Order in the amount of. ...... . . .. . . .. . .. . . . . .. . . . .t 21,899.00
The new(Contract Sum)(Guaranteed Maximum Price)including this Change Order will be . .f 657,744.00
The Contract Time will bel(ra ua"(deasD=al)(unchanged)by ( 0 )days
The date of Substantial Completion as of the date or this Change Order therefore is
NOTE: This summary&l s not rellea changes in the Contract Sum,Contract Time ur Guaranteed Nimmum Price which have been auhurized he
Curolmctiun Change Directive.
MANUEL SYNALOVSKI ARCHITECTS COASTAL CONT a TTN & n VFf . C111 OF naaia
ARCHITECT CONTRACTOR Ow'NER
3109 Stirling Road #202 807 N. Northlake Dr. 100 W. Dania Reach Blvd
Address Address 1 Addreai
Ft. Lauderda1 , FL 33312 Holl od 0 . Dania. IT,
BY y
DATE. / / DATE 2/18/99 DATE
CAUTION: You should sign an original AIA document which has this caution printed In red
An original assures that changes will not be obscured as may occur when documents are reproduced
AIA DOCUMENT G701 • CHANGE ORDER • 198' EDIIION • AIA* • OO 19R7 THE ve e //
AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW' YORK AVE. NW, WASIIINGTON, D.C. 21XX,6 O.(Lj/y9 G701-1987
waRNINn llnllrrnvd nhotocnnvinp violates U.S.eoovrinht laws and Is sublect to legal omsecullon,
1- c
r
L
7--
7
l
DANIA FIRE STATION NO. 1
CHANGE ORDER NO. 2
February 18, 1999
12) Partition wall Walls caps 780.00
End caps 660.00
13) Electrical 845.00
14) Keyboard panels for exterior overhead doors 360.00
15) Electric striker for Entrance door. 75.00
TOTAL AMOUNT CHANCE ORDER NO. 2... ..$21,899.00
Refer to detailed breakdown.
L
.f
L
7
-r
CITY OF DANIA BEACH
FIRE DEPARTMENT
INTER-OFFICE MEMORANDUM
TO: Michael W. Smith, City Manager
FROM: Michael L. Brown, Deputy Fire Chief Qf:;�
RE: Change Order No. 2 relating to Station 1 renovations
DATE: February 18, 1999
Attached hereto is the above briefly described Change Order. The items described
therein are being requested for the purposes set forth below.
In an effort to work within budget constraints for the costs of renovations and additions
to Station 1, some site improvements were eliminated; however, as construction has
progressed, we have discovered that for safety and access reasons, these items cannot
be eliminated. For example: (1) the front and rear aprons (designated "front slab" and
"rear slab") are insufficient to hold the weight of our fire/rescue vehicles and must be
upgraded; and (2) a sidewalk must be installed to allow access form the parking lot,
otherwise no safe and secure access exists.
Other items on this change order relate to interior improvements which we feel are
necessary to refine the overall efficiency and effectiveness of the department's
operations and use of work areas.
This change order reflects what we feel are necessary improvements and adds only
slightly over 3% to the construction costs.
If you have any questions relating to the foregoing, please do not hesitate to contact
me.
MLB:cIb
attachment
L
r
r ,
r
r,
r
Y
t
7,J1 Coas�alCon�ractin andDeuelo 9 mend Inc p ,
P.O.Box 22-3976
Hollywood,Florida 33022-3976
954.920-7444
Fax 954.927.4480
February 18, 1999
Manuel Synalovski Architects
Attn: Mr. Chris Bray
3109 Stirling Road, Suite 202
Ft. Lauderdale,FL 33312
RE: DANIA FIRE STATION
Dear Chris,
Listed below are the required changes at the above referenced project:
1) FrOntSlab-
Demolition and Excavation $ 1,050.00
Saw cut Paving 100.00
Compaction and Grading 300.00
Finish 1150 S.F. 387.00
Concrete 4000 P.S.I. Pump Mix 26 c.y. @$80.00 2,080.00
Mesh 4x4x6x6 Double-Total 2,600 S.F. @$0.45 1,170.00
Chairs for Mesh 200.00
C.J. -95 L.F. @ $1.50 142.00
Pump 30000
Sub Total $ 5,729.00
Overhead/Profit/Bond 97400
Total (Unit Price$5.25 S.F.) $ 6,703.00
2) Rear Slab-
25 x 25 =625 @$5.83 S.F. 3,644.00
Same S.F. as Front Slab
s-
.f
r
7
7
Mr. Chris Bray
February 187 1999
Page 2 of 3
3) Demo Concrete at Rear of Building 7 x 43 451.00
Grade and Sod 300 S.F. 30000
Sub Total $ 751.00
Overhead/Protit>Bond 128 00
Total $ 879.00
4) New Sidewalk-Entrance to Parking Lot 5'x 65' 975.00
5) Built-in desk in Lieutenant's Office. 60"main desk with
36"wing.
1,000.00
6) Built-in desk for Battalion Chief. 72"main desk with 36"wing
for computer and key pad pull-out. 1,200.00
7) Move Lieutenant's office wall 11"; move Battalion Chief's
bedroom wall 12'; close off Batalion Chiefs office. 300.00
8) "Knock down"to all interior painted walls-Office& living quarters. 2,500.00
9) Line striping on Bay floor.
778.00
10) Add fence 10'
300.00
11) Cabinets in Kitchen above Refrigerator.
900.00
12) Partition wall -Mica rounded caps Walls caps P 780.00
End caps 660.00
13) Electrical -
Pipe from door switches to Zetron
Phone in Locker Room 60.00
Power outlet in Hallway 60.00
Gang Box(5)and button 4s for overhead doors in Dispatch Room 25.00
Phone outlet and power in B.C. Bunkroom S.E. wall. .00
Phone outlet in T.V. Room,N.E. wall;wall mount South wall 1 60.00
Chiefs office-Move power and computer. 60.00
6000
Total Electrical $ 845.00
t-
ft—
7
Mr. Chris Bray
February 18, 1999
Page 3 of 3
14) Keyboard panels for exterior overhead doors-2 only. Not included
in first Change Order. $180 each
$ 360.00
15) Electric striker for Entrance door. Also not included in first Change
Order.
75.00
Total Amount of Change Order..............$ 21,899.00
I have prepared Change Order No. 2 with all of the above changes.
Should you have any questions or require any additional information, please contact me.
Sincerely,
Co contracting&Development, Inc.
JC4
President
GJM/bt
Attachment
t_
f
L