Loading...
HomeMy WebLinkAboutR-2011-020 - Amendment to CDM Work Order #16 for the Public Serv. Administration Building RESOLUTION NO. 2011-020 A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DANIA BEACH, FLORIDA, AUTHORIZING AN AMENDMENT TO WORK ORDER NO. 16 IN AN AMOUNT NOT TO EXCEED $38,123.00 FOR ENGINEERING SERVICES TO BE PROVIDED BY THE FIRM OF CAMP DRESSER AND MCKEE (CDM) FOR THE PUBLIC SERVICES ADMINISTRATION BUILDING PROJECT; AUTHORIZING THE PROPER CITY OFFICIALS TO EXECUTE THE WORK ORDER; PROVIDING FOR CONFLICTS; FURTHER, PROVIDING FOR AN EFFECTIVE DATE. WHEREAS, the City Commission previously approved a capital improvement program that included monies for a new Public Services Administration Building; and WHEREAS, the City requested a work order from Camp, Dresser and McKee for engineering services associated with construction of the new Public Services Administration Building; and WHEREAS, the work order follows prior work orders for the Nanofiltration plant, a ground storage tank, project coordination, the Southwest Community Center and water main upgrade work on the same site; and WHEREAS, the City previously adopted Resolution #2008-212 authorizing Work Order #16 from Camp, Dresser and McKee for services associated with the construction of the Public Services Administration Building; and WHEREAS, previously adopted Resolution #2010-038 authorized Amendment #1 to Work Order No. 16 and it was presented to the City Commission on March 9, 2010 in the amount of$45,860.00 for additional out-of-scope services as noted below at the request of the City in order to keep the Contractor working and the project moving forward as follows: A. Design adjustments to accommodate the lime sludge handling operations. B. Unforeseen underground debris in the footprint of the building foundation. C. Foundation redesign due to debris. D. Responses to additional "request for information" from contractor due to debris and coordination with other projects on the site, SW Community Center and Nano Plant. E. Addressing two major change order claims from contractor, West Construction. F. FPL coordination; and WHEREAS, there is a need for another amendment to this work order which shall be Amendment#2 as follows: CDM has provided additional out-of-scope services as noted in Exhibit "A" (a copy is attached and incorporated into this Resolution by this reference) at the request of the City in order to keep the Contractor working and the project moving forward. The additional work addressed the following: g G. Additional design services, construction drawings and permit drawings to incorporate telephone, data and fire alarm service connections and to address dumpster elevation changes. H. Additional RFI responses to contractor requests for variances from the plans to specifications. I. Additional site visits to address deficient window and louver installations. J. Repetitive shop drawing reviews in excess of the two revision cycles included in the base of scope of services. K. Additional review and negotiations for contractor change proposals and added services to prepare no-cost change orders to incorporate revised City policies. L. Extended services include: consultation and advice, payment application processing, project management, quality assurance, and resident project representative (RPR) services from the projected April 2010 project substantial completion date, incorporating all code- compliance and design aesthetics issues, to the actual July 2010 project substantial completion date; NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF DANIA BEACH, FLORIDA,AS FOLLOWS: Section 1. That the foregoing WHEREAS clauses are incorporated by reference and made a part of this Resolution. Section 2. That the proper City officials are authorized to execute an Amendment to Work Order #16 to pay for additional engineering services in an amount not to exceed $38,123.00 using funds provided to the Capital Projects Fund Project PWFAC by a transfer from Water Fund Account#401-3301-533-31-30—Professional Engineering Services. 2 RESOLUTION#2011-020 Section 3. That all resolutions or parts of resolutions in conflict with this Resolution are repealed to such extent of such conflict. Section 4. That this Resolution shall become effective immediately upon its passage and adoption. PASSED AND ADOPTED on February 22, 2011. �,/z a, C.K. McELY09 ,5 OR-COMMISSIONER ATTEST: rci�y LOVISE STILSON, CMC CITY CLERK •�`• ar� '``�` APPROVED AS TO FORM AND CORRECTNESS: (,1 . \ JA TH A A B O CITY ATTORNEY i 3 RESOLUTION #2011-020 CDM 6365 N.W.6th Way,Suite 200 Fort Lauderdale,Florida 33309 tel:+l 954 776.1731 faxo 9s4928-1649 January 4,2011 Dominic F.Orlando,Director of Public Services City of Dania Beach 100 W.Dania Beach Blvd. Dania Beach,FL 33004 Subject: City of Dania Beach Public Services Administration Building City Bid No.08-009 CDM Project No.28037-68265 Additional and Extended Engineering Services During Construction Dear Mr.Orlando: Under Work Order No. 16,CDM has been providing Engineering Services during Construction for the Public Services Administration Building to the City since October 29, 2008.The City has previously approved Amendment No. 1 to Work Order No.16 for additional out-of-scope services that CDM provided through August 2009.The project is now nearing Final Completion,and CDM has provided additional out-of scope services subsequent to Amendment No. 1 both at the request of the City and as required for the extended project duration. We forward this letter to request a second amendment to our Work Order No.16, Engineering Services During Construction for the Public Services Administration Building,to provide means of payment in the amount of$38,123 for out-of-scope services that CDM has provided on this project from September 2009 through Final Completion. The out-of-scope items are described below and their associated costs are itemized in the attached summary: • Additional designservices,construction drawings and permit drawings to incorporate gs telephone,data and fire alarm service connections and to address dumpster elevation changes; • Additional RFI responses to contractor requests for variances from the plans and specifications; • Additional site visits to address deficient window and louver installations, ciu-28037-6=64)M consulting•engineering•construction.operations r 5 CDM Mr.Dominic Orlando,P.E. January 4,2011 Page 2 • Repetitive shop drawing reviews in excess of the two revision cycles included in the base scope of services. • Additional review and negotiations for contractor change proposals and added services to prepare no-cost change orders to incorporate revised City policies;and • Extended services including;consultation and advice,payment application processing, project management,quality assurance,and resident project representative(RPR) services;from the projected April 2010 project substantial completion date,incorporating all code-compliance and design aesthetics issues,to the actual July 2010 project substantial completion date. CDM asserts that the scope and value of this request for amendment is fair and reasonable, and we appreciate the City's prompt consideration.Please call me at(954)776-1731 if you have any questions in the meantime. Very truly yours, ;ent hon Z.Goldman Services Manager Camp Dresser&McKee Inc. End. (As noted) CC., File,Jon Goldman,CDM CM 2W311-0266"32 x Exhibit 404 Onell City of Dania Beach Engineering Services during Construction for Public Services Administration Building Work Order No. 16, Amendment No. 2 Scope of Work I. Background and General Description of Services In 2007,the City of Dania Beach authorized CDM for the design and permitting of a new Public Works and Public Services Administration Building. Work Order No.16 is for general engineering services during construction associated with the Public Services Administration Building previously designed under Work Order No.10. Original Scope In general,the services provided under the base scope of Work Order No.16 consisted of the following tasks: Task A General Services During Construction Task B Resident Project Representative Services Task C Special Services During Construction Amendment No.1 Amendment No.1 to Work Order No.16 addressed CDM's additional engineering services during construction by CDM through August 2009. Amendment No.2 This amendment,Amendment No.2,to Work Order No.16 is for CDM's additional and extended engineering services during construction arising from changes to the scope of work from September 2009 through project completion. The total cost for the additional and extended engineering services in Amendment No.2 is$38,123 as indicated in the attached cost breakdown. Amendment No.2 excludes the costs for additional and extended engineering services arising from Code-compliance changes to the work.CDM has prepared a time impact analysis of the effects of the code-compliance changes relative to the contractor's approved'As-Planned'schedule(copy attached),and determined that such changes caused the project Substantial Completion date to extend from January 11,2010 on the'As-Planned'schedule to April 8,2010 on the'Code- Compliance Changes' schedule(copy attached).Other contractor-initiated and Cm A-1 rdWWW i City-initiated changes caused Substantial Completion to extend to July 23,2010 as indicated in the'Contractor&Owner Initiated Changes'schedule(attached).As such,the extended services portion of Amendment No.2 only applies to a IS- week period,representing the extension from April 8 to July 23,2010. The original scope of work,and the changes addressed by Amendment Nos.1 and 2 are summarized as follows: II. Scope of Work Task A-General Services During Construction CDM provided Basic Engineering Services in accordance with this scope of work prior to and during the proposed contract construction period to Final Completion(FC). This scope of work was for services during construction based on the Contract Times for the original scope,Amendment No.1 and Amendment No.2,as discussed in Section III. Basic Engineering Services included the following: A.1 Execution of Contract Documents Original Scope: After issuance of a Notice of Award by the City, CDM assisted the City and prepared three(3)sets of Contract Documents for execution by the Contractor and the City. Amendment No.1: No change. Amendment No.2: $0-No change. A.2 Conformed Contract Documents Original Scope: CDM conformed the bid documents,and prepared four sets of signed and sealed drawings,two sets for submittal to the Building Department by the Contractor,and two sets for submittal to the City for record purposes. CDM also issued signed and sealed drawings to address Building Department permit revisions. Amendment No.1: CDM prepared and issued additional drawing revision sets for construction to incorporate unforeseen changes to lime sludge handling accommodations,FP&L service changes,and building foundation changes. Amendment No.2: $757-CDM prepared and issued additional drawing revision sets for construction to incorporate unforeseen changes for:1)Telephone,data and fire c A-2 POEGM MI alarm service connections(Originally to be performed in-house by the City);and 2)Dumpster elevation changes to match the SW Community Center contractor's installation. A.3 Prepare and Issue Notice to Proceed/Preconstruction Meeting Original Scope: CDM provided support to the City issuing the Notice to Proceed(NTP),and coordinated and conducted the Preconstruction Conference and distributed minutes to the attendees. Amendment No.1: No change. Amendment No.2: $0-No change. AA Substitution of Materials and Equipment Original Scope: CDM investigated and advised the City on the contractor's proposed concrete wall substitution. The contractor proposed a credit for the substitution that effectively reimbursed the City for CDM's substitution review costs. Amendment No.1: No change. Amendment No.2. $0-No change. A.5 Consult and Advise Original Scope: CDM provided technical advice and assistance to the City,and maintained a computerized document control system(CDCS) to facilitate the tracking of documents throughout the original construction period. Amendment No. 1: CDM provided additional geotechnical,structural engineering and QA/QC services to evaluate and provide a cost-effective resolution to unforeseen underground debris discovered during the course of construction. Amendment No.2. $2,027-CDM provided additional technical advice and assistance,and additional document control services through Final Completion. Added costs, however,are solely based on the extended period from April 8 to July 23,2010. r A-S rnestw,+raper A.6 Respond to Requests for Information(RFI) Original Scope: CDM received,logged,responded and distributed up to five(5) RFIs related to technical interpretation of the drawings and specifications and requested changes to the Work. Amendment No.1: CDM received,logged,responded and distributed an additional 15 RFI's through August 2009 relating to alternate equal products. Amendment No.2: $1,675-CDM received,logged,responded and distributed an additional eight(8)RFI's since August 2009 relating to contractor's requests for variance from the plans and specifications. A.7 Periodic Site Visits Original Scope: CDM provided periodic site visits at intervals appropriate to the various stages of construction to observe site conditions and the Work to determine whether the Work is in conformance to the Contract Documents. Amendment No.1: No change Amendment No.2: $1,295-CDM provided two additional site visits; The first to assess and prepare a report on the window and louver installations based on the manufacturer and product approval requirements, and the second to provide a follow up assessment of the contractor's measures to correct the window and louver installations.CDM assisted the City to negotiate an extended 5-year Contractor warranty for the window installations. A.8 Progress Meetings Original Scope: CDM conducted on-site project progress meetings and prepared and distributed meeting minutes and periodic reports of field working conditions. Amendment No.1: No change. Amendment No.2 -No change.With the cooperation of the City and $ppe ty the contractor,CDM scheduled and conducted progress meetings on an as-needed basis,rather than monthly,and maintained this item within the originally budgeted scope. CDM A-a . a , A.9 Review Shop Drawings Submittals Original Scope: CDM received and logged in up to two revisions of each shop drawing and distributed them to appropriate parties for review for conformance to the Contract Documents,and then distributed submittals to appropriate entities after review. Amendment No.1: No change. Amendment No.2: $2,910-CDM received,Iogged,reviewed and distributed a third revision for eight(8)shop drawings due to the contractor's repeated failure to meet the Contract Documents. A.10 Review Payment Requests and Schedules Original Scope: CDM reviewed monthly pay requests and progress schedule updates,and made recommendations to the City for payment to the Contractor throughout the original contract duration. Amendment No.1: No change Amendment No.2: $1,994-CDM reviewed additional monthly pay requests and progress schedule updates,and make recommendations to the City for payment to the Contractor through Final Completion. Added costs, however,are solely based on the extended period from April 8 to July 23,2010. A.11 Perform Milestone Site Visits Original Scope: CDM visited the site to determine if the project is ready for partial utilization,substantial completion, and final completion in accordance with the Contract Documents,and prepared punch lists of items remaining to be completed by the contractor. Amendment No.1: No change. Amendment No.2: $0-No change. A.12 Project and i Management 1 Quality g Original Scope: CDM provided administrative functions required to manage project elements including schedule and budget. Amendment No.1: No change. i WN i A-5 rna�seurar» Amendment No.2: $1,675-CDM provided additional administrative functions required to manage project elements including schedule and budget through Final Completion. Added costs,however,are solely based on the extended period from April 8 to July 23,2010, A.13 Project Update Meetings Original Scope: CDM's project manager prepared and held internal monthly status meetings with key project staff members throughout the original duration of the project. Amendment No.1: No change. Amendment No.2: $1,940-CDM's project manager prepared and conducted additional internal monthly status meetings with key project staff members through Final Completion.Added costs,however,are solely based on the extended period from April 8 to July 23,2010. A.14 Quality Assurance(QA)/Technical Review Original Scope: CDM maintained a program of QA on this project, including periodic review of records and documentation. Amendment No.1: No change. Amendment No.2: $1,510-CDM continued to maintain an extended program of QA on this project,including periodic review of records and documentation through Final Completion.Added costs,however,are solely based on the extended period from April 8 to July 23,2010. A.15 Preparation of Status Reports Original Scope: CDM's project manager prepared written progress reports summarizing activities completed,work remaining,and identifying any problems which are ongoing or may be anticipated. Amendment No.1: No change. Amendment No.2: $0- No change.Similar to Item No. A.8,CDM's project manager prepared the written reports on an as-needed basis according to the progress and problems encountered in the work,keeping this item within the originally budgeted scope. II A-6 II� awns Task B-Resident Project Representative Services Original Scope: CDM provided part time Resident Project Representative(RPR)services to observe work of the Contractor for conformance to the Contract Documents on an average of twelve(12)hours per week for the original construction period of 450 days. Amendment No.1: CDM provided RPR services in excess of 12 hours per week to monitor the proper implementation of CDM's evaluation and resolution procedures for unforeseen underground debris. Amendment No.2: $10,670-CDM provided extended part time RPR services;by John Chandler,Jeffrey Manning and John Carr;to observe work of the Contractor for conformance to the Contract Documents through Substantial Completion.Preparation of punch lists and verification of punch list work is part of the original scope of services,and,therefore,not included in this amendment.Added costs are solely based on the extended period from April 8 to July 23,2010. Task C-Supplementary Services During Construction C.1 BuiIding Permit Process Assistance Original Scope: CDM provided technical and administrative assistance to the Contractor in obtaining a City of Dania Beach Building Permit,including signing and sealing of documents for submittal to the Building Department,responding to questions and requests for information issued by the Building Department during the review process,and attendance at the final review meeting. Amendment No.1: CDM prepared and issued additional signed and sealed drawing revisions to incorporate unforeseen design changes and to facilitate permit modifications and inspections due to lime sludge handling accommodations,FP&L service changes, and building foundation changes. m A-7 low,A, Amendment No.2: $1,920-CDM prepared and issued additional signed and sealed drawing revisions to incorporate unforeseen design changes and to facilitate permit modifications and inspections for:1)Telephone, data and fire alarm service connections(Originally to be performed in-house by the City);2)Dumpster elevation changes to match the SW Community Center contractor's installation,3)Differing electrical requirements between those used to base the design for the HVAC and air compressor equipment,and those selected by the Contractor; and 4) Incorporating the final Fuel Station connection to the Administration Building electrical system. C.2 Change Orders Original Scope: CDM negotiated five change proposals with the contractor on behalf of the City and prepared allowance account payment authorizations to reflect adjustments to the construction contract allowance accounts when warranted due to unforeseen conditions,and will prepare one final reconciliation change order at Final Completion of the project. Amendment No.1: CDM negotiated two additional change proposals for unforeseen conditions,foundation changes and additional excavations,and prepared allowance account payment authorizations to reflect adjustments to the construction allowance accounts. Amendment No.2: $9,750-CDM negotiated six additional change proposals for unforeseen conditions;fuel station power,lubrication system changes,hauling unsuitable soils,added communications and data ductbank,commercial range hood changes,and added pavement work;and prepare and process ten no-cost change orders to reflect all the adjustments to the construction allowance accounts,in order to comply with the City's revised contract change policies.The additional work in Amendment No.1 and Amendment No.2 specifically excludes all costs associated with change proposals for code- compliance issues,design conflicts,and aesthetic improvements,as well as costs for the final CM0►�B Pf1t&"li reconciliation change order which is part of the original scope of services.Over the course of the project, the contractor submitted 38 proposals totaling$341,225 for additions,deletions and changed conditions,which CDM negotiated to $207,813,saving the City$133,412. C.3 Record Drawings/FinaI Certification/Regulatory Agency Documentation Original Scope: CDM coordinated the receipt and review of the Contractor's information showing those significant changes made during the construction process,and will prepare for the City a set of reproducible record drawings(black line),an AutoCAD copy on CD- ROM,and two(2)blackline print sets showing those changes made during the construction process, based on information furnished by the Contractor. CDM prepared final certifications of completion of construction to appropriate regulatory agencies, along with record drawings as appropriate. Amendment No.1: No change. Amendment No.2 $0-No change. CA Project Closeout and Final Submittal Original Scope: CDM reviewed the Contractor's certified survey of the Work,and will organize and participate in final project reconciliation meetings with the City or the Contractor and jointly where required and prepare the closeout documents and coordinate the closeout of the project. Amendment No.1: No change. Amendment No.2: $0-No change. END OF EXHIBIT"ONE" cm A.4 P"IMMI M � A A F+ AD a a5� 85� St � M F s h N N N N e g 8 h w y yp Ifl�f � a�P. 5 H o® S�M � O M O O O 0 0 0 . O O O O O O O a g 0 O N � pp pp o p o p p p p o M M Vf 8 M Y! H p M N N N np M oo pp pp pp pO pp QQ pp Q� r n 0 0 0 0 0 0 0 0 ^ O O o 0 0 0 O 0 0 0 O O 0. N yq pp oo pp pp yN� po N m ua2f M W O � O N O O •O M O O Yf 0 0 d' T d� O N � W O O pp p N �Q$ jQ� �Qj O o L a N a 4 M F O O O O . N O O N . O h T . r o cc r d a a a n m o ,pa, g O m5y ply d a m L tli � � a � � c � � � .•`g � �� 3 E � g �' $ � 8 .a Rio 'o� 4 1 I � E ! , I ........... 1 - . _- __ f , ► . Cb 32 �i I . fi _a__ a .__. _ - -- ---- ; a 8 tea' to 'P77 °49 :29P xjq `x Visit a '4 '4 S '4 '4 °P '4 '? " 0? '4R�� 4W � � Y � '9ND7 '4q � '4 ^ � '4 � 'P � T 0 0 0 0 O 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0'O 0 0 0 0 O D TIC O O O O p 01.10 0 0 0 0 1 0 D O D O n n f M _� s � III 1 t As { Ir f � w R I " " m r _ � � U a p " a U i � 0 3 i " 11111 U o'o e o o OI'cl0(O 111 oo�o 11 it! Ill CIO O O O OO OOf O, O CO _ �._..y.... 0000 0 0 0 OHO O Oi0 7 0 0 0 0 0 0 0 OHO 0 0 0 OO 0 0 O�O,O O 1 b y O YiA IV 1V . �.� H N n ♦� b r » N N O tIV�O b 0 O ^ A n,n OC O. N N O N O N N O,O ( i