HomeMy WebLinkAboutR-2013-008 Authorized Additional Services from Calvin, Geordano & Associates, Inc. for Expansion of Southeast Stormwater Improvement Phase I Project not to exceed $96,420.00 RESOLUTION NO. 2013-008
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA, AUTHORIZING THE CITY MANAGER TO PURCHASE
ADDITIONAL ENGINEERING SERVICES FROM CALVIN, GIORDANO
AND ASSOCIATES, INC. RELATING TO EXPANSION OF THE
SOUTHEAST STORMWATER IMPROVEMENT PHASE I PROJECT FOR
REDESIGN AND CONSTRUCTION OVERSIGHT IN AN AMOUNT NOT TO
EXCEED NINETY-SIX THOUSAND FOUR HUNDRED AND TWENTY
DOLLARS ($96,420.00); PROVIDING FOR CONFLICTS; FURTHER,
PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the City Commission has directed the Public Services Director to seek
alternative solutions for the Southeast stormwater issues and to immediately identify a solution
for improvements to certain areas; and
WHEREAS,the Director determined that there is an immediate need to proceed with the
expansion of the Southeast Stormwater Phase I Project, which involves the replacement of the
Meadowbrook Main Stormwater Drainage Pump Station and Discharge Piping for this area of
the City; and
WHEREAS, the City had received notice of approval from the Florida State Revolving
Fund (SRF) for the Southeast area stormwater improvement loan for which the Public Services
Director had previously obtained approval to incur costs and to seek construction bids for this
Project; however, the costs of Project engineering design are not eligible for SRF funding and
therefore must be appropriated from the City's Stormwater Fund, accumulated Net Asset
balance; and
WHEREAS, the City has previously engaged and issued a P.O. to Calvin Giordano and
Associates, Inc. for the initial Southeast Storm Water Drainage Improvement Project engineering
design and services for a total amount of$126,151.00; and
WHEREAS, the Pubic Services Director recommends the purchase of additional
services for the Southeast Stormwater Drainage Improvement Project for engineering redesign
and services in an amount of $96,420.00, necessary to address requests made by the
Meadowbrook Condominium Associations, which are required to obtain easements for
construction and maintenance of the new pump station and also for the project engineering
oversight of Phase I during construction, by Calvin Giordano and Associates, Inc.;
NOW,THEREFORE,BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF DANIA BEACH,FLORIDA:
Section 1. That that certain agreement with Calvin Giordano and Associates in an
amount not to exceed Ninety-Six Thousand Four Hundred Twenty Dollars ($96,420.00) for
additional services for the Southeast Stormwater Drainage Improvement Project Phase I for
engineering re-design and for the project Phase I engineering oversight during construction for
the Southeast Stormwater Phase 1 Project is approved. Calvin, Giordano & Associates, Inc.'s
Proposal No. 09-2777.7 is attached as Exhibit "A"; and it is made a part of and is incorporated
into this Resolution by this reference.
Section 2. That the City Manager and City Attorney are authorized to make minor
revisions to the agreement for such services which are deemed necessary and in the best interests
of the City of Dania Beach.
Section 3. That costs of all Southeast Storm Water consulting engineering work shall
be charged to the Storm Water Fund, Southeast Storm Water Phase I Project — Consultant
Engineering Account No. 403-3804-538.31-30-63-10, and providing further that these costs shall
be funded by transfer of$222,571.00 from the City's available Storm Water Fund, Accumulated
Net Assets using revenue/resources Account No. 403-0000-389-90-02.
Section 4. That all resolutions or parts of resolutions in conflict with this Resolution
are repealed to the extent of such conflict.
Section 5. That this Resolution shall be in full force and take effect immediately
upon its passage and adoption.
PASSED AND ADOPTED on January 8,2013.
ATTEST:
LOUISE STILSON, CMC WALTER B. DUKE, III
CITY CLERK MAYOR
APPROVED A TO F RM AND CORRECTNESS: O�o�P�`S F1�ro�ry
TH014AS YANSAk6
CITY ATTORNEY ,
2 RESOLUTION#2013-008
Calvin, Giordano & Associates, Inc.
E X C E P T 1 0 N A L S 0 L U T 1 0 N S
Additional Services Agreement
DATE: December 6,2012
RE: SE Drainage Improvements-Phase 1 Building Redesign
CLIENT: City of Dania Beach
100 W.Dania Beach Boulevard
Dania Beach,FL 33004
ATTENTION: Mr.Robert Baldwin
CGA NO.: 09-2777.7
CGA HAS BEEN ADVISED TO PROCEED WITH THE FOLLOWING ADDITIONAL
SERVICES:
Due to the clients request for work outside the original scope of services,Calvin,
Giordano&Associates,Inc.will provide the following additional services:
Modifications are proposed to the design of the Meadowbrook pump station to
accommodate requests by the Meadowbrook Condominium Home Owners Association
(HOA). The pump,motor type and power source were requested to be changed to
Building Code Services submersible electric pumps thus changing the overall layout of the station and site. Noise
Coda Enforcement Construction Engineering& and visual appearance are a significant factor in modifications to the design. This proposal
Inspection includes the additional services required to modify the station as noted above and to revise
Construction Services the plans and specifications for the new design. Additionally,modifications to the
Contract Government contract documents and plans shall include an expanded contract scope to provide for the
Data Technologies& new pump selection and configuration as well as the additional items listed below.
Development
Emergency Management I. Professional Engineering Services
Services
Engineering
Governmental Services A. Electrical Engineering
Indoor Air Quality
Landscape Architecture&
Environmental Services 1. Due to revisions requested by the HOA,provide electrical
Municipal Engineering engineering design services to revise the electrical and
Planning instrumentation systems for Meadowbrook Pumping Station
Public Administration for a submersible pumping system including provisions for a
Redevelopment&Urban Design portable standby power system.
Surveying&Mapping
Traffic Engine Planning& 2. provide electrical engineering services during construction
Tragic Engineering
Utility&Community including response to R.Fls,shop drawing review,periodic
Maintenance Services observation,final inspection and production of record
drawings.
1800 Eller Drive,Suite 600
Fort Lauderdale, FL 33316
Phone:954.921.7781
Fax:954.921.8807
www.calvin-giordano.com
Fort Lauderdale West Palm Beach Port St.Lucie Homestead Clearwater Jacksonville Atlanta
December 6,2012
PW2of4
B. Civil Engineering
1. Design revisions due to revising the pumps to submersible electric
pumps and motors.
• Revise site plan and layout based on new pumping
configuration.
• Revise site grading for revised slab/decking Iayout and
elevation.
• CADD drawings of new layout of the station.
• Revise pump station calculations
• Revise contract drawings including station sections,details,and
general notes
2. Review and revise specifications as necessary to accommodate new
pump and electrical requirements.
3. Architectural aestheticstbuilding size reduction provided by Manuel
Synalovski Associates LLC when working on previous design with
building and sound attenuation.
4. Structural engineering design revisions to accommodate changes to
the sheet pile wall, foundation, intake structure and deck for
supporting pumps and motors.
5. Attend design review meetings with City at 30%, 60%,90'/0,and/or
HOA based on 90%and 100%submittals. Address comments as
required/directed.
6. Additional design items requested by the City:
• Regrade Meadowbrook driveway at SE 3rd Street entrance.
• Regrade Meadowbrook driveway at SE 3rd Avenue entrance.
II _-
December 6,2012
Pale 8 of 4
• Plans and analysis for intersection of SE 3rd St and SE 5th Ave
to provide ADA compliant crosswalk with brick paver detail.
• Include a plan sheet for replacement of degraded CMP pipe
connecting to the Meadowbrook Lake with the pump station;
locations as directed by the City.
• Prepare a planting plan and specifications for SE 3rd Avenue to
include in contract for bidding.
7. Re-permitting of the modified station design.
PROPOSED SCHEDULE OF FEES
I Professional Engineering Services
A Professional Electrical Engineering Services $10,960.00
B Professional Civil Engineering Services $85,460.00
Preliminary Engineering $6,940.00
Final Engineering $35, 120.00
Other Engineering Work Activity
Costs to date for meetings,investigation and $24,000.00
prelim plan changes from Meadowbrook condo
association
Miscellaneous Design Survey $3,000.00
Prepare planting plan and specifications for SE $3,500.00
3`d Avenue
Update specifications to include modified or new $2,220.00
design elements
Sub-Consultant
Architect Consultant $1,380.00
Geotech Consultant $2,800.00
Structural Engineering Consultant $6,500.00
H Meetings not included in I thru I Hourly
TOTAL its H"*Srnr a)
December 6.2012
Page 4 of 4
AUTHORIZATION
Kindly sign and return this authorization at your earliest convenience.
Calvin,Giordano&Associates,Inc.
will proceed upon receipt of authorization..
By. By: .j-i®,l Li �!c-
Mr. Robert Baldwin Shelley Eichner, AICP
City Manager Senior Vice President
Date: Date:
By:
Mr. Dominic F.Orlando,P.E.
Public Works Director
As to"scope of services"
Date:
Calvin, Giordano & Associates, Inc.
E X C E P T I O N A L S O L U T I O N S
a
PROFESSIONAL FEE SCHEDULE
Principal 215.00 LANDSCAPE ARCHITECT
Contract Administrator 190.00 Associate,Landscape Architect 165.00
Project Administrator 165.00 Senior Landscape Architect 130.00
Executive Assistant/Clerical 75.00 Environmental Administrator 125.00
Landscape Architect 115.00
ENGINEERING Environmental Specialist 105.00
Associate,Engineering(VI) 190.00 Landscape CADD Technician 95.00
Director,Engineering(V) 165.00 Environmental Assistant 85,00
Project Manager(IV) 145.00 Landscape Inspector/Arborist 105.00
Project Engineer(I If) 125.00 Landscape Designer 115.00
Engineer(11) 105.00 Landscape Site Plan Reviewer 130.00
Jr.Engineer(1) 100.00
Engineer Technician 105.00 SURVEYING
Senior CADD Tech Manager 115.00 Associate,Surveying 165.00
CADD Technician 95.00 Senior Registered Surveyor 145.00
Traffic Engineer(11) 125.00 Survey Crew 135.00
Traffic Engineer(I) 100.00 Registered Surveyor 130.00
Traffic Technician 90.00 Survey Coordinator 105.00
Permit Administrator 90.00 CADD Technician 95.00
3D Laser Scanner 355.00
DATA TECH DEVELOPMENT Hydrographic Survey Crew 330.00
Associate,Data Tech Dev. 165.00 G.P.S.Survey Crew 155.00
GIS Coordinator 145.00 Sub-meter G.P.S 75.00
GIS Specialist 125.00 Soft Dig(per hole) 480.00
Multi-Media 3D Developer 115.00 Utility Locates(per hour) 205.00
GIS Technician 100.00
Building Code Services Sr.Applications Developer 1650) INDOOR AIR QUALITY SERVICES
Code Enforcement Applications Developer 135.00 Sr.Environmental Scientist 115.00
Construction Engineering& Network Administrator 155.00 Environmental Scientist 100.00
Inspection System Support Specialist 115.00
Construction Services IT Support Specialist 85.00 CONSTRUCTION
Contract Government Associate,Construction 165.00
Data Technologies& GOVERNMENTAL SERVICES Construction Management Director 135.00
Development Associate,VP 190.00 Construction Manager 125.00
Emergency Management Director of Code Enforcement 145.00 Senior Inspector 100.00
Services Director of Building Code 145.00 inspector 90.00
Engineering Project Manager 145.00 Construction Coordinator 90.00
Grants Administrator 125.00
Governmental services Code Enforcement Field Supervisor 110.00 EMERGENCY MANAGEMENT
Indoor Air quality Code Enforcement Field Inspector 90.00 Director 145.00
Landscape Architecture& Building Official 115.00 Planner 105.00
Environmental Services Building Plans Reviewer 90.00 Assistant Planner 90.00
Municipal Engineering Building Inspector 90.00
Planning Permit Processor 75.00 PLANNING
Public Administration Associate,Planning 175.00
Redevelopment&Urban REDEVELOPNOM&URBANDESM Director of Planning 145.00
Design Revitalization Project Director/Manager 165.00 Planning Administrator 135.00
Surveying&Mapping Revitalization Coordinator 130.00 Assistant Director 125.00
Alternative Funding/Technician 100.00 Senior Planner 125.00
Transportation Planning& Commercial Zoning Administrator 130.00 Assistant Planner 90.00
Traffic Engineering Redevelopment Planner 105.00
Utility&Community Spccialist/Downtown Manager 100.00 EXPERT WITNESS
Maintenance Services Municipal Administrator 165.(X) Principal/Associate 330.00
Municipal Assistant Administrator 130.00 Registered Engineer/Surveyor 280.00
1800 Eller Drive,Suite 600 Municipal Department/Division[lead 105.00 Pmject Engineer 230.00
Fort Lauderdale,FL 33316 Phone:954.921.7781 In addition to the hourly rates listed above,charges will include direct out-of-pocket expenses
Fax:9 54.921.8807 such as reproduction,overnight mail,and other reinrbursables billed at a stultiplier of L25.