HomeMy WebLinkAboutR-2013-093 Authorized $156,789.99 Available in Marina Construction Project Account to fund Change Order for cost increases with Shoreline Foundation, Inc. & Approved Change Order No. 1 with Shoreline RESOLUTION NO. 2013-093
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA, AUTHORIZING THE PROPER CITY OFFICIALS TO
UTILIZE AN AMOUNT OF ONE HUNDRED FIFTY SIX THOUSAND
SEVEN HUNDRED EIGHTY NINE DOLLARS AND NINETY NINE CENTS
($156,789.99) AVAILABLE IN THE MARINA CONSTRUCTION PROJECT
ACCOUNT TO FUND A CHANGE ORDER FOR CONSTRUCTION
AGREEMENT COST INCREASES WITH SHORELINE FOUNDATION, INC.
AND FURTHER AGREEING TO AND APPROVING ACCEPTANCE OF
CHANGE ORDER NO. 1 WITH SHORELINE FOUNDATION, INC.;
PROVIDING FOR CONFLICTS; PROVIDING FOR FUNDING; FURTHER,
PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the City approved a project appropriation in a total amount of
$7,500,000.00 for the Marina Improvement-Phase II Construction Project that was assembled
through a combination of City General Fund cash advances, County Broward Boating
Improvement Program (`BBIP") grant awards, and Florida Inland Navigation District ("FIND")
grant awards; and
WHEREAS, a construction bid award and Agreement were approved in an amount of
$6,186,787.00 with Shoreline Foundation, Inc., for the Marina Construction-Phase II Project, and
a separate project oversight appropriation for Consulting Engineer oversight was provided in the
amount of $544,810.00 with Craven Thompson & Associates, Inc., resulting in a remaining
available project appropriation of$768,403.00; and
WHEREAS,through August 16, 2013, the Administration has expended a total amount of
$160,510.73 to separately pay for Project construction insurance, Project permits, and other
Project consulting costs, using available funding appropriations and resulting in a current
available appropriation balance of$607,892.27; and
WHEREAS, at various stages of the Project, several unforeseen site conditions and permit
related changes have been encountered that have resulted in eleven change order requests to the
City from the Project construction contractor, Shoreline Foundation, Inc.; and
WHEREAS, these change orders have been reviewed by the City's Project Consulting
Engineer at Craven Thompson & Associates, Inc., as well as the Public Services Director and
City Engineer; and
WHEREAS, two additional change order items are currently anticipated or are in the
process of being submitted to the City from Shoreline Foundation, Inc., for the completion of
the Marina Construction-Phase II Project; and
WHEREAS, upon the review and recommendation of the Project Engineer at Craven
Thompson and Associates, Inc., as well as the Public Service Director and City Engineer, the
Administration recommends City Commission approval for the use of available Marina
Construction Project appropriation funding to add a total not to exceed amount of$156,789.99 to
the original Shoreline Foundation, Inc. Marina Construction-Phase II Project Agreement, and
J �'
further to approve the related Change Order No. 1 in an amount not to exceed $156,789.99;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF DANIA BEACH,FLORIDA:
Section 1. That the foregoing "Whereas" clauses are true and correct and they are
incorporated into this Resolution by this reference.
Section 2. That the Marina Construction Project Change Order No. 1 summary, a
copy of which is attached as Exhibit "A", is made a part of and is incorporated into this
Resolution by reference.
Section 3. That the City Manager and City Attorney are authorized to make minor
revisions to such Change Order No. 1 as are deemed necessary and proper for the best interests
of the City.
Section 4. That funding is currently available from within the Marina Construction-
Phase II Project's available additional appropriations to pay for Change Order No. 1 in an
amount not to exceed $156,789.99 to Shoreline Foundation, Inc. for its completion of the
Project.
Section 5. That all resolutions or parts of resolutions in conflict with this Resolution
are repealed to the extent of such conflict.
2 RESOLUTION#2013-093
Section 6. That this Resolution shall be in force and take effect immediately upon its
passage and adoption.
PASSED AND ADOPTED on September 10, 2013.
ATTEST:
LOUISE STILSON, CMC WALTER B. DUKE, III
CITY CLERK MAYOR
APPROVED AS TO FO D ORRECTNESS: o P�5 FARsr Gry
THOMAS J. SBR
CITY ATTORNEY
1�
3 RESOLUTION#2013-093
Exhibit A
City of Dania Beach
Municipal Marina Project
Summary of Change Order Requests
CHANGE ORDER NO.1
1. CHANGE ORDER REQUEST 1
Date Submitted: 3/19/13
Purpose: Install sewer pump-out signage
Status: Rejected, as it was deemed unnecessary since payment for the signs will come from the
Project Signage Allowance pay Item.
Amount: $0.00
2. CHANGE ORDER REQUEST 2
Date Submitted: 3/22/13 (revised 6/7/13)
Purpose: Construct expansion joints in seawall cap.
Justification: Expansion joints in the seawall cap were not originally included in the bid set of
plans since concrete mortar and pavers will be installed on top. After further review with
Shoreline,the Structural Engineers and the City, it was determined that expansion joints would
be added to reduce cracking and possible movement of the pavers being installed on top of the
wall.
Status: Scope of work approved
Amount: Will be negotiated not to exceed $3,344.23
3. CHANGE ORDER REQUEST 3
Date Submitted: 4/2/13
Purpose: Upgrading the wood mooring piles.
Status: Rejected, as being unnecessary.
Amount: $0.00
4. CHANGE ORDER REQUEST 4
Date Submitted: 4/30/13 (revised 5/21/13)
Purpose: Revision of the feeder wire from the FPL Transformer to the main electrical panel
(Panel"DPA").
Justification: During Building Department permit review,the permitting agency questioned the
sizing of feeder wires. The Project Electrical Engineer determined that the feeder wire,while
NOT technically undersized would not be capable of any power additions. To ensure future
upgradability of the Marina and to satisfy the Building Department's concerns,the feeder wire
was upsized.
Status: Scope of work approved.
Amount: Will be negotiated not to exceed$3,805.62
5. CHANGE ORDER REQUESTS
Date Submitted: 5/28/13 (revised 6/12/13)
Purpose: Relocate A/C Condensers and install on raised stands, upsize circuits for dock lighting
transformers and additional grounding& lightning protection on Kiosks&Pavilions.
4 RESOLUTION#2013-093
Justification: City Building Permit review comments on the electrical design caused increases in
ground circuits, lightning protection and transformer sizes and City request to revise the fence&
sidewalk layout caused a change in the design for location and mounting methods for the A/C
condensers at the Dock Master Building.
Status: Review Pending
Amount: Will be negotiated not to exceed $43,067.74
6. CHANGE ORDER REQUEST 6
Date Submitted: 8/13/13
Purpose: Wall and door changes due to Fire Department review and comments.
Justification: City Fire Department requirements during permit review.
Status: Scope of work approved
Amount: Will be negotiated not to exceed$5,877.12
7. CHANGE ORDER REQUEST 7
Date Submitted: 6/5/13
Purpose: Building Permit fee cost
Justification: Amount of fees exceeded 2%of the total contract amount.
Status: Change Order was negotiated between SFI and the City and the City's Public Services
Department paid $53,677.72.
Amount: $0.00
8. CHANGE ORDER REQUEST 8
Date Submitted: 6/13/13 (revised 8/5/13)
Purpose: Fence,sidewalk,and landscape changes.
Justification: City requested changes to fence alignment and sidewalk widths.
Status: Scope of work approved
Amount: Will be negotiated not to exceed $12,159.02
9. CHANGE ORDER REQUEST 9
Date Submitted: 8/5/13
Purpose: Kiosk and pavilion finish changes made via ASI#1 Directive.
Status: Scope of work approved
Amount: Will be negotiated not to exceed $18,820.76
10. CHANGE ORDER REQUEST 10
Date Submitted: 7/11/13
Purpose: Changes to electrical panels due to adding circuits for the old Dock Master Building and
the Sanitary Lift Station.
Justification: Insufficient information existed during design to determine power source and
loads to original Dock Master Building. Construction excavation and demolition activities
allowed the Electrical Engineers to make a final determination of power requirements.
Status: Scope of work approved
Amount: Will be negotiated not to exceed $34,717.50
11. CHANGE ORDER REQUEST 11
Date Submitted: 7/1/13
Purpose: Additional permit fees for the metal roof truss shop drawing review.
5 RESOLUTION#2013-093
Status: Rejected
Amount:$0.00
12. CHANGE ORDER REQUEST 12
Date Submitted: Pending
Purpose: Additional jetting/blowing of excess materials for the gangways and Docks E and F
Justification: Environmental permitting restraints required for protection of seagrass during
dredging prevented the Contractor from excavating the entire footprint of the new docks.
Jetting the excess remaining materials will prevent the docks from hitting ground during
extreme low tides.This tide event actually occurred during July and August
Status: Review pending
Amount: Will be negotiated not to exceed$10,000.00
13. ALLOWANCE-$25,000.00 Not—to—Exceed
Project allowance to address unanticipated field conditions, required items to closeout Project,
additional permits and permit modifications.All costs will be negotiated at actual cost total not
to exceed$25,000.00
City of Dania Beach
Municipal Marina Project
Cost Summary
Change Order Max. Amount
1 $ -
2 $ 3,344.23
3 $ -
4 $ 3,802.62
5 $ 43,067.74
6 $ 5,887.12
7 $ -
8 $ 12,159.02
9 $ 18,820.76
10 $ 34,717.50
11 $ -
12 $ 10,000.00
$ 25,000.00
Allowance (NTE)
$ 156,798.99
Total TE
6 RESOLUTION#2013-093