HomeMy WebLinkAboutR-2015-070 - Executed credit change order No. 3 for $135,369.92 to closeout the marina construction agreement with Shoreline Foundation, Inc. RESOLUTION NO. 2015-070
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA, AUTHORIZING THE PROPER CITY OFFICIALS TO
APPROVE AND EXECUTE CREDIT CHANGE ORDER NO. 3 IN THE
AMOUNT OF ONE HUNDRED THIRTY-FIVE THOUSAND THREE
HUNDRED SIXTY NINE DOLLARS AND NINETY TWO CENTS
($135,369.92), TO CLOSEOUT THE MARINA CONSTRUCTION
AGREEMENT WITH SHORELINE FOUNDATION, INC.; PROVIDING FOR
CONFLICTS; FURTHER, PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the City approved a project appropriation in a total amount of
$7,500,000.00 for the Marina Improvement-Phase II Construction Project that was assembled
through a combination of City General Fund cash advances, County Broward Boating
Improvement Program (`BBIP") grant awards, and Florida Inland Navigation District ("FIND")
grant awards; and
WHEREAS, a construction bid award and an execution of an Agreement were approved
in an amount of $6,186,787.00 with Shoreline Foundation, Inc., for the Marina Construction-
Phase II Project, and a separate project oversight appropriation for a consulting engineering
oversight was provided in the amount of$544,810.00 with Craven Thompson& Associates, Inc.,
resulting in a remaining available Project appropriation of$768,403.00; and
WHEREAS, through August 16, 2013, the Administration has expended a total amount
of$160,510.73 to separately pay for Project construction insurance, Project permits, and other
Project consulting costs, using available funding appropriations, which resulted in a current
available appropriation balance of$607,892.27; and
WHEREAS, on September 10, 2013, the City Commission approved Resolution No.
2013-093 pertaining to Change Order No. 1, which consisted of change order requests 1-13 in a
total amount of$156,789.99; and
WHEREAS, on May 13, 2014, the City Commission approved Resolution No. 2014-037
pertaining to Change Order No. 2, which consisted of change order requests 14-34 in a total
amount of$87,337.13; and
WHEREAS, at various stages of the Project, several unforeseen site conditions and
related changes have been encountered that have resulted in forty-five (45) change order requests
to the City received from the Project construction contractor, Shoreline Foundation, Inc.; and
WHEREAS,these change orders have been reviewed by the City's Project Consulting
Engineer at Craven Thompson & Associates, Inc., as well as the City Public Services
Department Director and City Engineer; and
WHEREAS, upon the review and recommendation of the Project Consulting Engineer at
Craven Thompson & Associates, Inc., as well as the Public Services Department Director and
City Engineer, the Administration recommends City Commission approval to close out the
Marina Construction Project, and to approve Credit Change Order No. 3 in the amount of
($135,369.92), thereby adjusting the original Shoreline Foundation, Inc. Marina Construction-
Phase II Project Agreement to $6,295,544.20;
NOW,THEREFORE,BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF DANIA BEACH,FLORIDA:
Section 1. That the foregoing "Whereas" clauses are true and correct, and they are
made a part of and incorporated into this Resolution by this reference.
Section 2. That the Marina Construction Project Credit Change Order No. 3
summary, a copy of which is attached as Exhibit "A" is made a part of and is incorporated into
this Resolution by reference, is approved.
Section 3. That the City Manager and City Attorney are authorized to make minor
revisions to such Credit Change Order No. 3, as are deemed necessary and proper for the best
interests of the City.
Section 4. That funding was previously approved for the Marina Construction-Phase
II Project in the amount of $6,430,914.12 and the revised contract amount of $6,295,544.20,
which resulted in a total credit amount of($135,369.92) to process Credit Change Order No. 3,
to close out this Project with Shoreline Foundation, Inc., bringing the total approved
construction change order amount over the original bid award to $108,757.20.
Section 5. That all resolutions or parts of resolutions in conflict with this Resolution
are repealed to the extent of such conflict.
Section 6. That this Resolution shall be in force and take effect immediately upon its
passage and adoption.
2 RESOLUTION#2015-070
PASSED AND ADOPTED on July 28, 2015.
ATTEST: oy�A�t°Fs FIRST err
LOUISE STILSON, CMC O A. SALVINO, SR.
CITY CLERK YOR
APPROVED AS TO FO AND CORRECTNESS:
THOMAS J. SBRO
CITY ATTORNEY
3 RESOLUTION#2015-070
Exhibit A
City of Dania Beach
Municipal Marina Project
Summary of Change Order Requests
CHANGE ORDER NO. 3
The purpose of change order 3 is to zero out the contract amount in order to close out the above
mentioned project accounting for additional costs/credits since the most recently approved City CO 2
for the project
CONTRACT ADJUSTMENT SUMMARY
i
• Previously Approved Contract Amount n$c3nor�9,923Tc $6,430,914.12
44ncluding City Approved CO 1&2 Amounts)
• Previously Approved Changer Order Amount For Reference
Approved 156,789.99Negotiated
City CO 1(includes$25,000 Allowance) $ «�99 $126,494.08
City CO 2(includes$25,000 Allowance) $87,337.13 $79,429.13
I
Total Previously City approved $244,13642 $205,923.21
$244,127.12
• (Deduct)Negotiated reduction from approved CO's t'8�r $ 38,203 .91
• (Deduct)Allowance Amounts Remaining
a
Signage Allowance Remaining $10,062.22
FPL Allowance Remaining $17,103.79
Security Features Allowance Remaining $50,000.00
Furniture Allowance Remaining $20,000.00
I
Total of unused protect allowances(deduct) S97.166.01
9Peuiousl' A toved '� �£€ ,a $135, 369.92
CO3 Final Contract Amount Based Upon Final Proposed Adjustments $6,295,544.20
9
0
2
SUMMARY EXHIBIT OF CURRENT REQUEST FOR CHANGE ORDER LIST AND HOW PAYMENT APPLIED
35. CHANGE ORDER
Date Submitted: 04/17/14
Purpose: Install needed mooring pile at south leg of T shape portion of dock V.
Justification: Install needed mooring pile at south leg of T shape portion of dock V.
Amount: Negotiated not to exceed$1,848.24
Status: Scope approved to be paid $1,848.24 from$25,000.00 allowance from City Approved
change order 2.
Amount: 0
36. CHANGE ORDER
Date Submitted: 05/12/14
Purpose: Sewer Pump Out Relocation
Justification: Relocate sewer pump out for enhanced service performance
Amount:
Status: Rejected to be reviewed by Marina and City separately to determine if wanted.
Amount: 0
37. CHANGE ORDER
Date Submitted: 04/17/14
Purpose: Asphalt paving improvement upgrade
Justification: Additional pavement enhancement near marina for aesthetics
Amount: $1,848.00
Status: Rejected to be done as part of future project
Amount: 0
38. CHANGE ORDER
Date Submitted: 5/05/14
Purpose: Adjust cabinetry per building department for ADA requirements
Justification: Adjust cabinetry per building department for ADA requirements
Amount: Negotiated not to exceed$4,650.61
Status: Scope of work approved to be paid $4,650.61 from$25,000.00 allowance from City
approved change order 2.
Amount: 0
39. CHANGE ORDER
Date Submitted: 05/24/14
Purpose: Adjust mechanical duct work for make up air due to commercial dryer use
Justification: Design was for residential dryer and need is for commercial dryer additional costs
are not valid.
Status: Scope of work approved to be paid 1,662.36 from$25,000.00 allowance from City
approved change order 2
Amount: 0
40. CHANGE ORDER
Date Submitted: 05/27/2014(RFI#117) f
Purpose: Install bike pad due to existing asphalt unacceptable for pad use
Justification: Contractor removed existing asphalt unworkable for pad
Status: Rejected work unnecessary due to CO 41 modifications i
Amount: 0
41. CHANGE ORDER
Date Submitted: 06/17/2014(RFI#118)
Purpose: Adjust front walk area at north side of building and install
Justification: Plans revised to add additional walk path to allow benches to remain on level
route.
Status: Scope of work approved to be paid $4,992.38 from $25,000.00 allowance from City
approved change order 2
Amount: 0
42. CHANGE ORDER
Date Submitted: N/A
Purpose: Construct additional pump line for pump out system due to concerns with pump out
system.
Justification: Testing has confirmed constructed pump system operates.
Amount: 0
43. CHANGE ORDER
Date Submitted: 06/27/14
Purpose: Add breakers for time clock and dryer
Justification: Add breakers for time clock and dryer
Status: Scope of work approved to be paid $397.08 from $25,000.00 allowance from City
approved change order 2
Amount: 0
44. CHANGE ORDER
Date Submitted: 1/16/25
Purpose:Adjust pavers, concrete,and pavement at north kiosk to achieve ADA slope
requirements along route
Justification: Survey elevations of existing grade in field were different than shown on original
survey
Status: Rejected to be performed as part of separate project that includes parking lot redesign in
nearby area. ADA space may potentially be relocated as part of future project. I
Amount: 0
45. CHANGE ORDER
Date Submitted: 1/16/25
Purpose: Increase due to math error in change order 21
Justification: OH&P were left out of CO21 initially by error
Status:Scope of Work Approved to be paid from$25,000.00 allowance from remainder of City
approved change order 1
Amount: $1,543.14
The sub total of the currently requested change orders above is$15,093.81
Additionally we would like to close out the following allowance amounts remaining
Signage Allowance Remaining $10,062.22
FPL Allowance Remaining $17 103.79
Security Features Allowance Remaining $50,000.00
Furniture Allowance Remaining $20,000.00
City CO1 Allowance Remainder $901.94
City CO2 Allowance Remainder $6,722.55
Total Release of unused project Allowances $104,790.50
Total of all negotiated change orders from project beginning to end
Previously approved/negotiated Change Orders and Amounts
CO2 $2,695.71 CO1
CO4 $2,793.65 CO1
CO5 $23,892.52 CO1
CO6 $5,877.12 CO1
CO9 $18,820.76 CO1
CO10 $34,717.50 CO1
CO12 $10,000.00 CO1
CO8R1 $3,598.76 CO1
CO14111 $3,169.89 Paid by CO1 Allowance
CO15 $5,778.38 Paid by C01 Allowance
CO16R1 $1,391.22 Paid by CO1 Allowance
CO20 $1,696.32 Paid by CO1 Allowance
CO 19 Was previously approved in CO2 and negotiated to remove afterwards
CO21111 $22,661.16 CO2
CO22R1 $5,032.63 Paid by COI Allowance
CO25R1 $10,506.38 CO2
CO27R1 $12,668.44 CO2
CO30 $5,486.48 Paid by CO1 Allowance
CO32 $4,726.78 Paid by CO2 Allowance(to install electrical
outlets at kiosk including additional electrical run associated)
CO34 $15,315.70 CO2
i
i
Current Change Orders Amounts negotiated
CO35 $1,848.24 To be paid by CO2 Allowance
CO38 $4,650.61 To be paid by CO2 Allowance
CO39 $1,662.36 To be paid by CO2 Allowance
CO41 $4,992.38 To be paid by CO2 Allowance
CO43 $397.08 To be paid by CO2 Allowance
CO45 $1,543.14 To be paid by CO1 allowance
Total of all negotiated change orders listed above for project start to finish is$205,923.21
After all change orders have been added and all allowances of all kinds used to pay against change
orders the following is the net change to the contract amount for the project from the original
s
amount is as follows.
3
f
s
h
f]I
8