HomeMy WebLinkAboutR-2017-067 Approves Change Order Number Four (4) in the Amount of $13,282,50 to be Paid to MBR Construction, Inc. for the Dania Beach Ocean Park Revitilization Phase 1 Construction Project RESOLUTION NO. 2017-067
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA, AUTHORIZING THE PROPER CITY OFFICIALS TO
APPROVE CHANGE ORDER NUMBER FOUR (4) IN THE AMOUNT OF
THIRTEEN THOUSAND TWO HUNDRED EIGHTY TWO DOLLARS AND
FIFTY CENTS ($13,282.50) TO BE PAID TO MBR CONSTRUCTION, INC. IN
CONNECTION WITH THE DANIA BEACH OCEAN PARK
REVITALIZATION PHASE I CONSTRUCTION PROJECT; PROVIDING FOR
CONFLICTS; FURTHER, PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the Dania Beach Ocean Park Revitalization Project- Phase I was approved
for the construction and design of beach improvements; and
WHEREAS, the City Commission awarded a bid to MBR Construction, Inc. for One
Million Four Hundred Fifty Nine Thousand Eight Hundred Thirty Five Dollars ($1,459,835.00)
on November 10, 2015,pursuant to Resolution 2015-137; and
WHEREAS, the City Commission approved Change Order Number One (1) in the
amount of Sixty Six Thousand One Hundred Seven Dollars and Fifty Cents ($66,107.50) on June
28, 2016,pursuant to Resolution No. 2016-087; and
WHEREAS, on February 28, 2017, Change Orders Number Two (2) and Three (3) were
approved by the City Manager in the total amount of Twenty Four Thousand Seven Hundred
Twenty Four Dollars and Seventy Five Cents ($24,724.75) for additional work related to a beach
pump system and beach crossovers; and
WHEREAS, due to the beach erosion on the south side of the beach area, Change Order
Number Four (4) in the amount of Thirteen Thousand Two Hundred Eighty Two Dollars and
Fifty Cents ($13,282.50) is requested to be paid to MBR Construction, Inc., to include the cost of
installing one (1) bollard at the Quarterdeck Restaurant, stair extensions, steps and ipe wooden
gates for Crossovers Number Four (4) and Five (5), a copy of which change order is attached as
Exhibit "A", (and it is made a part of and is incorporated into this Resolution by this reference),
bringing the total contract amount to be paid to MBR Construction, Inc. to One Million Five
Hundred Sixty Three Thousand Nine Hundred Forty Nine Dollars and Seventy Five Cents
($1,563,949.75); and
WHEREAS, Change Order Number Four (4) requires approval by the City Commission,
as net change orders allowed by the City Manager are limited to $25,000.00 and funding
approval is required;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF
THE CITY OF DANIA BEACH, FLORIDA:
Section 1. That the foregoing "Whereas" clauses are ratified and confirmed as being
true and correct, and they are made a specific part of and incorporated into this Resolution by
this reference.
Section 2. That that the City Commission approves Change Order Number Four (4)
applicable to the Dania Beach Park Revitalization Phase I Project with payment to be made to
MBR Construction Inc., in the amount of Thirteen Thousand Two Hundred Eighty Two Dollars
and Fifty Cents ($13,282.50), and the City Manager and City Officials are authorized to execute
it.
Section 3. That funding appropriations for this project are available through the
Capital Projects fund Beach Revitalization Project Phase I Account Number 301-72-59-572-62-
10.
Section 4. That all resolutions or part of Resolutions in conflict with any of the
provisions of this Resolution are repealed to the extent of such conflict.
Section 5. That this Resolution shall become effective immediately upon its passage
and adoption.
PASSED AND ADOPTED on June 27, 2017.
ATTEST: RRo's Fi�T����
ArLo--A-t-Qw,
LOUISE STILSON, CMC 1 AMARA JA
CITY CLERK YOR
�a
1
APPROVED AS TO RM A CORRE
ft�
THOMAS J. A BRO
CITY ATTO Y
2 RESOLUTION#2017-067
i
i
■o nAR-
1020i NW 515E Street
Fort Lauderdale, FL 33309
PH (954)486-8404/FAX(954)486-9579
i
i
CITY OF DANIA BEACH PO#: 2016-00000197
100 W. Dania Beach Blvd. Project: Dania Beach Ocean Park Revitalization-Phase I
Dania Beach, FL 33004 100 N. Beach Road,Dania Beach, FL 33004
i
I
CHANGE ORDER No.4 I
This change order proposal request(COPR)is submitted requesting a change order to the contract.
Detailed basis/scope for CO#4:
I
r
2.Add one(1) Bollard at Quarterdeck: $ 500.00
3.Stair extension at crossover#4: add 3 additional steps to include IPE Stain $ 1,500.00
i
4.Stair extension at crossover#5: add 3 additional steps to include IPE Stain $ 1,500.00
5.2 IPE gates as requested by City at the end of beach side landing $ 8,000.00
at stair crossover#4. (Shop Drawing Incl.for Approval)
Subtotal: $ 11,500.00
10%OH: $1,150.00
5%Profit: $632.50
i
TOTAL CO#4: $13,282.50
Owner R truction- Inc.
Date Date
I
I