HomeMy WebLinkAboutR-2019-045 City Authorizing to Execute a First Amendment to the Agreement for a Capacity Allocation in Phase 1 of the C51 Reservoir Project; Providing for Conflicts RESOLUTION NO. 2019-045
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA, AUTHORIZING THE PROPER CITY OFFICIALS TO
EXECUTE A FIRST AMENDMENT TO THE AGREEMENT FOR A
CAPACITY ALLOCATION IN PHASE 1 OF THE C51 RESERVOIR
PROJECT; PROVIDING FOR CONFLICTS; FURTHER, PROVIDING FOR AN
EFFECTIVE DATE.
BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA:
Section 1. That City officials approved an Agreement for Capacity Allocation in
Phase 1 of the C-51 Reservoir at the June 26, 2018, City Commission Meeting by a unanimous
vote and it was executed by City officials.
Section 2. That the proper City officials are authorized to execute a First Amendment
Agreement for Capacity Allocation in Phase 1 of the Reservoir Agreement with Palm Beach
Aggregates, LLC, which Amendment is attached as Exhibit"A".
Section 3. That the City Manager and City Attorney are authorized to make minor
revisions to the First Amendment to Agreement Capacity Allocation in Phase 1 C-51 Reservoir
Agreement that are deemed necessary and proper for the best interest of the City.
Section 4. That all resolutions or parts of resolutions in conflict with this Resolution
are repealed to the extent of such conflict.
Section 5. That this resolution shall be in full force and take effect immediately upon
its passage and adoption.
PASSED AND ADOPTED on May 28, 2019.
ATTEST:
Pz/,-M
THOMAS SCHNEIDER, CMC LEW LLEN
CITY CLERK d► MAYOR
�qe[/SHE01�
APPROVED AS TO, O D CORRE TNESS:
THOMAS J. A7RO
CITY ATTOV
FIRST AMENDMENT TO
AGREEMENT FOR CAPACITY ALLOCATION
IN PHASE 1 OF THE C-51 RESERVOIR
CITY OF DANIA BEACH
This is a First Amendment ("First Amendment") to the Agreement for Capacity
Allocation in Phase 1 of the C-51 Reservoir (the "Agreement"), made and entered into by and
between Palm Beach Aggregates, LLC ("Company"), a Florida limited liability company, with
its principal offices at 20125 State Road 80, P.O. Box 700, Loxahatchee, Florida 33470, and the
City of Dania Beach, Florida ("Participant"), a municipality organized and existing under the
laws of the State of Florida, the address of which is 100 W. Dania Beach Blvd, Dania Beach, FL
33004. It is effective as of the date this First Amendment is fully executed by the Parties (the
"Effective Date"). Company and Participant shall collectively be called the "Parties" and each is
individually identified from time to time as a"Party."
Recitals
A. The Parties entered into the Agreement on July 31, 2018 to provide for surface
water storage capacity in the proposed collaborative development project known as the C-51
Reservoir, as further described in the Agreement ("C-51 Reservoir"), which is intended to be
constructed in two phases.
B. The Agreement provides for an allocation to Participant of one (1) million gallons
per day of storage in Phase 1 of the C-51 Reservoir, as further described in the Agreement("Phase
1 Reservoir").
C. Despite the best efforts of the Parties, it has taken longer than anticipated to
satisfy certain conditions precedent set forth in the Agreement, and the Parties desire to amend
the Agreement to extend the relevant time periods under it and to continue working together
towards completion of the Phase 1 Reservoir project.
NOW, THEREFORE, for good and valuable consideration, the receipt and sufficiency of
which are acknowledged and agreed upon,the Parties agree as follows:
1. The foregoing recitals are true and correct, and they are incorporated by this
reference.
2. Unless otherwise stated, for paragraphs 3 —4 below, words in stfuek thr-.ug type
are deletions from existing text and words in underline type (aside from previously included
headings) are additions to existing text.
3. Section 3.2 of the Agreement is amended, in part,as follows:
3.2 Termination. Upon delivery of written notice to Company, as defined by
Article 15 below, Participant may terminate this Agreement:
3.2.1 If Company fails to notify Participant, on or before Atne 30,
241-8 November 30, 2019, that it has sufficient permits,
commitments, and financing to commence the construction of the
Phase 1 Reservoir; or
4. Section 11.1 of the Agreement is amended, in part, as follows:
11.1 All of Company's obligations under this Agreement are expressly made
subject to all of the following conditions,which Company agrees to use its
reasonable efforts to promptly pursue and satisfy, time being of the
essence:
11.1.2 Company's securing full Construction Financing for the Phase 1
Reservoir within ninety iom days after- the Minimum Reserved
Gaparaity Dae on or before November 30, 2019, with a closing
date within ninety (90) days thereafter (the "Phase 1 Construction
Finance Date"). On or before the tenth (loth) day after the Phase
1 Construction Finance Date, and at least six
days before the closing date for Construction Financing,
Company shall notify Participant in writing of the Phase 1
Construction Finance Date, as well as the anticipated closing date
for Construction Financing.
5. The Agreement is amended to include an Appendix D (C-51 Reservoir—Phase 1
Project Completion Schedule), attached and incorporated by this reference. Company shall use
its best efforts to achieve the project milestones listed in Appendix D within the time periods
specified. If Company anticipates a delay in achieving any of the project milestones listed in
Appendix D, Company shall promptly notify Participant in writing of such anticipated delay.
6. Except as modified in this Amendment, all terms and conditions of the Agreement
shall remain in full force and effect. In the event of any conflict or ambiguity between this First
Amendment and the Agreement,this First Amendment shall control.
7. This First Amendment is effective on the Effective Date, and may be executed by
the Parties in counterparts which, when taken together, shall have the force and effect of an
original binding document.
(Remainder of Page Intentionally Left Blank)
2
IN WITNESS OF THE FOREGOING, the Parties have caused this Agreement to be
executed by their respective duly authorized officers as of the date and year set forth above.
PARTICIPANT
CITY OF DANIA BEACH, FLORIDA, a
Florida municipal corporation
ATTEST:
THOMAS SCHNEIDER, CMC LORI LEWELLEN
CITY CLERK MAYOR
APPROVED FOR FORM AND
SUBSTANCE
ANA M. GARCIA, ICMA-CM
CITY MANAGER
THOMAS J. ANSBRO
CITY ATTORNEY Date: , 2019
3
COMPANY
WITNESSES: PALM BEACH AGGREGATES, LLC, a
Florida limited liability company
By:
Signature Name: Enrique Tomeu
Title: President
Print Name Date:
Signature
Print Name
4
Appendix D
C-51 Reservoir—Phase 1
Project Completion Schedule
Revised November 26, 2018
Description Milestone Dates
Construction Financing Commitment June 30, 2019
Notice of Construction Financing Commitment July 10, 2019
Closing on Construction Financing September 30, 2019
Commencement of Construction October 2019
Construction Substantial Completion August 2021
Operational Testing September 2021
Final Cleanup and Demobilization September 2021
2021 Closing and Turnover to C-51 Reservoir, Inc. October 2021
Commencement of Operations October 2021