HomeMy WebLinkAboutR-2022-097 S3S Construction West Wing Renovation Project Contingency Amount Increase RESOLUTION NO. 2022-097
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA, AUTHORIZING THE INCREASE OF THE WEST WING
RENOVATION PROJECT'S CONTINGENCY AMOUNT BY AN
ADDITIONAL TWENTY-FOUR THOUSAND EIGHT HUNDRED SIXTY-
NINE DOLLARS AND THIRTY-TWO CENTS ($24,869.32), CHANGING
THE CURRENT CONTRACT AMOUNT TO A NOT TO EXCEED SIX
HUNDRED EIGHTY-TWO THOUSAND FOUR HUNDRED SIXTY-NINE
DOLLARS AND THIRTY-TWO CENTS ($682,469.32); PROVIDING FOR
CONFLICTS; FURTHER, PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the two-pronged aim of the City Hall West Wing Renovation Project is to
achieve full compliance with the American with Disabilities Act (ADA) requirements and create
office space for the elected officials and one small-sized city department; and
WHEREAS, during the early and middle stages of construction, the Contractor, S3S
Construction, discovered asbestos in the floor tiles, which required immediate removal, as well
as structural component issues on the roof and interior "bridge" structures that required change
orders totaling $24,971.76; and
WHEREAS, based on these unforeseen situations, a request for increasing the project's
contingency amount by $109,600.00 was authorized in March 2022; and
WHEREAS, during the final stages of the project, some interior re-arrangement of items
and electrical modifications need to be addressed as well as the installation of a window in one
of the offices; and
WHEREAS,the tasks that are required to complete the project will cost$24,869.32;
NOW, THEREFORE,BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF DANIA BEACH, FLORIDA:
Section 1. That the foregoing "WHEREAS" clauses are ratified and confirmed as
being true and correct, and they are made a specific part of and incorporated into this Resolution
by this reference.
Section 2. That the City Commission authorizes the proper City official's approval of
a Contingency Fund increase in the amount of$24,869.32, which changes the current contract
amount to a not to exceed amount of$682,469.32.
Section 3. That funding will be funded to the Capital Projects Fund Account 301-18-
00-519-62-10 via an appropriation of Administrative Impact fees, transferred to the project
account.
Section 4. That all resolutions or parts of resolutions in conflict with this Resolution
are repealed to the extent of such conflict.
Section 5. That this Resolution shall be in full force and take effect immediately
upon its passage and adoption.
PASSED AND ADOPTED on June 28, 2022.
ATTEST: zok6-4
n 74:0
THOMAS SCHNEIDER, CMC TAMARA JAM
CITY CLERK �; MAYOR
APPROVED AS TO FORM AND CORRECTNESS:
E E . B TSIS
AT RNEY
2 RESOLUTION#2022-097
loor tiles, which required immediate removal, as well
as structural component issues on the roof and interior "bridge" structures that required change
orders totaling $24,971.76; and
WHEREAS, based on these unforeseen situations, a request for increasing the project's
contingency amount by $109,600.00 was authorized in March 2022; and
WHEREAS, during the final stages of the project, some interior re-arrangement of items
and electrical modifications need to be addressed as well as the installation of a window in one
of the offices; and
WHEREAS,the tasks that are required to complete the project will cost$24,869.32;
NOW, THEREFORE,BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF DANIA BEACH, FLORIDA:
Section 1. That the foregoing "WHEREAS" clauses are ratified and confirmed as
being true and correct, and they are made a specific part of and incorporated into this Resolution
by this reference.
Yas S38
lkpY Prime Contract Change Order (CO)
'`' CONSTRUCTION
Project Information Prime Contract Change Order
Project# 210121 Contract# 001
Title City Hall Second Floor Renovation CO# 17
Address 100 West Dania Beach Boulevard Issue Date 06-Jun-2022
Subject Changes Requested by Owner
City,State,Zip Dania Beach,FL 33004
Country
Owner/Customer Prime Contract Company
Contact Dincer Akin Ozaydin Contact Kevin Maragh
Company City of Dania Beach Company S3S Construction,Inc.
Address 100 West Dania Beach Boulevard Address 7320 Griffin Road
Suite 222
City,State,Zip Dania Beach,FL 33004 City,State,Zip Davie,FL 33314
Country Country United States
Phone 954-924-6800 Phone (954)859-5661
Fax Fax (954)859-5663
You are directed to make the following changes to this Contract:
CO#17:Changes Requested by Owner
This CO has been generated following the on-site meeting with the PM and several department personnel on May 26th.The requested changes are:
1. Breakroom 204—Remove cabinet sections to make way for a new refrigerator.Specs to be provided by City.Install the same cabinets into Office 224.
2. Relocate HR's copier to Office 224.
3 Eliminate cabinets in Copy Room 222 to make space for a new refrigerator
4 Office 207—Make new exterior wall cut out for new window on the south wall+/-38"H x 111'W.Fumish and install new window.
5. Add new electrical circuits for refrigerators.
6. Add LV box and stub up at new copy location.
7. Install water lines for new refrigerators.
8. June 16th site meeting.Storage Room 210-Relocate Door&Frame to hallway side.
All other terms and conditions of the Contract Documents shall remain in effect
Original Contract Price $548,000.00
Net change by previous Change Orders $109,600.00
Contract Amount Prior to this Change $657,600.00
Amount of this Change Order $24,869.32
Revised Contract Amount,including this Change Order $682,469.32
The Contract time due to this Change Order has increased by 40 Working Days
Response'❑Accept 0 Do Not Accept
City of Dania Beach S3S Construction,Inc.
Company Company
By Date By Date
Page 1 of 2
3 S3S Prime Contract Change Order (CO)
CONSTRUCTION
Pro.osed Items
Item# Item Description Quantity Unit Unit Price Total Price
1 CPR#17.Cabinet and Countertop Modification and Re-installation 1 LS 3,536.00 3,536.00
2 CPR#17:New Window Opening Cutout/Demo,Prep rough opening 1 LS 2,250.00 2,250.00
3 CPR#17:Electrical Circuits/Outlets 1 LS 1,104.00 1,104.00
4 CPR#17:Add Cabinet Backing at New Location 1 LS 650.00 650.00
5 CPR#17:Manlift Rental for Wall Cutout and Window Installation 1 LS 1,800.00 1,800.00
6 CPR#17:New Window and Installation 1 LS 3,792.59 3,792.59
7 CPR#17:Finishes:Drywall,Stucco patch,and paint 1 LS 2,150.00 2,150.00
8 CPR#17:Plumbing,install water lines for refrigerators 1 LS 1,060.00 1,060.00
9 CPR#17:Field General Conditions 1 LS 1,307 41 1,307.41
10 CPR#17:GC Overhead&Profit 1 LS 2,647.50 2,647.50
11 CPR#17:Bond Fee 1 LS 669 82 669.82
12 CPR#17:Permit Fee Allowance for revised drawings 1 LS 360.00 360.00
13 Storage Room Door Relocation 1 LS 3,542.00 3,542.00
Subtotal=$24,869.32
Tax=$0.00
Total=$24,869.32
Page 2 of 2
r
4 Office 207—Make new exterior wall cut out for new window on the south wall+/-38"H x 111'W.Fumish and install new window.
5. Add new electrical circuits for refrigerators.
6. Add LV box and stub up at new copy location.
7. Install water lines for new refrigerators.
8. June 16th site meeting.Storage Room 210-Relocate Door&Frame to hallway side.
All other terms and conditions of the Contract Documents shall remain in effect
Original Contract Price $548,000.00
Net change by previous Change Orders $109,600.00
Contract Amount Prior to this Change $657,600.00
Amount of this Change Order $24,869.32
Revised Contract Amount,including this Change Order $682,469.32
The Contract time due to this Change Order has increased by 40 Working Days