Loading...
HomeMy WebLinkAboutR-2023-151 Amending Scope for Southeast Drainage Project - WSP USA Inc.REsoLUrroN No.2ox-ltl A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DANIA BEACH, FLORIDA, AUTHORIZING THE PROPER CITY OFFICIALS TO AMEND THE AGREEMENT BETWEEN THE CITY OF DANIA BEACH AND WSP USA. INC.. IN ORDER TO CHANGE THE SCOPE OF THE EXISTING AGREEMENT FOR THE SOUTHEAST DRAINAGE PROJECT TO ELIMINATE CONSTRUCTION ENGINEERING INSPECTION (CEI), AND ADDING IN THE FOLLOWING SERVICES: POST ENGINEERING SERVICES INCLUDING ADDRESSING REQUESTS FOR INFORMATION (RID SUBMITTALS, REVIEWING DESIGN CHANGES FOR LTNFORESEEN CONDITIONS, AND PREPARING RECORD DRAWINGS; PROVIDING FOR CONFLICTS; FURTHER, PROVIDING FOR AN EFFECTIVE DATE. WHEREAS, On May 11, 2021, the City Commission approved Resolution 21-068 authorizing a substitute agreement with WSP in the amorurt $880,471.87 for engineering services for the Southeast Drainage Retrofit Project; and WHEREAS, City Commission authorized the award under the request for qualifications (RIQ) No. 19-014 to WSP USA, Inc., for engineering design services, bidding support, design services during construction, and project certification for the Southeast Drainage Retrofit Project; and WHEREAS, Broward County Transportation Surtax funds are funding in part the construction of the Southeast Drainage Retrofit Project and Su(ax regulation prohibit the design engineer from providing construction engineering and inspection (CEI) services; and WHERB,AS, the reviewing agencies (Broward County and South Florida Water Management District)also require the City to modif! the scope of services to expand the scope of post engineering services, to include more extensive requests for information (RFI) submittals, reviewing design changes for unforeseen conditions, and preparing record drawings; WHEREAS, due to the additional seruices required, ard the overall increase in the cost of the design due to reviewing agency requirements and the addition ofnew services to the agreement, the conhact cost act has remained steady, despite the removal ofCEI services; NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF DANIA BEACH, FLORIDA: Section 1. That the above "Whereas" clauses are ratified and confirmed, and they are made a part ofand incorporated into this Resolution by this reference. Section 2. That the proper City officials are authorized to amend the underlying Agreement to modi$ the scope of services for the Southeast Drainage Project with WSP USA, Inc. (WSP) to eliminate Construction Engineering lnspection (CEI), and to provide the following additional services: post engineering services including addressing requests for information (RFI) submittals, reviewing design changes for wrforeseen conditions, and preparing record drawings. Section 3. That the City Manager and City Attomey are autlorized to make minor revisions to the Amended Agreement which are deemed necessary and proper and in the best interest of the City and to execute extensions that do not alter costs or scope of the agreement. Section 4. That the Agreement is funded with Purchase Order 2021-00000320 and there is no financial impact since the cost of the agreement does not change. Section 5. That all resolutions or parts of resolutions in conflict with this Resolution are repealed to the extent of such conflict. Section 6. That this Resolution shall become effective within ten (10) days of its passage and adoption. pAssED AND ADoprFD onulgwwx 12,2023. Motion by second by FINAL VOTE ON ADOPTION: Commissioner Joyce L. Davis Commissioner Tamara James Commissioner Marco Salvino Vice Mayor Lori Lewellen ELORA CITY CLERK wAPPROVED AS TO FORM AND CORRECTNESS: RESOLUTION #2ON-I ' I FIRST AMENDMEI{T TO AN EXISTING AGREEMENT BETWEEN THE CITY OF DAI{IA BEACH, FLORIDA AIID WSP USA, INC. INC, FOR SERVICES RELATEI) TO THE SOUTIIEAST DRAINAGE PROJECT AND AMENDING THE EXISTING AGREEMENT TO PROVIDE A REDUCTION IN THE PROJECT SCOPE AIID DELIVERABLES. This is the First Amendment ("Amendment") to an Agreement (the "Agreement") existing between the City of Dania Beach, Florida, a Florida municipal corporation (the "City") and WSP USA, Inc. ("Contractor"), a foreign corporation registered to conduct business in Florida, having its local office located at 7650 Corporate Center Drive, Suite 300, Miami, Florida 33126. The original Agreement dated May 13, 2021, is made a part of and is incorporated into this Amendment by this reference. In consideration of the mutual covenants, terms and conditions contained in the Amendment, and other good and valuable consideration, the adequacy and receipt of which are acknowledged and agreed upon, the parties agree as follows: L Due to County grant requirements, the Parties agree to amend the scope of the subject Agreement to eliminate Construction Engineering Inspection (CEI) services and to add the following services: a. Post Engineering Services (including addressing requests for information (RFI) submittals; and b. Review design changes for unforeseen conditions; and c. Prepare record drawings. 2. The Parties acknowledge and agree upon the changes in Scope as shown in the attached "Scope and Fee Proposal Amendment" which is incorporated by this reference and attached to this Amendment as Exhibit *A". 3. That in all other respects, the Agreement, and all Exhibits to it, are ratified and reaffirmed, and remains in full force and effect. SIGNATTJRES ON THf,, FOLLOWING PAGES IN WITNESS OF THE FOREGOING. the parties have executed this Amendment effective as of ATTEST: ELORA RIERA, MMC CITY CLERK APPROVED AS TO LEGAL FORM: EVE A. BOUTSIS CITY ATTORNEY CITY: CITY OF DANTABEACH, FLORIDA a Florida Municipal Corporation ARCHIBALDJ. RYANIV MAYOR ANAM. GARCIA, ICMA-CM CITYMANAGER 2023. WITNESSES:CONTRACTOR WSP USA, Inc., a foreign corporation resistered to conduct business in Florida. Signature Signature PRINT Name PRINT Name Signature PRINT Name Date STATE OF COUNTY OF The foregoing instrument was acknowledged before me by means ofE physical presence or E online notaxization, on this _ day of 20-, by of WSP USA, Inc., a foreign corporation, registered to conduct business in Florida on behalf of the corporation. He is personally known to me or who has produced (type of identification ) as identification. Mv Commission Exoires:NOTARY PUBLIC, STATE OF (Name ofAcknowledger Typed, Printed or Stamped) Title \\\l) Decen'rber 0.1. l0li Via emai l: frodri guez@daniabeachfl.gov Mr. Fernando Rodriguez, Public Services Director City of Dania Beach 1201 Stirling Road Dania Beach, FL 33004 RE: Southeast Drainage lmprovements Phase 2 Engineering Design Services, Bidding Suppon, Design Services During Construction, Construction Administration and Project Certification Scope and Fee Proposal Amendment Dear Mr. Rodriguez: WSP USA, Inc. WSP) is pleased to submit this proposal for engineering design services, bidding suppon and design services during construction associated with the Southeast Drainage lmprovements Phase 2 Project in the City of Dania Beach, Florida. Below please find our proposed detailed scope of work based on our understanding from our recent discussions. PII0.I ECT T'NDERSTAN I)IN(; The purpose ofthe Project is to address current flooding issues at the neighborhood bounded by SE 3d Street to the north, SE 2d Avenue to the west, SE 7th Street to the south and SE 56 Avenue to the east, Der Exhibit A- Fioure 'l of Request for Qualification (RFQ) 19-014 documenl Within these timits, there are priority areas located at ihe current low spots that result in traffic disruptions and repeated private property losses due to flooding. The Project area is about 103 acres and is in a low-lying area within the basin, which receives runoff from the west. Based on preliminary analysis of existing LiDAR data and ICPR-4 model runs, the improvements should consider a contribution area of approximately 190 acres. The contributing area of 190 acres is bounded by SE 2d St and SE 3'd Street to the north, state road US-1 to the west, SE 1oth Street to the south and SE sth Avenue to the east. The City is also requesting that the storm event to be modeled for the proposed solutions will be a storm event of 3-day duration and 25 year return frequency, with flooding duration of less than 6 hours, with less than 2 inches of flooding at the crown of the road. WSP understands that the City of Dania Beach is seeking drainage solutions (ie. Pump stations, drainage wells, exfiltration trenches, etc.) to reduce flooding, including duration and severity, reduce neighborhood impacts and mitigate project costs. SCoPF] OF SERVICES Based on our Project Understanding indicated above, please find below a detailed description of the proposed scope of work associated with this projecl This scope of work is for providing engineering consulting services, including developing a complete drainage report, 100% design plans and technical specifications, obtaining WSP L]SA SLrile 300 7650 Coroorale Cenler Drive ft am FL 33125 Tel:+l 305 51,1-3 r 00 Far +1 305 251 5735 \\\I) required Permits for the anticipated construction Project. In addition, to provide bidding suppon to the City and professional consultation throughout the development ofthe Project, including design services during construction, and Project's final certif ication. TASK1. BASIS OF DESIGN REPORT Upon issuance of a Notice to Proceed (NTP), WSP will start the preparation of the Basis of Design Report. As part ofthis Report, WSP is including a Drainage Feasibility Study utilizing previous plans/study/as-builts/survey/GlS atlas review, permits review, agencies Pre-Application meetings, anticipated Permit Matrix. WSP will prepare a Drainage Report based on the requirement of a storm event of 3-day duration and 25 year return frequency, with flooding duration of less than 6 hours, with less than 2 inches offlooding at the crown ofthe road. As minimum the Repon will include the modeling of the existing conditions (Pre-Development), the modeling of the proposed condition (Post-Development), Figures and the ICPR Model results for this storm event. In addition to the 3-day duration and 25 year return road, as requested by the City WSP will provide ICPR model results for the 10 year and 100 year storm events. In order to provide a responsible recommendation regarding the feasibility of the wells including wells capacity (to be included in the Basis of Design Report), WSP propose two (2) test wells to be installed to a depth of 150 feet and water samples will be collected at s-foot intervals from 70 to 150 feet. The findings will be included in a Reasonable Assurance Report to be prepared by our subconsultant Terracon, in addition to Conceptual Plan layout for City Review and Acc€ptance. The Drainage Report will include Conceptual Best Management Practices for System Maintenance and operations. As required by the City, upon acceptance and approval of Conceptual Layout and Drainage Report, WSP will proceed to 30% plans phase and release sub- consultants for Surveyin9, Geotechnical Evaluation, Hydrological Testing. In addition, the Basis of Design Report will include an opinion ofprobable mst (Class 4 Estimate) based on a 15% design. Thistask willbecompleted within 45 calendar days after NTP. Task 'l Deliverables: > Three (3) hard copies and electronic pdf copy of the Basis of Design Report which includes; o o o o Drainage Report lrtection Wells Reasonable Assurance Repon Recommended Project 11"x17" Conceptual Plans in PDF and CAD Files . Drainage Collection System Conceptual Plan View I Stormwater Pump Station Conceptual Drawing Permit Matrix with anticipated agencies having jurisdiction on the Project and estimated timeframe for processing Electronic Copies of Drainage Calculations 0pinion of Probable Costs (Class 4 Estimate) o o TASK 2 - INVESTIGATTONS AT.ID 3096 DES\GN SUBMITIAL Upon approval by the City of Task 1 deliverables, WSP will start the preparation of the 30% design documents. As part of this Task, WSP is including the coordination with existing utilities, including design ticket, Topographic Survey, Geotechnical Evaluation and Report for existing subsurface conditions and wells feasibility, 30% Design drawings, 30% Index of Technical Specifications. lt is anticipated that Task 2 will be completed within 60 calendar days after the NTP. WSP understands that the following tasks andlor documents will be provided as part of Task 2 - Investigation and 30% Design Submittal; - Attendance to one (1) Kick-off Meeting with the City. \\\ l) Topographic and Tree Survey - our subconsultantPremiere Design Solutrons (Broward County CBE), will prepare a tree and topographic survey plans with elevations measured on so-foot cross sections and at high and low points. Survey will show above-ground improvements and locations of trees pursuant to City of Dania Beach code. Survey will be performed from Right-of-Way to Right-of-Way and extend 50 feet beyond project limits at street intersections. Topographic survey for alle)Mays will be extended up to 50 feet into the alle)|ways at the intersections with City roads. The Vertical Datum will be NGVD 1929 Survey will be prepared in accordance with City Standards and in AutoCAD version 2016 or later. Geotechnical Report - As part of the field investlgation, our Subconsultant Terracon Consultants, Inc. will provide seven (7) soil borings ranging from a depth of 10-40 feet, two (2) exfiltration tests and two (2) Double Ring infiltration tests. Utility Coordination - WSP will coordinate with existing utility owners within the Project limits. Design will be completed taking into consideration these utilities. As part of the Utility Coordination, the City will provide WSP with information on existing water, sewer and storm water utilities within the Project limits. The 30% Design deliverable will include the utility Matrix. Available utility data obtained as part of the design ticket will be incorporated into the plans. Sunshine 811 Design Ticket will also be obtained. 30% Design Plans - For the development ofthis task, WSP will provide the following: . Plan Sheets, including but not limited to the following engineering disciplanes; o Civil o Mechanical o Electrical o Instrumentation & Control o Structural o Landscape . The following plan listing is anticipated based on the projected Scope of Work; o Cover Sheet o General Notes o Existing Conditions (Based on Land Survey, As builts and Atlas) o Proposed Alignment Key Map o Proposed Alignment Plans View o Collection System o Force Main System o MiscellaneousDetails o Pump Station Location and Mechanical Drawings o lrUection well location o Electrical Design Sheets for Pump Station o Structural Design Sheets for Pump Station Components o Landscape Sheet (around pump station) 0pinion of Probable Construction Cost - WSP will prepare and provide to the City an Engineering opinion of Probable Construction Cost based on the 30% design documents. Index of Technical Specifications - WSP will develop the Index of Technical Specifications for each construction discipline necessary to construct the Project Attendanceto one (l) 30% Design Review Meeting with the City. Page 3 \\\ lt Task 2 Deliverables: > Two (2) 24" x 36" signed and s€aled Survey Plans and 2016 CAD Files > Two (2) signed and sealed Geotechnical Report > Utility Matrix and Utility Coordination Letters > Three (3) hard copies 24" x 36" and electronic pdf copy of the 30% Design Plans and 2016 or later CAD Fites > Three (3) Electronic Copies of 30% opinion of Probable Cost > Three (3) Electronic Copies of Index ofTechnical Specifications > Updated Design Schedule rASK 3 - GO96 DESIGN SUBI\AITIAL For the development of this Task, WSP will provide the following; - Copy ofthe City of Dania Beach 3096 Comments and Responses from 3096 Design Submittal. - Show profile elevation ofthe top of pipe and finished grade for the proposed force mains. As indicated by the City's consultant, profiles for gravity drainage is not required and therefore not included. - ldentification of demolition limits and items on the Design Plans - Additional Detailed information to Plan Sheets, including but not limited to the following sheets; o Cover Sheet o GeneralNotes o Proposed Alignment Key Map o Proposed Alignment Plans o Collection System o Detailed Force Main SlEtem including alignment and profiles o MiscellaneousDetails o Pump Station Location and Detailed Mechanical Drawings o Injection well location o Detailed Electrical Design Sheets for Pump Station o Detailed Structural Design Sheets for Pump Station Components o Detailed Landscape Sheet (around pump station) - Draft Technical Specifications - Attendance to the 60% Design Review Meeting with the City of Dania Beach Task 3 Deliverables: > Updated Utility Matrix ) Three (3) hard copies 24" x 36" and electronic pdf copy of the m% Design Plans and 2016 or later CAD Files > Three (3) Electronic Copies of 60% Design Opinion of Probable Cost > Three (3) Electronic Copies ofthe Draft Technical Specifications > Updated Design Schedule \\\l) TASK 4 - PERMITTING PACKAGE WSP will prepare the Permitting Packages and obtain appticable signatures once the 60% submittal has been reviewed and approved by the City. WSP will submit the Permit Packages and checks to the respective permitting agencies, respond to any RFls the agencies may have, and attend meetings. This task will include the following; WSP will coordinate all permitting efforts with the City. WSP will identify all applicabte permits and approvals. Pre- application meetings will take place during the 30% Design Phase. WSP will provide meeting minutes listing the permit requirements and limiting conditions for all pre-application meetings. Permit application fees witl be paid by Consultant and reimbursed by the City. Anticipated agencies that have been identified for this project include but is not limited to; - City of Dania Beach - Engineering Permit - City of Dania Beach - Building Permit - Broward County - Surface Water Management - Broward County - Environmental Resource License (Modification or withdrawal of existing DF11-1042) - South Florida Water Management District (SFWMD) - Environmental Resource License (Modification or withdrawal of existing) - Florida Department of Environmental Protection (FDEP) - Discharge Permit Task 4 Deliverables: For each of the above identified permits, the following activities are anticipated and included in this scope; > Pre-application meeting and up to two (2) fo ow-up meetings as needed > Preparation of application and supporting documentation > Permit Package Submittal and processing > Responses to Request for Additional Information from Agencies. > Tracking Sheet with indication of dates of submittal of each application and approval or comments from the corresponding agency. TASK5-90 Dedrgnsubmittals For the development of the 90% Design Submittal, WSP will provide the following; - Copy of the City of Dania Beach 60% Comments and Respomes from 60% Design Submittal - Additional Detailed information to Plan Sheets - 90% Structural Plans for the two (2) pump station, including Detailed Specifications and Calcutations - 90% Technical Specifications - Attendance to the 90% Design Review Meeting with the City of Dania Beach Task 5 Deliverables: > Three (3) hard copies 24" x 36" and electronic pdf copy of the 90% Design Plans and 2016 or later CAD Files > Three (3) Electronic Copies of 90% Design opinion of Probable Cost > Three (3) Electronic Copies of the Detailed Technical Specifications > Updated Design Schedule \\\l) TASK 6 - 1oo9r'o D€sign Submittals The 100% Design Submittal will include the following items; - Copy of Comments and Responses from the Permit Package Submittal Review - Permits and 0riginal stamped permit plan sets - Eledronic DVD copies of geotechnical report, survey, engineering drawings, construction specificattons, calculations and permits (Submit all MS Word, MS Excel, PDF, CAD Files associated with the Project) Task 6 Deliverables: > Approved 10096 Construction Plans - Four (4) copies 24" x36", includlng regulatory agencies comments incorporated > DVD with 100% Construction Plans (CAD Files and PDF) T ASK 7 - P\IBLIC TNVOLVEMENT As pan of this Task, WSP and its subconsultant, Infinite Source Communications Group (ISCG) will be providing Public Information Support to the City throughout the duration ofthe Project. During this initial Task our team will perform the following activities; - PreDare a database of all the stakeholders and elected officials. - Development of Project fact sheets. - Distribution of Notices to the Community via e-mailthrough constant contact. - Attend Project coordination meetings. - Coordinate and host one (1) public meeting inviting affected residents and local agencies to review ptans, meet the team and ask any questions related to the work. - ISCG will secure the venue, schedule the meeting, develop the project flier, mail information to the public and work with Dania Beach to promote the meeting. - ISCG will work with the team to develop a presentation or any project displays andlor graphics. - ISCG will prepare all sign-in sheets, comment cards and other meeting materials. TASKE-BIDDINGSUPPORT WSP will suppon City's staff during the bidding phase. The following activities are anticipated and included in the scoDe for this task: - Coordinate the release of bidding documents with the City - Prepare One (1) Agenda for Pre-Bid Meeting - Attend and participate in one (1) Mandatory Pre-Bid Meeting - Prepare and submit to the City the meeting minutes of the Pre-Bid Meeting - Evaluate and provide response to questions from prospective bidders in a timely manner - Develoo addenda as needed - Review all bids for sufficiency and provide evaluation results to the City - Provide Recommendation of Award to the City - Provide support to the City in the preparation of Contract Documents \\\l) WSP will work with the City to provide a master copy of the Design Package in electronic format (PDF). lt is our understanding that the City will be responsible for distribution of bid packages to prospective bidders via online distribution through the City's bidding platform. WSP will respond to technical questions forwarded by the City as part of the scope. The questions witl be responded using the Addendum Form provided by the City for expedited response time and will generate necessary supporting documents, as applicable, and submit them to the City for distribution to registered plan holders. As part of the bids review, WSP will evaluate the construction approach, bid schedules, mntact and verify references, evaluation of qualifications of the bidders for undertaking the work on the project, and provide a recommendation of award. Task I Deliverables: > WSP will provide one (1) Draft for City's review and One (1) Final version of the Pre-Bid Meeting minutes in electronic format F One (1) Bids Evaluation Report with Recommendation of Award in electronic format. The evaluation report will include a spreadsheet comparing bidder's pricings. IASK 9 - DESIGN SEFNICE.S DURING CONSTRUCTION SER\AGES SCOPE AND DELIVERABLES As Engineer of Record afld4eFstru€tien+funagefi WSP will provide design services during construction, shop drawingreViews,RF|sresponse5,|imitedsiteVisits, es5 r€$+ir€d-t€5tsrreview of as-builts and Project Certifications together in coordination with the City of Dania Beach, and the Contractor(s). The services include: WSP will ettenC' Genduct and prepare agenCa and minutes fer the pre €enstrs€tien meeting. WSP period ically will monitor the contractor's on-site construction activities and inspect materials in the project site, are in accordance with the plans, specifications, and special provisions for the construction contract, and verify that accepted/approved shop drawing submittals exist for each item being delivered, to ascertain that the project is constructed in reasonable conformity with the construction documents. lf materials do not conform with the constructiondocuments,WsPwi||notifythecontractor'M contfact€H{eily€peretiens e time €f *re visits a k, WSP will ebsewe monitor the progress of the work at times appropriate to the construction so as not to impede the Contractor's progress. WSP will advise the Contractor ofdeviations, defects or deficiencies observed in the work. csnstructien pregress anC iCentify pessible Calays, lf feunC, WSP will netify the City and eentraGt€r ts take anC will mplete any €eeCed+e€ai+s \\\l) WSP is not authorized to change, revoke, alter, enlargg relax or release any requirements of the Contract Documents without written approval from the City. As Engineer of Record, WSP will be responsible for the certificationofProjectandapproVa|ofAs-Bui|ts.tg WSP will not be responsible for, and will not control the means, methods, techniques, sequences andlor pr@edures of construction for the Project. No action taken by WSP will relieve the Contractor from their obligation to perform the Work in strict conformity with the requirements of the construction Contract Documents together with all other applicable laws, rutes and regulations. WSP will review materials testing by a third party testing labr te be previded by the eentracter, te ensure their @igneC facilities, These meteriels in€lsdeseils, asphat+ mine the te meet ths WSP will eerCinate with centraGter t€ inage well start up testing' and swit€hgeer testing, lf requesteCr WSP will submit te the eity Cecumentatien re^erls en @e w€ekthe€nstruetisn workisdenegrassgg t€+he€ity{reekl} WSP will prepare the agenCas, atend and eenCuct Genstruction pregress meetings (asssrred en+msnthly i€trfi€gress meetings, WSPwill r an€e with tt|o WSP will meniter mechani€al eqsipment testing anC start ups, and will participats in the final inspe€tien ef the and will prsCsce a certificae ef sub.gntial 6€mpletion, end finaliratien ef Gentract cheGklist, WSP will also coordinate and receive documentation and records from the Contractor for comDliance with the project contract in accordance to the City's procedures. WSP willreview as-built drawings, operation and maintenance reports provided by the contractor. WSP will assist the City in project closeout procedures. Task 9 Deliverables: \\\l) HrogFess+{eetingeAgendss HiS€etindAiFut€s >-fia€pe€ti€n+ep€rts ) Review Pressure Test reoorts > Review System Test Reports > Final Punch List > Review and recommendations for approval of Contractor's change orders - Up to five (5) Change orders > Contractor's Record Drawings Log File > Request For Information (RFl) Logs. Up to 50 RFls overall, including but not limited to stakeholders, permitting agencies and grant offices. > Submit responses to contractor, stakeholders, and permitting agencies l+Fklweek€f{€nstru€ti€n eo*Fe€t€fl3-menths) , Submit responses to grant agencies including, but not limited to: ,. Broward County, Transportation Surtax Funds, Project No. DANl,017 /. Florida Division of Emergency lvlanagement, Hazard Mitigation Grant Program, Project No. 4337-494- R > Florida Department of Environmental Protection, Resilient Florida, Project No. 22FRP2t1 > Review of shop drawings - up to fifty (50) reviews > Review of Project's As-Builts prepared by Contractor > obtain Project's Certifications and close out permits PROPOSED STAFFING It is anticipated that WSP will provide staff members in the following positions: Project Manager (Part-Time) (WSP): - WSP'S Project Manager will serve as the owner's Consu ltant point of contact and report work progress, budget status, major Project issues and other pertinent information to the City. - Manage the City's contract with WSP. Manage sub consultants. nttendsr cends6ts and pre^are agendas and meeting minstes fer csnstrustien prggress meetings (one pe. 13 me€ths€f4enstrc€tie+ .serVeasthecity'srePresentatiVeforthereview@i€Fofc|aims and change orders. - Review and Recommendation of payments, processing of RFls and+Fes, change orders, claims, project start- up and closeout. -----R€+i€trc€Fstru€ti€n+r€cesse$ Page 9 \\\l) - Keep and update Submittal and RFI Logs. Review prqjeGt activities with €lientand €entracter's field sspervisien reselving Cisputesand other is$ues, Review Caily insp€gtien rsperts and ether ^rqiect de€smentatien, Attends and lead censtructien mgetinqs with 6lient anC Gontra€ters, ene{ilnspe€te*{Ped-+ime} Site eenditiens: menitsr site 6enditiens fer safegf hazarCs Curing onsite, n$insps€ters are net qualified sr trained sefety sngineersr they are net expected ts reEegnize all types ef hararCs, Thsreferer inspe€tors ars n ---+ecording€f+un€h Reviewing and previds comments ef Gsntra6ter as bsilts, Maintaininga r€Gerd ef ebssrvatiens in regarC ts Genstruetien quality, safety precoCsres, and nen €€m€li€fl€€ll|rerk Maintaining a recsrC ef Cameges t€ existing utilities and snisting infrastru€tsrsr and assseiated €errectiv€ @k+ Prsgress Reperts: prepare repens decurFenting the verisus censtrsetien activiti€s ecsJrring in tl.e Prd€6t, Damage te Existing Utilities: identify any existing facilitiss damaged by ths Csntra€ter and verify thatths eenracter has netifisC ths rsspe€tive ewner(d, eentraGter are respensible fer predu€ing a Ceteiled damage Equipment Tssts and qf*erns Stert Up; verify that equipment tests anC syst€ms stert up6 are cenduct€C in the presence sfapp hereef, Du.ing the t€stsr the Prdect Ma the test precCures{nC{ta$upr Pl'etograph;6 Rseerd; prevade a phet€gr^phi€ re€erd sf $e €enstruGtien, beginning with pre €snstru€tien Ph€tegraphs will bo ith ime '\dheren€e t€ eentra€t De€sments: review rnetsrials and werknanship gfths prdeets and repert ts the ei+ any deviatiens frem the Gsntract Ce€umenE In.pect€r will alss det€rmine tl€ acceptability ef the werk/materials and in cenGert with EOR, Re6erd Drawingsi menitsr te ensure th^t red line Crawings are being preperly maintained by the eentractsr ^nd that a Flerida R€ ie'# the red line Crawings en the 30th ef every month, er msre eften, as CeemeC necessary by the Prqte€t grrunds fer Pay Reqsests: The Canstructisn Inspe€ter will meet with the gsntra€terr in the field, t€ verify eentracter pey reqsest quentitis d Page I0 \\\ ll withllelding eoftrector menthly Frogrsss ^aymsnB until ssch tims as ths red lins drawings ars breught sp will rscemmend to the eit$ whe will mako a final Csterminatien if withhelding paymsnt is msriteC, Preject is Netifi€atien: Threugh esr psblie invelvement ssbcensultant lSeG wa will GeerCinats with ths Centra6ter te inferm $s nsighbering rssiC€ncs / bssinsss establish ments ef the spGeming €enstru€tien wsrk' by msens of @ Prde* eempletieni Insps€ts prds€ts fer substential anC final cempletien anC prspares list ef any defi€i€n€i€+ INFORMATION TO BE PROVIDED BY CLIENT ln order to complete the Scope of Services, the following items are to be provided by the Client: l. Permit application fees and agency review fees. 2. As Built or GIS Atlas for existing watet sewer and storm water facilities 3. Subsoil geotechnical report for previous projects 4. Topographic Survey prepared fc previous Fojects in CAD format SCHEDULE OF IMPLEMENTATION wSP is prepared to begin the work immediately upon receiving written notic€ to Foce€d. WSP will begin preparing the Basis ofDesign Report upon rec€ipt ofthe notice to proceed. A Preliminary Schedule oflmplernentation is provided as Exhibit A to this Proposal. FEE SCHEDULE The services described herein will be performed on a lump sum Not-to-Exceed fee basis as in the amorutt of $8t4171.t7 in aqnrdance to the Fee Schedule below and Exhibit B's labor rates. Reimbursable expenses for the amoun of 825,50A(N for this contmct include, but are not limited to, permitting fees, printing and reproduction cose and soft digs. The total lump sum Not-to-Exceed fee basis cost is $88{1,471.87. Refer to Exhibit B for the manhours and detailed Fee Schedules. Per Broward County Requirements, 30olo ofthe work needs to be performed by a Broward County CBE Firm. For thisjob, we are using Premiere Design Solutions, Inc. and Conemco Consultants for a total CBE Percentage of33.417o. FEE SCHEDULE TABLE Basis ofDesign Report lnvestigdion and 30olo Design Submittal Page 11 \\\lt Task 3 60010 Detailed Design $101,208.34 Lump Surn Task 4 Permitting Package $79,s45.1s Hou y, Nd-toExc€ed Task 5 907o Design Submittal $71,012.1t Lump SuIn Task 6 l00elo Design Drawings $51,857.31 Lump Sum Task 7 Public Involvement $36,780.27 Hourly, Not-to-Exc€ed Task 8 Bidding Support s20,t72.61 Hourly, Not-to-Exc€ed Task 9 Design Sewices During Constuction s2m,166.64 Lump Surn Reimbursable Expenses $25,500.00 Allowance TOTAL $8t0.,9r47 Lump Sum II{VOICING WSP will invoice morthly. Vr/SP requires payment ofinvoices within 30 days ofthe receipt ofinvoices lnvoices not paid within 30 days are subjcct to a s€rvice charg€ including costs ofcollection and attaney's fees, ifnecessary. ASSUMPTIONS, EXCLUSIONS AND LIMITATIONS 1. Since the amicipated design will not utilize a proposed dmimge swale in West LakE no wetlsnd impacts are proposed as part ofthe hojec{. No work or swale creation as prwiously designed by othen will be done, sinoe no wetlands work is proposed. It is anticipst€d that there arc no protected spccies surveys or permitting required. Ifthere are nrctland or protected species permits requird this will be provided as additional scope. The agencies withjurisdiction for this Projcct include City ofDania B€aclf Florida D€parment of Environmental Prcection, Souh Florida Water llhnagement District (SFWMD) and Broward County. SFWMD ERP is scheduled to expire in 7/7/2020. This needs to be modified. As part oflhe previous Project, SFWMD p€rmit application # 1t0106-l I has been issEd. Broward Co. License # DFI l-lM2 is p€nding. USACE permit SAJ-201l-00199 (IP-M5W) is pcnding. Broward Co. surface urater permit L200901I is pending and will need to be modified and is rpquired for issuance based on no work proposed in West take/property east ofSE 5th Ave. The SFWMD permit will be modifed or withdrawn and the Browrd Co. license App. DFI lJ()4Z and USACE Application will be withdrawn. Scope does nct include any wetland mitigttion monitoring or post-construction water quality. Protected species and other incidental wildliF observations will be noted Species.specific assessments (such as bonneted bat, rmding birds, indigo snakes) are not included in this scope, but can be provided as an additional service. There are existing outralls to West Lake Park that were not previously permitted. Consultant shall propose to inctrporde those culv€rts into the permit, assuming as a Design Crileria $at Post Dwelopnrcnt discharge condition onto the West Lake Park will be comparcd to PI€ Development Condition. Horwer, if the permitting agencies reject their use or rcquire additional agreements, legal counsel, notice ofviolation 2. 3. 4. 5. 6. 7. Page 12 \\\ ll resolutioq or extraordinary coordination beyond the typical permitting r€quirements, this will be coordinated by the City. 8. 5-year certification ofsurhce water management system is not included. 9. Tree Permitting efforts and fees are excluded. 10. It is anticipated up to l0@ $500/EA. Subsurface geophysical utility investigationg soft digs" as described on ASCE 3842. 11. Traffic and Signalization Anatysis is not included as part ofthis Proposal. 12. Proposal do not include monitoring and inspection ofthe contractor's Work Zone Traffic Control Plan or requests of modifications to the Work Zone Traffic Contol Plan, including Altemate Work Zone Traffic Contol Plarl to be in accordance with the applicable permi*. 13. Vibration monitoring services are not included in this scope of work. 14. Permit fees are assumed to be reimbursed by the Ovrner. Permit Application Fees have been estimated in $20,000 for budg* puposes. Receipts from Permit Agencies will be submited as part ofthe invoices. 15. The Electdc Switchgear panel will include an outlet for emergency generalor connection. The design ofa standalone generator set is not included in the scope of services, 16. Responses to grant agencies can be provided if infomration requested can be obtained from existing project design documents. Any additional information requ€sted by grant agencies is not included in this scope but can be pror ided as an additional service. PaOe 13 \\\l) CLOSURE Thank you for the opporhmity to submit this proposal and look forward to working with you on this project. We are confident that our integrated services and experience will prove successful on this exciting project. WSP can begin working immediately on the project upon receipt the signed authorization, one copy ofthe signed proposal. Ifihis proposal is acceptable to you, please sign below as your formal authorization to proc€ed and retum a copy to us for our files. Ifyou have questions, please call us at 305.514.3100. Sincerely, A==-./,f Wemer Reinefeld. P.E. Project Manager AUTHORIZATION Receipt ofthis Proposal, including the General Terms and Conditions annexed h€reto, is hercby acknowledged and all ofthe terms and conditions contained therein are acceDt€d. City ofDania Beach RE: Southeast Drainage lmprovements Phase 2 Engineering Design Services, Bidding Support, Design Services During Construction and Project Certification Scope and Fee Proposal Amendment Compstry:(Client) By/Title: (Authofi zed reprcsentltive) Sigtrature By: Dste: Page 14