HomeMy WebLinkAboutR-2024-069 Craven Thompson & Associates, New Beach Restroom and Storage Facility ProjectRESOLUTION NO. 2024-
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DANIA
BEACH, FLORIDA, AUTHORIZING DESIGN ENGINEERING AND
PROJECT MANAGEMENT SERVICES FROM CRAVEN THOMPSON AND
ASSOCIATES FOR THE OCEAN PARK NEW RESTROOM FACILITY AND
CONVERSION OF EXISTING RESTROOM FACILITY INTO A STORAGE
FACILITY PROJECT IN AN AMOUNT NOT TO EXCEED FOUR HUNDRED
SEVENTY THOUSAND SIX HUNDRED SEVENTY-TWO DOLLARS
($470,672.00); PROVIDING FOR CONFLICTS; FURTHER, PROVIDING FOR
AN EFFECTIVE DATE.
WHEREAS, the Public Services Department is requesting authorization to accept a
proposal for design engineering and project management services from Craven Thompson and
Associates for the Ocean Park New Restroom Facility and Conversion of Existing Restroom
Facility into a Storage Facility Project (the "Project"); and
WHEREAS, Craven Thompson & Associates was chosen as one of fifteen firms awarded
a contract as an approved engineering consultant for continuing contract services by the City
Commission on January 12, 2021, pursuant to RFQ No. 20-005 under Resolution No. 2021-007;
and
WHEREAS, Craven Thompson & Associates will provide engineering, project
management, design plans, permitting, and bidding assistance services related to this project in an
amount not to exceed Four Hundred Seventy Thousand Six Hundred Seventy -Two Thousand
Dollars ($470,672.00), which proposal is made a part of and incorporated into this Resolution as
Exhibit "A".
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMbIISSION OF THE
CITY OF DANIA BEACH, FLORIDA:
Section 1. That the above "Whereas" clauses are ratified and confirmed, and they are
made a part of and incorporated into this Resolution by this reference.
Section 2. That Craven Thompson & Associates is authorized to provide design
engineering and project management services for the Ocean Park New Restroom Facility and
Conversion of Existing Restroom Facility into a Storage Facility Project in an amount not to
exceed Four Hundred Seventy Thousand Six Hundred Seventy -Two Thousand Dollars
($470,672.00).
Section 3. That the City Manager and City Attorney are authorized to make minor
revisions to the services Agreement as are deemed necessary and proper and in the best interest of
the City.
Section 4. That American Rescue Plan Act (ARPA) funding is available for this
Project and shall be appropriated to Ocean Park Restroom and Storage Facility Project
Professional Services Account No. 415-45-24-545-31-10.
Section 5. That all resolutions or parts of resolutions in conflict with this Resolution
shall be repealed to the extent of such conflict.
Section 6. That this Resolution shall be effective 10 days after passage.
Ham PASSED AND ADOPTED on !-i J 2024.
/
Motion by l oynffl . Qry U S second by i L% M f 1,&{ •
FINAL VOTE ON ADOPTION: Unanimous V/
Yes No
Commissioner Joyce L. Davis
Commissioner Tamara James
Commissioner Marco Salvino
Vice Mayor Lori Lewellen
Mayor Archibald J. Ryan IV
0 �r!?*
itoo Lw- A
APPROVED AS TO FORM AND CORRECTNESS:
' OUTSIS
TTORNEY
I
RYAN IV
2
RESOLUTION #2024-0 (got
Engineers
Plaeancrs
Suraevors
Landscape Architects
3561 N.W. 53rd Street
Fart Lauderdale, fL 33309.6311
(954)739-6400
April 26, 2024
Mr. Dincer Ozaydin, P.E.
Director Public Services Director/City Engineer
City of Dania Beach
1201 Stirling Road
Dania Beach, Florida 33004
RE: OCEAN PARK NEW RESTROOM FACILITY AND CONVERSION OF EXISTING
RESTROOM FACILITY TO STORAGE FACILITY
DANIA BEACH, FLORIDA
CTA PROPOSAL NO. 2024-C11.062 (REVISED)
Dear Mr. Ozaydin:
The firm of Craven Thompson & Associates, Inc. (CTA) is pleased to provide the
following proposal for Civil, Survey, Geotechnical, Environmental, Architectural, Site
Planning, Structural, Mechanical, Electrical, and Plumbing Design services and Project
Management. The scope of work is for the design of a new proposed restroom facility
at the north side of Ocean Park just north of the parking lot and to convert the existing
restroom facility, if structurally feasible, to a storage facility. An initial structural task is
proposed just to determine if the existing restrooms can be structurally reinforced to
be converted to a storage facility. If it is determined to be feasible, additional
architectural, structural, and MEP scope and fees will be needed and will be presented
in a separate proposal. Our tasks to address the scope of work described above with
the given information available is as follows:
I. SURVEYING SERVICES
1.1 Topographic Survey (CTA Task No. 11020)
Prepare an updated Topographic Survey of the parking lot and
entrance roads for Dania Beach Ocean Park as shown in attached
Exhibit "A". The Survey will meet current surveying requirements of
the Board of Professional Surveyors and Mappers of the State of
Florida, as outlined in Chapter 5J-17 of the Florida Administrative
Code. The Topographic survey will include the recovery and/or setting
of horizontal control monumentation relative to State Plane, Florida
East Zone, NAD 83(90) HARN, in US survey feet, there will be no
setting of boundary corners in conjunction with this survey. The
Topographic survey will include location of aboveground visible
improvements (i.e. buildings, pavement, slabs, fences, parking striping,
trees, and utility features and a portion of the dune, lying within the
existing areas marked in Exhibit "A". We will obtain sanitary and
storm sewer rim elevations with pipe invert elevations including size
and type of pipe with direction of flow, if visible, and not obstructed.
Topographic elevations will be obtained at intervals sufficient for
engineering design purposes. Elevations will be based on the North
American Vertical Datum of 1988 (NAVD 88) and referenced to a
Florida Department of Transportation or National Geodetic Survey
benchmark. We will show the approximate Mean -High Waterline
contour based on the elevation from FDEP and the Coastal
Construction Control Line. The survey will be prepared in AutoCAD
Civi13D, Version 2022 or higher drawing file format.
LumpSum .......................................................... $8,500.00
Mr. Dincer Ozaydin
CTA Proposal No. 2024-Cll.062(Revised)
April 26, 2024
Paee 2
1.2 Designate and Locate Underground Utilities (CTA Task No. 12050)
Engage, subcontract, and coordinate the services of a licensed underground utility
location subcontractor to horizontally designate (paint or flag) utilities within the
subject property as shown in Exhibit "A" (attached). The subcontractor will use
electromagnetic detection and/or ground penetrating radar techniques, to locate
utilities.
LumpSum.................................................................................... $7,500.00
SUB -TOTAL FOR SURVEYING SERVICES.................................$16,000.00
II. GEOTECHNICAL SERVICES (To Be Provided by Tierra South Florida)
2.1 Soil Borings and Geotechnical Report Adequate for Pile Construction
The task shall include three (3) - 70 foot depth SPT borings.
The geotechnical report shall include at a minimum the following:
• Methods and procedures for field sampling and laboratory testing
• Test boring logs and classifications
• Laboratory Test Results
• Summary of subsurface Stratification (Soil types, profiles with blow counts and N
values based on standard penetration tests for each soil layer and boring)
• Existing Groundwater Levels and Estimated Seasonal High and Low Levels
• Distribution and Thickness of Unsuitable bearing soils (if any)
• Foundation Design Recommendations
o Allowable soil bearing pressure
o Soil passive sliding resistance
o Coefficient of Soil / Concrete friction
o Allowable lateral passive pressure
o Soil Dry and wet densities
o Effective angle of internal resistance
o Soil cohesion
LumpSum.................................................................................. $16,720.00
SUB -TOTAL FOR GEOTECHNICAL SERVICES...........................$16,720.00
III. ENVIRONMENTAL SERVICES (To be provided by the Chappell Group, Inc.)
3.1 Design Phase Environmental Services (CTA Task No. 41000)
Assist Prime with preparation of the site plan layout and plan development based on
permitting constraints. Attend meetings with City and Consultant Team. Review plans
and provide comments and revisions. Assist Prime and structural engineer with seawall
design and dune restoration and walkovers.
LumpSum.................................................................................... $6,000.00
CIZPAN-IROMPSON&ASSOCIATES INC
Mr. Dincer Ozaydin
CTA Proposal No. 2024-C11.062 (Revised)
April 26, 2024
Page 3
3.2 Environmental Permitting (CTA Task No 41110)
Prepare and finalize permit drawings and prepare applications for the proposed
structures to be renovated and constructed east of the Coastal Construction Control
Line (CCCL). Prepare responses to FDEP and FFWCC Requests for Additional Information
(RAls) and revise plans and exhibits as necessary for permit approval.
LumpSum.................................................................................. $26,000.00
3.3 Bidding Assistance for Environmental Design (CTA Task No. 41130)
Assist with responses to bid questions related to environmental design.
LumpSum....................................................:............................... $5,500.00
3.4 Environmental Construction Consulting Services (CTA Task No. 41120)
Attend construction meetings and assist with construction related reviews for
environmental construction requirements. Perform environmental construction
observation and reports. (Task is for duration or one year maximum)
LumpSum.................................................................................. $21,000.00
3.5 Tree Inventory and Arborist Report (CTA Task No. 21070)
Conduct a site visit to perform a tree inventory and analysis, including a full arborist
report for all trees within the defined limits of work.
LumpSum.................................................................................. $13,500.00
SUB -TOTAL FOR ENVIRONMENTAL SERVICES ....................... $72,000.00
IV. CIVIL ENGINEERING SERVICES
4.1 Prepare Water and Sewer Plans (CTA Task No. 31040)
Prepare water sewer plans adequate for approval through all governing agencies
assuming only a package private lift station required for north new restroom facility and
sewer lateral for storage facility. If changes are required to the public station or public
gravity main as a result of the project, additional fees will be required for additional
design as an additional service.
LumpSum.................................................................................. $14,900.00
4.2 Prepare Paving Grading and Drainage Plans (CTA Task No. 31030)
Prepare paving grading and drainage plans adequate for approval through all governing
agencies. Task includes stormwater design calculations required for SWM license and
earthwork dredge and fill calculations required for environmental CCCL permit to assist
environmental consultant.
LumpSum.................................................................................. $16,900.00
4.3 Prepare Standard Engineering Sections and Details (CTA Task No. 31035)
Prepare standard engineering sections and details adequate for approval through all
agencies including but not limited to demolition plans, erosion control plans, pavement
marking and signage plans, typical cross sections, and engineering details.
LumpSum.................................................................................... $6,900.00
CRMN•1NQMPSON & ASSQCIMES INC
Mr. Dincer Ozaydin
CTA Proposal No. 2024-C11.062 (Revised)
April 26, 2024
4.4 Civil Permitting/Processing CTA Task No. 31080)
Prepare and process engineering permits through the following agencies:
• Broward County Environmental Protection SWM License
Broward County Environmental Protection Sewer License
• Florida Department of Environmental Protection Water Permit (If Applicable)
• City of Dania Beach
LumpSum.................................................................................... $5,900.00
4.5 Civil Construction Administration Services (CTA Task No.31120)
• Attend Pre -Construction conference meetings
• Prepare Meeting Minutes for Pre -Construction Meeting.
• Review and process shop drawings.
• Perform general site inspections/reviews as required to determine in general if the
work is being performed in a manner that when completed will be in accordance
with the contract documents. Inspections will be part-time, approximately three (3)
hours per day, three (3) days per week for a Senior Inspector with an anticipated
construction schedule of six (6) months to complete construction of all utilities and
paving.
• Take photos of construction activities during site visits.
• Review RFI's and change order request and provide professional opinion of request
to City project manager (if required).
• Negotiate change orders on behalf of the City (if required).
• Substantial and Final walkthrough with Contractor, Client, and regulatory agencies.
• Prepare final punch list and follow-up.
• Attend regular bi-weekly TEAM's meetings if required up to 6 months in total.
LumpSum.................................................................................. $15,900.00
SUB -TOTAL CIVIL ENGINEERING SERVICES............................$60,500.00
V. SITE PLAN PROCESSING LANDSCAPE ARCHITECTURAL AND IRRIGATION SERVICES
5.1 Schematic Design (CTA Task No. 24002)
(Includes one submission only, any comments will be addressed in Task 2)
• Survey, as -built drawing review and existing conditionsverification
• Overall site plan, as per schematic design by PGAL Architects
• Plan enlargement (one) as appropriate for one key area with hardscape selection (one
option only)
• Schematic planting plans with proposed plant selections (tree/palm only;
shrubs in high, medium and low categories only; plant species not included)
• Schematic lighting plansshowing locations of proposed lightfixtures
• Character imagery for outdoor furnitureand signage
LumpSum.................................................................................... $8,000.00
MAN Q44PSON & ASSOCIATES INC
Mr. Dincer Ozaydin
CTA Proposal No. 2024-C11.062 (Revised)
April 26, 2024
Paee 5
5.2 Design Development (CTA Task No. 24003)
(includes one submission & one revision)
(100% Design Development Submission for Preliminary Contractor Pricing)
• Layoutplan showing dimensions, material labels and pavingpatterns.
• Plan enlargements as appropriate forkey area (one only).
• Treedisposition plans.
• Planting plan, plant schedule and planting details, including preliminary plant
selection for dune restoration (in correlation with Dune Restoration Plans from
Chappell Group).
• Landscape grading plans with spot elevations only, as per Civil PGD Plan.
• Exterior lighting plans showing locations, light, types, and fixtures (electrical
photometric plans excluded).
• Site furniture plans showing locations and furniture schedule.
• Site details for the following:
o Seawalls and/or any retaining walls (If applicable)
o Walkways, ramps, and/or steps (If applicable)
o Paving materials, color selections and patterning (if applicable)
o Beach portal, for dune crossing (boardwalk/steps/etc.) (If applicable)
o Site furnishings, including light fixtures (If applicable)
o Excludes any structural details and electrical plans
LumpSum.................................................................................. $17,000.00
5.3 Construction Documents (CTA Task No. 24004)
(includes one submission and one revision)
(100% Construction Documents for submittal to the City for Site Plan Approval, bidding
and permitting)
• Final site layout plan, in conjunction with PGAL's Site Plan, showing dimensions,
materials, paving patterns and site plan elements suitable for bidding and
construction.
• Final planenlargement for key area (one only).
• Final Tree Disposition plans, including tree removal/relocation plan for all existing
trees and palms within area of work only. Includes one (1) site visit to verify tree
species as per arborist report provided by Chappell Group.
• Final Landscape Plan, including planting plan, plant schedule and planting details,
including plant selection for dune restoration (in correlation with Dune Restoration
Plans from Chappell Group).
• Final exterior lighting plan showing locations, light types and fixtures (task does not
include electrical or photometrics plans — to be done by others).
• Final site furnishing plans showing locations, furniture schedule, and including
details including manufacturer information, size, color, model, etc.
• Finalized site plan details as included in the previous task (Design Development), for
all items approved by the City. Excludes structural details and electrical plans.
Note: All walls and steps will be finishes only and aesthetic. All functional/ mechanical
and structural drawings to be done by others.
LumpSum.................................................................................. $16,700.00
CRNEN*IHQ44PSON & ASSOCINES INC.
Mr. Dincer Ozaydin
CTA Proposal No. 2024-C11.062 (Revised)
April 26, 2024
Paee 6
5.4 Rendering (CTA Task No. 21055)
Prepare one (1) rendering of the schematic landscape plan and update once the final
landscape plan is developed. Task to include providing one (1) mounted 24" x 36" plan
if needed and a pdf of the rendering. Excludes photorealistic renderings or 3D
renderings.
LumpSum.................................................................................... $3,900.00
5.5 Site Plan Processing (CTA Task No. 21020)
Prepare submittal packages and process final site plan through the City of Dania
Beach. Task includes DRC process only and excludes City Council submissions.
Assumes project to be classified as small-scale development.
LumpSum.................................................................................... $9,000.00
5.6 Attendance at Meetings (CTA Task No. 24000)
Task includes the preparation for and attendance at meetings and conference calls with
the Client, architect and/or other team members for project coordination and approval.
This task includes staff level meetings at the City as well as the various team members.
Hourly, Not-to-Exceed.................................................................$7,500.00
ADDITIONAL CONSTRUCTION DOCUMENTS FOLLOWING SITE PLAN APPROVAL
5.7 Irrigation Plan (CTA Task No. 21035)
Prepare irrigation plans for the new landscape area, including details and
specifications suitable for bidding and construction. This includes the area
surrounding the proposed restroom building, the storage building and any necessary
temporary irrigation for dune planting establishment. Irrigation plans to be prepared
once the site and landscape plans have been approved by the City. Water Source is
to be an existing potable source. Task includes any modification to existing irrigation
system affected by the new construction, which includes one (1) site visit to verify
the existing irrigation system and components with City maintenance staff. Task does
not include electrical plans.
LumpSum.................................................................................... $8,500.00
5.8 Cost Estimate (CTA Task No. 24080)
Prepare a preliminary cost estimate based on the final site design approved by the
City.
LumpSum.................................................................................... $1,300.00
5.9 Specifications (CTA Task No. 24031)
Prepare technical specifications (Division II), detailing the proposed improvements.
LumpSum.................................................................................... $2,600.00
CROWEN-1flQ44PSCN & ASSOCINES INC
Mr. Dincer Ozaydin
CTA Proposal No. 2024-C11.062 (Revised)
April 11, 2024
Paee 7
LANDSCAPE ARCH. BIDDING CONSTRUCTION OBSERVATION AND PROJECT MANAGEMENT
5.10 Bidding Assistance (CTA Task No. 24060)
Assist the City of Dania Beach with the bidding of the construction documents including
the attendance at pre -bid meeting and responding to RFI's and development of
addenda, if required. Task includes review of final bids, if requested. Task does not
include facilitation of pre -bid meetings or agenda.
Hourly, Not-to-Exceed.................................................................$5,300.00
5.11 Shop Drawing Review (CTA Task No. 21060)
Review shop drawing for the hardscape, site amenities, lighting fixtures, irrigation, and
landscape portions of the project.
Hourly, Not-to-Exceed................................................................. $3,900.00
5.12 Construction Observation (CTA Task No. 21065)
Perform construction observation for the hardscape, site amenities, lighting fixtures,
irrigation, and landscape portions of the project. Task includes up to six (6) site visits.
Task also includes observation reports, final punch list and review of pay applications.
Hourly, Not-to-Exceed.................................................................$7,500.00
SUB -TOTAL FOR LANDSCAPE AND IRRIGATION SERVICES ...... $91,200.00
VI. ARCHITECTURAL SERVICES FOR NEW RESTROOM FACILITY
6.1 Schematic Design Phase (Provided by Subconsultant PGAL)
(New Restroom Facility Only)
• Provide schematic plan options for client review and approval.
• Incorporate survey information.
• Coordinate with Civil Engineer and Landscape Architect.
• Review and coordinate the foundation recommendations provided in the Geotech
report.
• Meet with Client to review and finalize direction on selected plan.
LumpSum.................................................................................... $6,875.00
6.2 Design Development Phase (Provided by Subconsultant PGAL)
(New Restroom Facility Only)
• Based on approval of the Schematic Design phase, the design team shall include
develop the selected floor plan option. This phase shall also identify major electrical,
plumbing and structural requirements.
• Coordinate with Civil Engineer and Landscape Architect.
• Provide general fixture/furnishing layout and finish material selections with a finish
board.
• Meet with Client to review and finalize direction on all design elements.
• Client -directed changes to the program or layout after the Design phase is approved
will be an add service.
LumpSum.................................................................................. $13,750.00
CRINEN •1FIQ44PSON & ASSOCIM7ES INC
Mr. Dincer Ozaydin
CTA Proposal No. 2024-C11.062 (Revised)
April 26, 2024
6.3 Planning & Zoning Phase (Provided by Subconsultant PGAL)
(New Restroom Facility Only)
During this phase of development, plans will be submitted to the City Planning & Zoning
Division for DRC review and approval. Preparation of applications and submittal process
are by CTA under separate tasks.
LumpSum.................................................................................. $12, 750.00
6.4 Construction Document Phase (Provided by Subconsultant PGAL)
(New Restroom Facility Only)
• Based on approval of the Design Development phase, construction documents will
complete the coordination and details required for permitting and bidding of the
architecture, structural, electrical, plumbing and interior finish documents.
• Meet with Client to review and finalize any open construction document items.
LumpSum.................................................................................. $20,625.00
6.5 Bid & Permit Phase (Provided by Subconsultant PGAL)
(New Restroom Facility Only)
• Upon completion of the Construction Documents phase, plans will be signed/sealed
and prepared for permit review by the Building Department.
• Once all review comments have been satisfied, the plans will be submitted for bid to
contractors selected by the Client.
• PGAL will assist the Client with the review of the bids and provide supplemental
instruction / clarification of the construction documents and consider requests for
substitutions.
LumpSum.................................................................................... $3,438.00
6.6 Construction Phase (Provided by Subconsultant PGAL)
(New Restroom Facility Only)
This phase will include the following:
• Attendance at one pre -construction meeting.
• Attendance at Owner -Architect Contractor construction meetings every other week.
• Review of contractor shop drawings and information submittals.
• Respond to "Requests for Information" (RFI) from contractor.
• Resolve design discrepancies and issue clarification document.
• Provide bi-weekly site visits for general observation of the work.
• Provide a substantial and final completion observation and report.
LumpSum.................................................................................. $17,188.00
SUB -TOTAL FOR ARCH. FOR NEW RESTROOM FACILITY ........ $74,626.00
CRIUM-I iQMPSQN &ASSOCIMES INC
Mr. Dincer Ozaydin
CTA Proposal No. 2024-C11.062 (Revised)
April 26, 2024
VII. ARCHITECTURAL SERVICES FOR CONVERTED STORAGE FACILITY
7.1 Structural Evaluation of Storage Facility (Provided by Subconsultant PGAL)
Task includes structural evaluation of the existing beach side restroom building and
foundation systems. Basic services shall be within the general practice of professional
services and standard of care for architecture and engineering. The structural engineer
will perform a site visit to evaluate existing conditions, visibly inspect the building,
determine the existing foundation system for the building, and prepare a report that will
outline the structural requirements and determine the scope of work necessary to
convert the existing beach side restrooms into a storage facility.
LumpSum.................................................................................... $3,S00.00
7.2 Schematic Design Phase (Provided by Subconsultant PGAL)
(Converted Storage Facility Only)
• Provide schematic plan options for client review and approval.
• Incorporate survey information.
• Coordinate with Civil Engineer and Landscape Architect.
• Review and coordinate the foundation recommendations provided in the Geotech
report.
• Meet with Client to review and finalize direction on selected plan.
LumpSum.................................................................................... $6,875,00
7.3 Design Development Phase (Provided by Subconsultant PGAL)
(Converted Storage Facility Only)
• Based on approval of the Schematic Design Phase, the design team shall include
develop the selected floor plan option. This phase shall also identify major electrical,
plumbing and structural requirements.
• Coordinate with Civil Engineer and Landscape Architect.
• Provide general fixture/furnishing layout and finish material selections with a finish
board.
• Meet with Client to review and finalize direction on all design elements.
• Client -directed changes to the program or layout after the Design phase is approved
will be an add service.
LumpSum.................................................................................. $13,750.00
7.4 Planning & Zoning Phase (Provided by Subconsultant PGAL)
(Converted Storage Facility Only)
During this phase of development, plans will be submitted to the City Planning & Zoning
Division for DRC review and approval. Preparation of applications and submittal process
are by CTA under separate tasks.
LumpSum ....... ............... ................................................ I........... $12,750.00
CRMNAROMPSON & ASSOCIMES INC
Mr. Dincer Ozaydin
CTA Proposal No. 2024-C11.062 (Revised)
April 26, 2024
7.5 Construction Document Phase (Provided bySubconsultant PGAL)
(Converted Storage Facility Only)
• Based on approval of the Design Development Phase, construction documents will
complete the coordination and details required for permitting and bidding of the
architecture, structural, electrical, plumbing and interior finish documents.
• Meet with Client to review and finalize any open construction document items.
LumpSum.................................................................................. $20,625.00
7.6 Bid & Permit Phase (Provided bySubconsultant PGAL)
(Converted Storage Facility Only)
• Upon completion of the Construction Documents phase, plans will be signed/sealed
and prepared for permit review by the Building Department.
• Once all review comments have been satisfied, the plans will be submitted for bid to
contractors selected by the Client.
• PGAL will assist the Client with the review of the bids and provide supplemental
instruction / clarification of the construction documents and consider requests for
substitutions.
LumpSum.................................................................................... $3,438.00
7.7 Construction Phase (Provided bySubconsultant PGAL)
(Converted Storage Facility Only)
This phase will include the following:
• Attendance at one pre -construction meeting.
• Attendance at Owner -Architect Contractor construction meetings every other week.
• Review of contractor shop drawings and information submittals.
• Respond to "Requests for Information" (RFI) from contractor.
• Resolve design discrepancies and issue clarification document.
• Provide bi-weekly site visits for general observation of the work.
• Provide a substantial and final completion observation and report.
LumpSum.................................................................................. $17,188.00
SUB -TOTAL FOR ARCH. FOR CONVERTED STORAGE FACILITY.... $78,126.00
Vill. EXTERIOR_ STRUCTURAL ENGINEERING SERVICES FOR BREAKAWAY SEAWALL AND
CROSSOVER
8.1 Structural Design and Permit Documents (Provided bySubconsultant MUE Engineers)
Services include:
• Structural Engineering services include structural design of a breakaway site
retaining wall.
• Structural design of an ADA compliant wood framed dune cross over structure.
LumpSum.. ......................... ...................................................... $11,500.00
SUB -TOTAL FOR EXTERIOR STRUCTURAL ................ I............ $11,500.00
Mr. Dincer Ozaydin
CTA Proposal No. 2024-C11.062 (Revised)
April 26, 2024
Page 11
IX. PROJECT MANAGEMENT
9.1 Project Management During Design and Bid Period (CTA Task No. 24070A)
Provide oversite of project to ensure timeline and direction desired by client are
followed as closely as possible. Management and direction of design disciplines. Attend
meetings and provide coordination between client and design team.
Hourly, Not -to -Exceed ................. ......................................... ..... $15,000.00
9.2 Proiect Management During Construction Period (CTA Task No. 24070B)
Provide oversite of project to ensure timeline and direction desired by client are
followed as closely as possible. Management and direction of design disciplines. Attend
meetings and provide coordination between client and design team.
Hourly, Not -to -Exceed ...................................................... ......... $15,000.00
SUB -TOTAL FOR PROJECT MANAGEMENT...........................$30,000.00
X. REIMBURSABLES PERMIT FEES AND MISC. ADDITIONAL DESIGN FEES
10.1 Reimbursable (CTA Task No. 31140)
Reimbursable expenses such as permit fees, courier services, FeclEx, progress prints,
permit prints, or other clerical/design expenses for any active project being performed
for Dania Beach by Craven Thompson & Associates, Inc. This task shall also include fees
if authorized by owner for permit applications and additional miscellaneous design.
Estimated Budget...................................................................... $20,000.00
SUMMARY OF FEES
1.
SURVEYING SERVICES.......................................................................
$16,000.00
II.
GEOTECHNICAL SERVICES................................................................
$16,720.00
III.
ENVIRONMENTAL SERVICES............................................................. $72,000.00
IV.
CIVIL ENGINEERING SERVICES........................................................... $60,500.00
V.
SITE PLAN PROCESSING LANDSCAPE ARCHITECTURAL
AND IRRIGATION SERVICES...............................................................
$91,200.00
VI.
ARCHITECTURAL SERVICES (RESTROOM FACILITY) .............................
$74,626.00
VII.
ARCHITECTURAL SERVICES (STORAGE FACILITY) ................................
$78,126.00
Vill.
EXTERIOR STRUCTURAL ENGINEERING SERVICES FOR
BREAKAWAY SEAWALL AND CROSSOVER .........................................
$11,500.00
IX.
PROJECT MANAGEMENT..................................................................
$30,000.00
X.
REIMBURSABLES PERMIT FEES AND MISCELLANEOUS
ADDITIONAL DESIGN FEES................................................................
$20,000.00
GRANDTOTAL................................................................................
$470,672.00
CRAMN•1ROMPSON&ASSOCIMES INC.
Mr. Dincer Ozaydin
CTA Proposal No. 2024-C11.062 (Revised)
April 26, 2024
Page 12
Items Not Included
1. Site planning, Architectural, structural, mechanical, plumbing, and electrical design of storage facility
structure. Once structural evaluation determines it is feasible to use existing structure an additional
scope of fees required will be provided for the previously mentioned disciplines.
2. City Council submissions and Attendance
Optional Additional Services
1, Specialty Engineering other than that provided above
2. Phased permit submittals
3. Low voltage (empty raceways included)
4. FF&E selection and procurement
5. Lighting controls (beyond building code minimum)
6. LEED certification and related fees
7. Wet pipe suppression systems
R. Value engineering
9. Permit Expediting Services
10. As-Builts
TERMS
TERMS OF THIS CONTRACT SHALL FOLLOW THAT OF THE CURRENTLY ACTIVE
MASTER CCNA CONTRACT BETWEEN THE CITY OF DANIA BEACH AND CRAVEN
THOMPSON & ASSOCIATES, INC.
LIABILITY
PURSUANT TO F.S. 558.0035, AN INDIVIDUAL EMPLOYEE OR AGENT MAY NOT BE
HELD INDIVIDUALLY LIABLE FOR NEGLIGENCE.
Acceptance
This proposal and fee schedules are based on acceptance within 30 days of the date of preparation. If
not accepted by you within that time period, we reserve the right to re-evaluate the terms and
conditions contained herein.
The above will be subject to the terms and conditions specified in the Contract Documents, RFQ No. 20-
005, Architectural, Surveying, Landscape Architecture Consulting Services. If the proposed work and
fees contained herein are agreeable with you, please provide a Purchase Order and a Notice to Proceed.
Sincerely,
CRAVEN THOMPSON & ASSOCIATES, INC.
� l�l° 6✓
LEONARD (ZAACH) GAMBLE, P.E.
Senior Engineer
LZG/tg
CIPIEN-IRO i1PSON & ASSQCIMES INC.