HomeMy WebLinkAboutInv# Pay App 13 - Burkhardt Construction - 07/17/2025Burkhardt Construction, Inc.
515 Palm St
West Palm Beach, Florida 33401
Project: 2408 - CW Thomas Park
800 NW 2nd St
Dania Beach, Florida 33004
Phone: (561) 659-1400
Prime Contract Change Order #006: DEDUCT "BILLED CO'S" PER CODB
REQUEST
TO:City of Dania Beach
100 W Dania Beach Boulevard
Dania Beach, Florida 33004
FROM:Burkhardt Construction, Inc.
515 Palm Street
West Palm Beach Florida 33401
DATE CREATED:7/ 09 /2025 CREATED BY:Brandon Rhodes (Burkhardt Construction, Inc.)
CONTRACT STATUS:Approved REVISION:0
REQUEST RECEIVED
FROM:
LOCATION
DESIGNATED REVIEWER: REVIEWED BY:
DUE DATE: REVIEW DATE:07/10 /2025
REFERENCE: CHANGE REASON:
EXECUTED: No SCHEDULE IMPACT:
ACCOUNTING METHOD: Amount Based CONTRACT FOR: 1:CW Thomas Park PO #2024-00000271
FIELD CHANGE: No TOTAL AMOUNT: ($56,066.78)
DESCRIPTION:
OWNER'S CONTINGENCY TO BE BILLED IN SEPERATE PAY APP / ACCOUNT.
ATTACHMENTS:
CHANGE ORDER LINE ITEMS:
PCCO #006
#Cost Code Description Type Amount
1 17-01701 - Contingency
DEDUCT 35.3 "FROM PREVIOUS APPLICATION" FOOTBALL FIELD AND
BASKETBALL CT - INSTALL MIRAFI RS4801 GEOGRID FABRIC TO EXTEND
THE LIFESPAN OF THESE SURFACES
Commitment ($54,227.50)
2 17-01701 - Contingency DEDUCT 35.4 "FROM PREVIOUS APPLICATION" BCI MANAGEMENT FEE
(5% PER CONTRACT)Commitment ($1,839.28)
Subtotal:($56,066.78)
Grand Total:($56,066.78)
The original (Contract Sum)$ 21,354,322.35
Net change by previously authorized Change Orders ($799,311.05)
The contract sum prior to this Change Order was $ 20,555,011.30
The contract sum will be decreased by this Change Order in the amount of ($56,066.78)
The new contract sum including this Change Order will be $ 20,498,944.52
The contract time will not be changed by this Change Order
Burkhardt Construction, Inc.page 1 of 2 Printed On: 7/10/ 2025 12 :51 PM
PCCO #006