HomeMy WebLinkAboutInv# 86975 - CALVIN, GIORDANO & ASSOCIATES, INC. - 06/30/2021CITY OF DANIA BEACH (820)Invoice number 86975 Invoice date 06/30/2021 Page 1 of 11 - Oaks Townhomes R/W Permit - S/W Construction -- coordination with CGA Construction Team and the Contractor concerning the sidewalk -- no approved detail in the plans nor base or subbase requirements; coordination with CD on how to proceed 06/16/2021 0.50 150.00 75.00 - Discussion with Transystems with PSD to discuss the weight limit of the bridge at NW 1st Street and Bryan Road and provided information to PSD for them to further discuss the sign placements 06/16/2021 0.50 150.00 75.00 - drove through Fort Lauderdale and passed by a few bridges to check if they had maximum load signs; correspondence with CGA Traffic Engineer and Engineering Director concerning weight limit for the City bridge at NW 1st St and Bryan Road 06/10/2021 1.25 150.00 187.50 - Taylor Lane -- picked up the title searches from Paramount Title Company 06/10/2021 1.00 150.00 150.00 06/09/2021 0.75 150.00 112.50 06/09/2021 0.25 150.00 37.50 - Signs for the Bridge on NW 1st Street near Bryan Road -- correspondence with PSD on the loading maximum for the bridge - went to SW 40th Ave to check the ROW pavement restoration; went over the plans with the Contractor concerning the existing and proposed sidewalk in the ROW - NW 1st Street and Bryon Road bridge -- correspondence with Eric Reid on how to proceed with the maximum limit signs for the bridge 06/04/2021 0.25 150.00 37.50 - Oaks Place Townhomes -- coordination with CGA inspector and the Contractor on finishing the pavement restoration -- allowed them to continue working to complete the job; further correspondence with the Contractor indicating that it is not apparent that the project had been completed 06/04/2021 0.50 150.00 75.00 General Project Supervision Project Manager (IV) Heidi B. Henderson Date Hours Rate Billed Amount Labor 10-101 ENGINEERING-ROADWAY Billing period through June 30, 2021 CGA PM: Jenna Martinetti PO# 2019-00000168 Email: Sabino, Deborah E. <dsabino@daniabeachfl.gov>, ap@daniabeachfl.gov CC: Lajoie, Corinne <clajoie@daniabeachfl.gov> CC: Dincer A. Ozaydin <dozaydin@daniabeachfl.gov> CC: AJohnson@daniabeachfl.gov CITY OF DANIA BEACH (820) ATTN: FINANCE DEPT 100 W. DANIA BEACH BLVD DANIA BEACH, FL 33004 Invoice number 86975 Date 06/30/2021 Project 192777 DANIA BEACH MISCELLANEOUS ENGINEERING SERVICES APPROVED BY DEPUTY DIRECTOR Date 06/30/2021 Invoice number 86975CITY OF DANIA BEACH (820) 192777 DANIA BEACH MISCELLANEOUS ENGINEERING SERVICESProject CITY OF DANIA BEACH (820)Invoice number 86975 Invoice date 06/30/2021 Page 2 of 11 06/03/2021 3.00 150.00 450.00 06/02/2021 0.50 150.00 75.00 - coordination on ROW inspection 20-1897; Assisted to Applicant for the Request for Extension on Permit No. 20-00001260; correspondence with Emuna Construction on the status of the repaving - coordination for PW inspections for ROW permit 20-1898 and 20-1897 06/01/2021 0.25 150.00 37.50 General Project Supervision Project Manager (IV) Heidi B. Henderson Date Hours Rate Billed Amount Labor 10-107 ENGINEERING PROGRAM MANAGEMENT SE 2nd Ave - review of change order for paving outside limits and boring services. 06/14/2021 1.00 150.00 150.00 General Project Supervision Project Manager (IV) Jenna Martinetti 06/28/2021 0.25 150.00 37.50 - coordination with CD on the stop work order to Crown Castle on SE 2nd Ave due to the WM project General Project Supervision Project Manager (IV) Heidi B. Henderson Date Hours Rate Billed Amount Labor Phase subtotal 187.50 10-104 ENGINEERING-WATER - Atlantica at DB -- correspondence with Applicant; reviewed the drainage plan and prepared the drainage letter to BC for their SWM permit; forwared the letter to Dincer for his signature 06/22/2021 0.50 150.00 75.00 General Project Supervision Project Manager (IV) Heidi B. Henderson Date Hours Rate Billed Amount Labor 10-103 ENGINEERING-STORM SEWER -- coordination with the Contractor for the sidewalk inspection and plan approval / acceptable details for SW 40th Ave 06/17/2021 0.25 150.00 37.50 General Project Supervision Project Manager (IV) Subtotal 5.25 787.50 Heidi B. Henderson Date Hours Rate Billed Amount Labor Phase subtotal 787.50 10-101 ENGINEERING-ROADWAY Date 06/30/2021 Invoice number 86975CITY OF DANIA BEACH (820) 192777 DANIA BEACH MISCELLANEOUS ENGINEERING SERVICESProject CITY OF DANIA BEACH (820)Invoice number 86975 Invoice date 06/30/2021 Page 3 of 11 06/17/2021 2.00 150.00 300.00 - Engineering email, program management, and pre-con coordination -- scheduled a pre-con for PERMIT# 21- 0696 (GRIFFIN RD & SW 40TH AVE) and coordination with PSD and the Contractor and his team and confirmation that they can commence construction next week 06/17/2021 1.00 150.00 150.00 - Engineering email, program management, and inspection coordination -- scheduled a pre-con for PERMIT# 21-0696 (GRIFFIN RD & SW 40TH AVE) and coordination with PSD and the Contractor and his team; - coordination with Multi-signs for their two sign inspections; coordination for the PW final inspection for 20-0509 -- PSD had no record of the inspection and / or plans; 06/17/2021 1.00 150.00 150.00 06/16/2021 0.25 150.00 37.50 - inspection coordination with CGA for permits 20-036, 20-0861 - coordination with the CGA inspection team, the Contractor, and the CD on the new sidewalk in the ROW for SW 40th Ave Oaks Place Townhomes; they called inspection but do not have an approved detail; provided direction on how to proceed - Engineering email; program management; inspection coordination for 20-2116, 21-0035, 21-0861; picked up permits for the 3 inspection requests for 20-2116, 21-0035, 21-0861 from PSD 06/15/2021 2.00 150.00 300.00 06/15/2021 0.50 150.00 75.00 - Engineering email; followed up with Community Development for ROW permit 20-1920; followed up with Manny on the review of the driveway details 06/14/2021 0.25 150.00 37.50 - Engineering email; program management -- followed up with SW 40th Ave Oaks Place pavement restoration; found permit 16-2150 per ATTs request and provided them a copy; updated PSD permit log; sent out atlases 06/10/2021 2.25 150.00 337.50 - prepared atlases for 1301 S. Federal Hwy and Dania Beach Blvd and Bryan Road area 06/09/2021 0.50 150.00 75.00 - Engineering email and program management -- assisted the Applicant on 21-0083 to schedule a form board building inspections; assisted the Applicant to schedule a building inspection for Bldg Paving Subgrade For permit # 2021-0205 06/09/2021 1.50 150.00 225.00 06/08/2021 2.00 150.00 300.00 - Engineering email; program management-- finalized scheduled pre-con for Permit# 21-0486 (Dania Elementary); coordination with Residence, CGA, and CD for the Driveway Inspection for 21-0083; picked up permit 21-0083 at CD; correspondence with ATT to locate permit 16-2150 - Engineering email; program management -- coordination of pre-con for PERMIT# 21-0486 and Dania Pattoni; received atlas request / design ticket and sent to be logged and logged request; correspondence with Applicant on City details; followed back up with CD on driveway details; inspection coordination 06/07/2021 2.00 150.00 300.00 - Engineering email and program management -- coordination on pre-con for 21-0468; coordination on permit 20-1898 since there are no more handholes in stock and the sidewalk was not repaired: confirmed with CD on how to proceed and notified applicant; called back Applicants that had left messages; notified Records of atlases sent for the large FPL request 06/04/2021 1.00 150.00 150.00 - Program management; engineering email -- coordination on ROW inspections and Change of Contractor with Community Development (CD), Contractor, and Inspector for 20-1898 and 20-1897; correspondence and scheduling for pre-con for Dania Panattoni; continued coordination on both 20-1898 and -1897 for their inspection and CD requirements; picked up permits from CD; logged permits at PSD General Project Supervision Project Manager (IV) Heidi B. Henderson Date Hours Rate Billed Amount Labor 10-107 ENGINEERING PROGRAM MANAGEMENT Date 06/30/2021 Invoice number 86975CITY OF DANIA BEACH (820) 192777 DANIA BEACH MISCELLANEOUS ENGINEERING SERVICESProject CITY OF DANIA BEACH (820)Invoice number 86975 Invoice date 06/30/2021 Page 4 of 11 06/28/2021 0.25 150.00 37.50 06/25/2021 1.00 150.00 150.00 - coordination on the Dania Cove Drainage project building permit and the Ocean Park Drainage project building department; coordination with PSD GIS concerning atlas request - Dania Cove -- submitted responses to Bldg driveway permits; submitted ROW permit 06/24/2021 1.00 150.00 150.00 - Coordination with CD on current active City projects -- Dania Cove and SE 2nd Ave Watermain projects; call with Reviewer and EOR 06/23/2021 1.00 150.00 150.00 - received large atlas request; logged request; requested design ticket and coordination with PSD GIS to prepare the atlases, etc. 06/23/2021 0.25 150.00 37.50 06/23/2021 0.50 150.00 75.00 - Sent atlas to Applicant for W&S Verification - Permit No. 20-2136; correspondence with Applicant and PSD to confirm WWTP info - inspection coordination with ATT and inspector for 16-00002150 ATT 7EA80058N; went to PSD to pull the permit to clarify information 06/22/2021 0.50 150.00 75.00 06/22/2021 1.00 150.00 150.00 06/22/2021 0.50 150.00 75.00 - inspection coordination for Permit # 21-0014 Engineering Inspection - Pressure Test (CMC) between inspector and CD and PSD; Darren confirm that he will handle the inspection and that CGA does not need to be present - reviewed the water and sewer applications (HRS, BC, FDEP Water and Wastewater Applications) and the Water and Sewer Plan for Atlantica at Dania Beach; correspondence with the Applicant and forwarded it to Dincer for signatures - permit coordination; program management -- coordination with CD concerning pending Dania Cove permits; coordinated team call; discussion with EOR concerning comments; discussion with CD concerning comments and best way to proceed 06/21/2021 0.50 150.00 75.00 06/21/2021 1.00 150.00 150.00 06/21/2021 0.25 150.00 37.50 - Coordintion with Castillo Engineering concerning the FDOT Project 436196-1 along SW 40th Ave; provided Oaks Place info and discussion of FDOT pre-con meeting 06/21/2021 0.25 150.00 37.50 - Assisted Kimley-Horne concernng Tru Hilton concerning the FDOT After-the-Fact permit close out - inspection coordination for permit 16-00002150 ATT 7EA80058N and Permit # 21-0014 Engineering Inspection - Pressure Test (CMC) - Engineering email; program management -- followed up with emails and scheduled times to discuss the HRS Application for Atlantica Dania Beach, OASIS Development, and Tru Hilton FDOT Utility permit certification 06/18/2021 0.25 150.00 37.50 - prepared atlas for Permit No. 20-2136 CD request to confirm utility provider; requested logging of request; correspondence with PSD and Requestor 06/17/2021 0.50 150.00 75.00 - Engineering email, program management, and ROW permit tracking -- contacted Contractor for he inspection request for 20-0509 and had him drop off plans at PSD; picked up ROW permit at CD; met with Manny to discuss outstanding items; dropped off permits at PSD and picked up permit; logged permits General Project Supervision Project Manager (IV) Heidi B. Henderson Date Hours Rate Billed Amount Labor 10-107 ENGINEERING PROGRAM MANAGEMENT Date 06/30/2021 Invoice number 86975CITY OF DANIA BEACH (820) 192777 DANIA BEACH MISCELLANEOUS ENGINEERING SERVICESProject CITY OF DANIA BEACH (820)Invoice number 86975 Invoice date 06/30/2021 Page 5 of 11 - correspondence with CGA's Engineering Director and Electrical Engineer concerning the cost estimate; provided the cost estimate to PSD; further correspondence concerning the additional of photocell and light timers. 06/14/2021 2.00 150.00 300.00 - corrdination with CGA's Electrical Engineer on the current design for the medians and how we need to modify it moving forward; coordination call with Fernando on the status of the project 06/11/2021 2.00 150.00 300.00 - Met with PSD and CGA's Electrical Engineer to go over Phase 1 and Phase 2 scope and deadlines; coordination with Christmas Lights Designers for the Wattage necessary for the medians; requested FDOT as- built info again 06/10/2021 2.00 150.00 300.00 - Continued the review to assess how the machine will be situated at locations T, U, W; went over the additional light pole locations that require GFIs 06/09/2021 1.00 150.00 150.00 - went through all 23 sites and assessed how the directional bore machine will be situated, electrical panel / transformer, and recepticle with CGA's Electrical Engineer; went over the additional light poles that require GFIs 06/08/2021 5.00 150.00 750.00 General Project Supervision Project Manager (IV) Heidi B. Henderson Date Hours Rate Billed Amount Labor 10-167 CITY FDOT UTILITY PERMIT FOR HOLIDAY LIGHTS Inv 051421 Title seaches TITLE SERVICES 2,050.00 06/30/2021 PARAMOUNT TITLE SERVICES, INC. Markup 25.00% 2,050.00 512.50 2,562.50 2,562.50 Rate Basis Markup Amount Subtotal 2,050.00 Units Cost Rate Cost Amount Billed Amount Expense 06/29/2021 0.75 150.00 112.50 - Engineering email -- responded to various emails and coordination with PSD Staff to address the emails such as atlas requests, determing if the pre-con for Schedule a PreCon for Permit 2021-00000338 - USI # 2560 was necessary; and requesting PS information for FDEP sanitary sewer permit application - Saratoga Crossing III - coordination on inspection 2021-00000083; coordination with ATT and CGA for 16-00002150 ATT 7EA80058N 06/28/2021 0.25 150.00 37.50 - coordination to schedule a PreCon for Permit 2021-00000338 - USI # 2560 06/28/2021 0.25 150.00 37.50 - coordination with Applicant and PSD to obtain pump station data for their BC W WW permit General Project Supervision Project Manager (IV) Subtotal 30.00 4,500.00 Heidi B. Henderson Date Hours Rate Billed Amount Labor Phase subtotal 7,062.50 10-107 ENGINEERING PROGRAM MANAGEMENT Date 06/30/2021 Invoice number 86975CITY OF DANIA BEACH (820) 192777 DANIA BEACH MISCELLANEOUS ENGINEERING SERVICESProject CITY OF DANIA BEACH (820)Invoice number 86975 Invoice date 06/30/2021 Page 6 of 11 Create E1. Revise. 06/24/2021 1.00 95.00 95.00 06/17/2021 2.50 95.00 237.50 Revise plans and notes Fdot utility. Revise light Pole plans. 06/16/2021 5.50 95.00 522.50 Calculations for cost estimate 06/11/2021 1.00 95.00 95.00 Revie plans per commetnts. Create a PH I Set whcih includes Light Pole locations. 06/10/2021 3.75 95.00 356.25 Revise plans per comments. Create Light Pole plans for City meeting 06/09/2021 8.00 95.00 760.00 Revise plans per utilities. Revise plans per comments. 06/08/2021 3.00 95.00 285.00 Add utility information for for plans for Holiday Lighting 06/07/2021 7.00 95.00 665.00 CAD Drafting/Design CADD Technician Katharine J. Kupsky Review final drawings. Set up drawing for FDOT permiting. DSS drawings. 06/29/2021 0.50 150.00 75.00 Field visit to verify existing pole receptacle installations with CODB PW electrician. Electrical design 06/23/2021 6.00 150.00 900.00 Holiday Lights pole design 06/21/2021 1.00 150.00 150.00 Start re-doing electrical requirements to holiday light median per CODB lighting supplier. Start pole holiday lighting plan mark-ups. Start revising cost estimates 06/11/2021 5.00 150.00 750.00 Meeting with client. Cost estimates for the streetlight poles and median holiday lights. Start marking streetlight poles. 06/10/2021 12.00 150.00 1,800.00 Coordinate all directional boring. Mark-up drawings. 06/08/2021 6.00 150.00 900.00 Engineering Design Project Manager (IV) Subtotal 30.50 4,575.00 Jorge R. Cervantes - reviewed Phase 1 plans; reviewed status of the project; submitted for the FDOT Utility permit 06/29/2021 2.50 150.00 375.00 - coordination with the Electrical Engineer for Phase 1 plans; coordination with PSD to access the FDOT access panel on the light pole; coordination with Holiday Lighting Contractor 06/23/2021 1.00 150.00 150.00 General Project Supervision Project Manager (IV) Subtotal 15.50 2,325.00 Heidi B. Henderson Date Hours Rate Billed Amount Labor 10-167 CITY FDOT UTILITY PERMIT FOR HOLIDAY LIGHTS Date 06/30/2021 Invoice number 86975CITY OF DANIA BEACH (820) 192777 DANIA BEACH MISCELLANEOUS ENGINEERING SERVICESProject CITY OF DANIA BEACH (820)Invoice number 86975 Invoice date 06/30/2021 Page 7 of 11 06/15/2021 3.00 90.00 270.00 Permit # 21-0083 Inspected ROW driveway apron. Inspection passed. Permit # 20-00001168 Oak Townhomes - Was on site inspecting Lamar Enterprises paving the southbound lane of SW 40th Ave. around MH-0. Checked mix of Asphalt and Asphalt temperature. Both were good. Crew laid 2" of Asphalt. 06/09/2021 4.00 90.00 360.00 Checked on MOT ahead of paving. Contractor waiting on MOT crew. 06/04/2021 1.00 90.00 90.00 Permit - 20-00001168 - Drove to site to check MOT ahead of paving. Paving rescheduled again for this coming Friday 6.4.21 Permit - 20-1898 - Inspected ROW of directional boring. Inspection Failed. Permit - 20-1897 Inspected ROW of directional boring. - Inspection Failed. 06/02/2021 4.00 90.00 360.00 Permit 20-00001168 Drove to site due to crew supposed to be paving SW 40th Ave. today. Crew postponed paving until tomorrow 6.2.21 due to rainy weather. 06/01/2021 1.00 90.00 90.00 Field Inspection & Observation Inspector Charles J. Oddo 06/04/2021 4.00 90.00 360.00 Oaks TowHomes Contractor was paving north bound on S W 40th Ave. by M - H # 8 and M- H # 0. Contractor paved south bound by M - H # 8 only, did not have enough asphalt to complete job. I stayed extra hours waiting for crew to finish. Contractor stopped work at 5:30 PM. Contactor could not provide me with a asphalt ticket, an did not have it on site. Field Inspection & Observation Inspector Carlos A. Diaz Date Hours Rate Billed Amount Labor 50-100 CONSTRUCTION OBSERVATON 06/29/2021 2.00 95.00 190.00 Revise City Holiday lighting plans for FDOT submittal. Revise plans. 06/25/2021 0.50 95.00 47.50 CAD Drafting/Design CADD Technician Subtotal 34.25 3,253.75 Katharine J. Kupsky Date Hours Rate Billed Amount Labor Phase subtotal 10,153.75 10-167 CITY FDOT UTILITY PERMIT FOR HOLIDAY LIGHTS Date 06/30/2021 Invoice number 86975CITY OF DANIA BEACH (820) 192777 DANIA BEACH MISCELLANEOUS ENGINEERING SERVICESProject CITY OF DANIA BEACH (820)Invoice number 86975 Invoice date 06/30/2021 Page 8 of 11 R/W permits inspection coord. 06/18/2021 0.50 175.00 87.50 06/17/2021 0.50 175.00 87.50 R/W permits inspection coord. 06/11/2021 0.50 175.00 87.50 R/W inspection cpoord. - Oaks Townhomes paving R/W inspection cpoord. - Oaks Townhomes paving coord. / scheduling 06/10/2021 0.50 175.00 87.50 R/W inspection cpoord. - AT&T 06/09/2021 0.50 175.00 87.50 R/W inspection cpoord. - AT&T 06/08/2021 0.50 175.00 87.50 Oaks Townhomes R/W permit paving inspection / MOT coord. 06/04/2021 0.75 175.00 131.25 R/W permit inspections coord.; inspection results looging coord. 06/03/2021 1.25 175.00 218.75 R/W permits inspections coord. / scheduling 06/02/2021 0.50 175.00 87.50 R/W permits inspections coord. / scheduling 06/01/2021 0.75 175.00 131.25 General Project Supervision Director Eng (V) Robert Mcsweeney ROW Inspection for permit # 16-2150. All Handholes located at this time. 06/29/2021 1.00 90.00 90.00 06/22/2021 3.00 90.00 270.00 Permit#20-2116 Went to site to perform a pressure test of new 2" HDPE sewer system. Was postponed until 1pm then I was told we don't have to be there. Permit#16-2150 Inspected neighborhood for ATT handholes. Oaks Townhomes - 20-1168 Checked slopes of sidewalks poured the day before and observed contractor saw cut sidewalks. permit - 21-0035 Inspected footer for new signage. Footer failed due to not correct dimensions. Permit - 21-0861 - Inspected footer for new signage. Inspection passed. Permit - 20-2116 Sewer project. Inspected site checking on directional bore project. Crew completed directional boring. 06/16/2021 4.00 90.00 360.00 Permit #20-00001168 Oaks Townhomes Inspected Asphalt final and temporary striping of Asphalt. - Inspection passed. Checked Sidewalk forms on west side of SW 40th Ave. Forms good. Checked concrete mix for Sidewalks. mix good. Crew poured Sidewalk on west side of SW 40th Ave. Waited on concrete trucks. Field Inspection & Observation Inspector Subtotal 21.00 1,890.00 Charles J. Oddo Date Hours Rate Billed Amount Labor 50-100 CONSTRUCTION OBSERVATON Date 06/30/2021 Invoice number 86975CITY OF DANIA BEACH (820) 192777 DANIA BEACH MISCELLANEOUS ENGINEERING SERVICESProject CITY OF DANIA BEACH (820)Invoice number 86975 Invoice date 06/30/2021 Page 9 of 11 06/30/2021 0.25 175.00 43.75 R/W permit inspection / coord. 06/29/2021 0.75 175.00 131.25 R/W permit inspection / coord. 06/23/2021 0.50 175.00 87.50 R/W permit inspection coord. 06/21/2021 1.00 175.00 175.00 R/W permit inspection coord. General Project Supervision Director Eng (V) Subtotal 8.75 1,531.25 Robert Mcsweeney Date Hours Rate Billed Amount Labor Phase subtotal 3,781.25 50-100 CONSTRUCTION OBSERVATON Invoice total 22,047.50 Date 06/30/2021 Invoice number 86975CITY OF DANIA BEACH (820) 192777 DANIA BEACH MISCELLANEOUS ENGINEERING SERVICESProject CITY OF DANIA BEACH (820)Invoice number 86975 Invoice date 06/30/2021 Page 10 of 11 99-100 REIMBURSABLES 0.00 0.00 0.00 0.00 0.00 70-101 ENVIRONMENTAL 0.00 0.00 0.00 0.00 0.00 70-100 LANDSCAPE ARCHITECTURE 0.00 0.00 0.00 0.00 0.00 66-100 GOVERNMENTAL SERVICES 0.00 0.00 0.00 0.00 0.00 60-100 PLANNING ASSISTANCE 0.00 0.00 0.00 0.00 0.00 50-100 CONSTRUCTION OBSERVATON 0.00 17,566.25 3,781.25 21,347.50 -21,347.50 31-100 SOFTWARE 0.00 0.00 0.00 0.00 0.00 30-100 DATA TECH & DEV 0.00 0.00 0.00 0.00 0.00 15-100 CEI 0.00 0.00 0.00 0.00 0.00 20-101 FPL EASEMENT-DANIA BEACH MARINA 0.00 1,435.00 0.00 1,435.00 -1,435.00 20-108 SURVEY - MISC ASSISTANCE 0.00 650.00 0.00 650.00 -650.00 20-102 SE 2ND AVE WM EMERGENCY SURVEY & DATUM CONVERSION - SURVEY 0.00 7,997.50 0.00 7,997.50 -7,997.50 10-167 CITY FDOT UTILITY PERMIT FOR HOLIDAY LIGHTS 0.00 11,555.00 10,153.75 21,708.75 -21,708.75 10-122 SE 2ND AVE WM EMERGENCY SURVEY & DATUM CONVERSION - ENG 0.00 8,281.25 0.00 8,281.25 -8,281.25 10-121 LS 7 REHABILITATION 0.00 3,600.00 0.00 3,600.00 -3,600.00 10-120 ELECTRICAL ENGINEERING 0.00 0.00 0.00 0.00 0.00 10-119 FDOT CRA MULTIMODAL PEDESTRIAN SAFETY IMPROVEMENTS 0.00 650.00 0.00 650.00 -650.00 10-118 BRIDGE MAINTENANCE SUPPORT 0.00 1,235.00 0.00 1,235.00 -1,235.00 10-117 43RD TERRACE DRAINAGE 0.00 675.00 0.00 675.00 -675.00 10-116 BEACHFRONT RESTROOM RENOVATIONS 0.00 650.00 0.00 650.00 -650.00 10-115 QUARTERDECK ELEVATOR 0.00 0.00 0.00 0.00 0.00 10-114 UNDERGROUNDING OF UTILITIES AT THE BEACH 0.00 3,635.00 0.00 3,635.00 -3,635.00 10-113 BEACH PARKING LOT DRAINAGE 0.00 775.00 0.00 775.00 -775.00 10-112 SE DRAINAGE IMPROVEMENTS 0.00 1,645.00 0.00 1,645.00 -1,645.00 10-111 US1 TRANSIT IMPROVEMENTS 0.00 700.00 0.00 700.00 -700.00 10-110 LS 10 REHABILITATION 0.00 800.00 0.00 800.00 -800.00 10-109 LS 5 REHABILITATION 0.00 1,175.00 0.00 1,175.00 -1,175.00 10-108 SW 40TH AVE - FDOT 0.00 5,652.50 0.00 5,652.50 -5,652.50 20-100 SW 40TH AVE ROW DEDICATION 0.00 1,042.50 0.00 1,042.50 -1,042.50 10-107 ENGINEERING PROGRAM MANAGEMENT 0.00 101,606.25 7,062.50 108,668.75 -108,668.75 10-106 ENGINEERING-MISC.0.00 5,100.00 0.00 5,100.00 -5,100.00 10-104 ENGINEERING-WATER 22,000.00 19,300.00 187.50 19,487.50 2,512.50 10-103 ENGINEERING-STORM SEWER 21,075.00 25,237.50 75.00 25,312.50 -4,237.50 10-102 ENGINEERING-SANITARY SEWER 28,537.00 31,640.00 0.00 31,640.00 -3,103.00 10-101 ENGINEERING-ROADWAY 44,013.50 71,408.75 787.50 72,196.25 -28,182.75 DANIA COVE DRAINAGE 0.00 1,947.50 0.00 1,947.50 -1,947.50 ENGINEERING-DEVELOPMENT REVIEW 0.00 74,522.50 0.00 74,522.50 -74,522.50 Total 115,625.50 400,482.50 22,047.50 422,530.00 -306,904.50 Description Contract Amount Prior Billed Current Billed Total Billed Remaining Invoice Summary Date 06/30/2021 Invoice number 86975CITY OF DANIA BEACH (820) 192777 DANIA BEACH MISCELLANEOUS ENGINEERING SERVICESProject CITY OF DANIA BEACH (820)Invoice number 86975 Invoice date 06/30/2021 Page 11 of 11 80698Rev 09/30/2020 10,396.25 10,396.25 81298Rev 10/31/2020 9,037.50 9,037.50 82234Rev 11/30/2020 9,497.50 9,497.50 82863Rev 12/31/2020 10,820.00 10,820.00 83551Rev 01/31/2021 10,792.50 10,792.50 84207Rev 02/28/2021 11,468.75 11,468.75 84715Rev 03/31/2021 19,603.75 19,603.75 85492 04/30/2021 21,983.75 21,983.75 86405 05/31/2021 14,158.75 14,158.75 86975 06/30/2021 22,047.50 22,047.50 Total 139,806.25 22,047.50 14,158.75 21,983.75 19,603.75 62,012.50 Aging Summary Invoice Number Invoice Date Outstanding Current Over 30 Over 60 Over 90 Over 120