HomeMy WebLinkAboutInv# 20627489 - KIMLEY HORN & ASSOCIATES, INC - 01/31/2022Please remit payment electronically to:If paying by check, please remit to:
Account Name:KIMLEY-HORN AND ASSOCIATES, INC.KIMLEY-HORN AND ASSOCIATES, INC.
Bank Name and Address:WELLS FARGO BANK, N.A., SAN FRANCISCO, CA 94163 P.O. BOX 932520
Account Number:
ABA#:
2073089159554
121000248
ATLANTA, GA 31193-2520
10pt blank space
CITY OF DANIA BEACH
ATTN: DINCER OZAYDIN
1201 STIRLING ROAD
DANIA BEACH, FL 33004
Federal Tax Id: 56-0885615
For Services Rendered through Jan 31, 2022
Invoice No:20627489
Invoice Date:Jan 31, 2022
Invoice Amount:$22,660.00
Project No:044719010.1
Project Name:LIFT STATION IMPROVEMENT
Project Manager: RATAY, GARY
Client Reference:RFQ 20-008
RESO #2021-056
PO# 2021-00000215
LUMP SUM 096120044719010.12000531044719010.1LS-1NONE
Description Contract Value
%
Complete
Amount Earned
to Date
Previous Amount
Billed
Current Amount
Due
TASK 1- SITE VISIT/FIELD INVESTIGATION 13,800.00 100.00%13,800.00 13,800.00 0.00
TASK 2- FIELD SURVEY 28,500.00 100.00%28,500.00 28,500.00 0.00
TASK 3- 60% DESIGN SUBMISSION 161,200.00 100.00%161,200.00 161,200.00 0.00
TASK 4- 90% DESIGN SUBMISSION 113,300.00 30.00%33,990.00 11,330.00 22,660.00
TASK 5- FINAL DESIGN SUBMISSION 81,500.00 0.00%0.00 0.00 0.00
TASK 6- PERMITTING 28,500.00 0.00%0.00 0.00 0.00
TASK 7- BIDDING SERVICES 6,500.00 0.00%0.00 0.00 0.00
TASK 8- POST DESIGN SERVICES 56,500.00 0.00%0.00 0.00 0.00
PROJECT CONTINGENCY 10,000.00 0.00%0.00 0.00 0.00
Subtotal 499,800.00 47.52%237,490.00 214,830.00 22,660.00
Total LUMP SUM 22,660.00
Total Invoice: $22,660.00 044719010.1
If you have any questions, please contact Casey Crozier at 561-840-0807 or Casey.Crozier@kimley-horn.com 31CGC
kimley-horn.com 8201 Peters Road, Suite 2200, Plantation, FL 33324 954 535 5100
February 17, 2022 KH Project #: 044719010
Dincer Ozaydin
Public Services Deputy Director
City of Dania Beach
1201 Stirling Road
Dania Beach, FL 33004
Re: Design of Lift Station Generators
RFQ No. 20-008
City Purchase Order No. 2021-00000215
KH Invoice# 20627489
Dear Mr. Ozaydin,
Below is a summary of the activities completed from January 1, 2022 through January 31,
2022 for the above-referenced project.
Task 4 – 90% Design Submission
· Holding internal progress meetings to discuss project requirements, design
development, and associated schedule.
· Finalize lift station 11 and 12 calculations for new pump selections.
· Continue coordination with pump manufacturer for proposed pump curves and
dimensional information.
· Continue coordination with electrical engineer on generator and control system design.
· Continue with 90% design development.
· Continue with development of technical specifications.
· Start development of design reports.
Deliverables:
· No deliverables in January
Next Month’s Activities
· Finalize and submit 90% design for review.
·Finalize and submit draft technical specifications for review.
·Start permit coordination and submit permit applications for review.
·Finalize and submit design reports for review.
Mr. Dincer Ozaydin
KH January 2022 Progress Report
February 17, 2022, Page 2
kimley-horn.com 8201 Peters Road, Suite 2200, Plantation, FL 33324 954 535 5100
Should you have any questions or comments regarding our work activities, please call me at
954-535-5112.
Very truly yours,
KIMLEY-HORN AND ASSOCIATES, INC.
Gary R Ratay
Project Manager
K:\FTL_Civil\044 Jobs\044719010 Design of Lift Station Generators\Invoices\January 2022\044719010 Lift Station Generator
Progress Report_January 2022.docx