HomeMy WebLinkAboutInv# 0000148956 - CHEN MOORE & ASSOCIATES - 10/04/2024chen moore and associates 500 W Cypress Creek Road, Suite 600
Fort Lauderdale, Florida 33309
Dincer Ozaydin 954.730.0707 (Phone)
City of Dania Beach 954.730.2030 (Fax)
1201 Stirling Rd
Dania Beach, FL 33004-3643
October 4, 2024
Project No: 22-0090.00045
Invoice No: 0000148956
PO No: 2023-00000057
Project 22-0090.00045 Stormwater Master Plan - RFQ 22-023 - PO 2023-00000057
Professional Services from September 1. 2024 to September 30, 2024
Fee
Billing Phase
Percent To Date Previous Current
Fee Complete Amount Amout Amount
Data Collection
625,725.00
87.8932
549,969.90
547,172.40
2,797.50
Public Involvement
38,510.00
89.7506
34,562.97
34,562.97
0.00
Preparation of Stormwater Model
191,650.00
95.3039
182,650.00
182,650.00
0.00
Preparation of Stormwater Master Plan
161,850.00
61.8273
100,067.50
81,677.50
18,390.00
Implementation of Stormwater Master Plan
33,800.00
0.00
0.00
0.00
0.00
Additional Services
20,000.00
32.709
6,541.79
6,541.79
0.00
Reimbursable Expenses
5,000.00
6.336
316.80
316.80
0.00
Total Fee
1,076,535.00
874,108.96
852,921.46
21,187.50
Total Fee
21,187.50
Total this Invoice $21,187.50
Authorized By: Date: 10/4/2024
Dincer Alcin Ozaydin, P.E
Deputy Public Services Director/City Engineer
J nif Smith, P.E.
***************************************************** Amount Due Upon Receipt of Invoice ***************************************************** Please remit
to: 500 W. Cypress Creek Rd., Ste 600, Ft. Lauderdale, FL 33309 - I - THANK YOU for your business - I -
43iiF2
ore and associates
CITY OF DANIA BEACH
STORMWATER MASTER PLAN
PROJECT PROGRESS REPORT #21
OCTOBER 3, 2024
*Bold text includes updates since last progress report
➢ City of Dania Beach — Client
➢ Chen Moore and Associates— Prime
➢ Stoner and Associates — Surveying
➢ Brizaga — Public Outreach, Sea Level Rise
➢ Cummins Cederberg —Tidal Flood Barriers (Sea Wall) Assessment
➢ Data Collection Memo — completed, submitted to City on January 31, 2023
➢ Field Verification Survey — completed, submitted GIS database December 11th 2023
➢ CRS Floodplain Management Planning Committee (FM PC) — in progress
o CMA coordinating with Earl King on items to include in SWMP for additional CRS points
➢ Existing Conditions Stormwater Model — completed, submitted on January 12, 2024
➢ Future Conditions Stormwater Model with Sea Level Rise — CMA submitted on April 12, 2024;
no comments from City
➢ Basin Ranking/Vulnerability Memo— CMA submitted on April 22nd 2024; City advised 4/23 to
move forward.
➢ Sea Wall Assessment —submitted to City on January 12th 2024
➢ Study Area System Improvement Alternatives — Modeling proposed alternatives for each study
area - ongoing
➢ Public Involvement—
• Kickoff Meeting held June Sot" 2023 to discuss public outreach plan
o Meeting held September �9" 2023 to discuss details for first meeting
o Initial Resident Meeting held November 13th2023, Brizaga distributed minutes and
recordings
o Second Resident Meeting held July 11th 2024, Brizaga distributed minutes and
recordings.
➢ Kickoff meeting with City PM Decembers, 2022
➢ Kick off meeting with City January 18, 2023
➢ Public Outreach kickoff meeting June 30, 2023
➢ Public Outreach coordination meeting September 29, 2023
➢ Initial Public Outreach meeting November 13, 2023
➢ Progress Meeting to review EC Model Results March 28, 2024
*Additional coordination calls occurred throughout project timeline
➢ Analysis of System Improvement Alternatives —October 2024
➢ CIP Conceptual Layout and Cost Estimates —November 2024
➢ Review SWUF— November 2024
➢ SWMP — December 2024
➢ Third (Final) Public Meeting — December 2024/January 2025
City of Dania Beach
CMA
➢ Model Study Area System Improvement Alternatives
➢ Review City CRS data
Subs
➢ Brizaga —Prepare Citizens Guide for City review
2